SJVN Green Energy Commissions 45 MW Solar Project in Assam
POWER & RENEWABLE ENERGY

SJVN Green Energy Commissions 45 MW Solar Project in Assam

SJVN Green Energy (SGEL), a subsidiary of SJVN, has commissioned 45 MW of a 50 MW solar project in Sonitpur district, Assam. The project is part of SGEL’s planned renewable energy development in the state and has begun commercial operations for the commissioned capacity.

In a regulatory filing, SGEL said it had signed a Power Purchase Agreement with Assam Power Distribution Company (APDCL) on February 7, 2024, for supplying 50 MW of solar power from the project. Electricity generated from the commissioned capacity is being supplied to APDCL under the agreement.

APDCL issued the Trial Run Certificate for the commissioned capacity on November 21, 2026. The project also achieved commercial operation on the same date, marking the start of its operational phase under the power supply arrangement.

The project is located in Sitalmari village under the Barsola block of Assam and is being developed in the Dhekiajuli Revenue Sector of Sonitpur district. SGEL had announced the project in March 2024, with an estimated development cost of Rs. 2.91 bn. Power from the facility is contracted to APDCL at a tariff of Rs. 3.92 per unit.

SJVN Chairperson and Managing Director Geeta Kapur had earlier said the company had established a presence in Assam through SGEL. The renewable energy arm was developing three solar projects in the state with capacities of 200 MW, 70 MW and 50 MW, representing a planned combined capacity of 320 MW.

Another SGEL project in Assam is a 70 MW solar facility in Dhubri. Prime Minister Narendra Modi laid the foundation for that project on March 4, 2024, and the facility was subsequently commissioned in January 2026.

SJVN Green Energy (SGEL), a subsidiary of SJVN, has commissioned 45 MW of a 50 MW solar project in Sonitpur district, Assam. The project is part of SGEL’s planned renewable energy development in the state and has begun commercial operations for the commissioned capacity. In a regulatory filing, SGEL said it had signed a Power Purchase Agreement with Assam Power Distribution Company (APDCL) on February 7, 2024, for supplying 50 MW of solar power from the project. Electricity generated from the commissioned capacity is being supplied to APDCL under the agreement. APDCL issued the Trial Run Certificate for the commissioned capacity on November 21, 2026. The project also achieved commercial operation on the same date, marking the start of its operational phase under the power supply arrangement. The project is located in Sitalmari village under the Barsola block of Assam and is being developed in the Dhekiajuli Revenue Sector of Sonitpur district. SGEL had announced the project in March 2024, with an estimated development cost of Rs. 2.91 bn. Power from the facility is contracted to APDCL at a tariff of Rs. 3.92 per unit. SJVN Chairperson and Managing Director Geeta Kapur had earlier said the company had established a presence in Assam through SGEL. The renewable energy arm was developing three solar projects in the state with capacities of 200 MW, 70 MW and 50 MW, representing a planned combined capacity of 320 MW. Another SGEL project in Assam is a 70 MW solar facility in Dhubri. Prime Minister Narendra Modi laid the foundation for that project on March 4, 2024, and the facility was subsequently commissioned in January 2026.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

DMRC Invites Bids for Solar-Linked BESS Power Procurement

Delhi Metro Rail Corporation (DMRC) has invited bids for renewable energy from an Inter-State Transmission System (ISTS)-connected generating plant combining a solar photovoltaic (PV) system with a co-located Battery Energy Storage System (BESS). The procurement will be conducted through competitive bidding followed by an e-reverse auction. The last date for submitting online bids is December 10, 2026, at 3 PM. DMRC will open the technical bids on December 11, 2026, at 3 PM. The opening of financial bids and the e-reverse auction will be scheduled after completion of the technical evaluation. ..

Next Story
Infrastructure Energy

Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30. Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of s..

Next Story
Infrastructure Transport

India’s First High-Speed Rail Service to Begin in 2027

India’s first high-speed rail service will commence in 2027, with the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail corridor scheduled to open first, Railway Minister Ashwini Vaishnaw said. The remaining sections to Mumbai will be opened in phases. Vaishnaw said 456 km of pier work and 371 km of viaduct construction had been completed by September. About 600,000 noise barriers had been installed along a 299 km stretch, while 9,300 overhead equipment masts had been erected across a 206 km viaduct. Four mountain tunnels have been excavated, and 5 km of the 21 km Maharashtra tunnel..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code