L&T Achieves Double Tunnel Breakthrough at Dibang
Equipment

L&T Achieves Double Tunnel Breakthrough at Dibang

Larsen & Toubro (L&T) has achieved a historic double milestone at the Dibang Multipurpose Project (Lot-02) in Arunachal Pradesh. On 28 April 2026, its Heavy Civil Infrastructure team recorded simultaneous breakthroughs in Diversion Tunnel-4 and Diversion Tunnel-5, successfully coordinating two daylighting blasts on the same day amid the difficult geological and environmental conditions of the Lower Dibang Valley.

With this, the project has now completed breakthroughs in three of the five diversion tunnels, following DT-3 in February. The 2880 MW Dibang Multipurpose Project is a critical national hydroelectric initiative. The final blasts were witnessed by Narender Kumar, Executive Director, NHPC, who appreciated the team’s technical resilience and commitment to engineering excellence.

The Lot-02 scope includes a 37-km access road network, two permanent bridges and five diversion tunnels totalling 6.4 km. The milestone reflects the project team’s execution capabilities in complex underground construction and marks further progress towards strengthening India’s sustainable energy infrastructure.

Larsen & Toubro (L&T) has achieved a historic double milestone at the Dibang Multipurpose Project (Lot-02) in Arunachal Pradesh. On 28 April 2026, its Heavy Civil Infrastructure team recorded simultaneous breakthroughs in Diversion Tunnel-4 and Diversion Tunnel-5, successfully coordinating two daylighting blasts on the same day amid the difficult geological and environmental conditions of the Lower Dibang Valley.With this, the project has now completed breakthroughs in three of the five diversion tunnels, following DT-3 in February. The 2880 MW Dibang Multipurpose Project is a critical national hydroelectric initiative. The final blasts were witnessed by Narender Kumar, Executive Director, NHPC, who appreciated the team’s technical resilience and commitment to engineering excellence.The Lot-02 scope includes a 37-km access road network, two permanent bridges and five diversion tunnels totalling 6.4 km. The milestone reflects the project team’s execution capabilities in complex underground construction and marks further progress towards strengthening India’s sustainable energy infrastructure.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement