India’s First High-Speed Rail Service to Begin in 2027
RAILWAYS & METRO RAIL

India’s First High-Speed Rail Service to Begin in 2027

India’s first high-speed rail service will commence in 2027, with the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail corridor scheduled to open first, Railway Minister Ashwini Vaishnaw said. The remaining sections to Mumbai will be opened in phases.

Vaishnaw said 456 km of pier work and 371 km of viaduct construction had been completed by September. About 600,000 noise barriers had been installed along a 299 km stretch, while 9,300 overhead equipment masts had been erected across a 206 km viaduct.

Four mountain tunnels have been excavated, and 5 km of the 21 km Maharashtra tunnel has been completed using the mountain tunnelling method. The corridor includes a 7 km undersea section beneath Thane Creek, forming part of India’s first undersea rail tunnel. Two tunnel boring machines launched in July 2026 from Vikhroli and Sawli are being used for the work.

Civil work has been completed at eight stations, with architectural finishing underway. Work is also progressing at rolling stock depots in Sabarmati, Surat and Thane. The project’s fixed infrastructure, including transformers, mast cross arms, ground wires, protection wires and feeder wires, is being manufactured domestically.

India’s first indigenous bullet trains are also under development. Integral Coach Factory and Bharat Earth Movers are manufacturing the B28 trainset, designed to operate at 280 kmph; its first body frame has been completed and is undergoing structural testing. Track trials are expected by mid-2027, while a B35 trainset designed for 350 kmph is planned as the next development.

Vaishnaw attributed the project’s delayed progress to pending permissions and land acquisition in Maharashtra, which held up work for nearly 2.5 years. The COVID-19 pandemic caused a further two-year interruption, while full construction began in 2021.

India’s first high-speed rail service will commence in 2027, with the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail corridor scheduled to open first, Railway Minister Ashwini Vaishnaw said. The remaining sections to Mumbai will be opened in phases. Vaishnaw said 456 km of pier work and 371 km of viaduct construction had been completed by September. About 600,000 noise barriers had been installed along a 299 km stretch, while 9,300 overhead equipment masts had been erected across a 206 km viaduct. Four mountain tunnels have been excavated, and 5 km of the 21 km Maharashtra tunnel has been completed using the mountain tunnelling method. The corridor includes a 7 km undersea section beneath Thane Creek, forming part of India’s first undersea rail tunnel. Two tunnel boring machines launched in July 2026 from Vikhroli and Sawli are being used for the work. Civil work has been completed at eight stations, with architectural finishing underway. Work is also progressing at rolling stock depots in Sabarmati, Surat and Thane. The project’s fixed infrastructure, including transformers, mast cross arms, ground wires, protection wires and feeder wires, is being manufactured domestically. India’s first indigenous bullet trains are also under development. Integral Coach Factory and Bharat Earth Movers are manufacturing the B28 trainset, designed to operate at 280 kmph; its first body frame has been completed and is undergoing structural testing. Track trials are expected by mid-2027, while a B35 trainset designed for 350 kmph is planned as the next development. Vaishnaw attributed the project’s delayed progress to pending permissions and land acquisition in Maharashtra, which held up work for nearly 2.5 years. The COVID-19 pandemic caused a further two-year interruption, while full construction began in 2021.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

DMRC Invites Bids for Solar-Linked BESS Power Procurement

Delhi Metro Rail Corporation (DMRC) has invited bids for renewable energy from an Inter-State Transmission System (ISTS)-connected generating plant combining a solar photovoltaic (PV) system with a co-located Battery Energy Storage System (BESS). The procurement will be conducted through competitive bidding followed by an e-reverse auction. The last date for submitting online bids is December 10, 2026, at 3 PM. DMRC will open the technical bids on December 11, 2026, at 3 PM. The opening of financial bids and the e-reverse auction will be scheduled after completion of the technical evaluation. ..

Next Story
Infrastructure Energy

Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30. Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code