Rs 4,517.50 billion worth of housing stuck in stages of non-completion
Real Estate

Rs 4,517.50 billion worth of housing stuck in stages of non-completion

Despite the establishment of a regulatory mechanism, countless homebuyers have been left in the lurch by their builders. In fact, Rs 4,517.50 billion worth of housing is currently stuck in various stages of non-completion across top seven cities, according to data from real-estate services company ANAROCK.

Most of these projects do not fall within the ambit of RERA as they were launched years before it was implemented. Also, with many states having diluted the Centre's original RERA rules, homebuyers have only the courts to approach, which is a notoriously tedious task in India.
  
Areas like the National Capital Region (NCR) and Mumbai Metropolitan Region (MMR) collectively account for 72 per cent of the total stuck housing units across the top seven cities worth Rs 3490.1 billion—nearly 77 per cent of the total worth of the stuck projects. In comparison, the main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units with a total worth of Rs 417.7 billion. Bengaluru has less than half the total delayed stock in Pune (86,700 units), while Chennai has the least project delays during this period, with around 8,650 units worth Rs 56.20 billion.
 
“Besides the lack of will of some developers to complete their projects and preference for funds diversion, the tightening credit crunch has been a major factor contributing to this mounting problem,” observes Anuj Puri, Chairman, ANAROCK Property Consultants. “Also, every delayed project results in cost overruns, which compound the funding crunch even further. Lack of project clearances, for whatever reason, also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without requisite approvals in place, resulting in their projects getting stuck.” 
 
As one of the possible solutions to this problem, the government-owned NBCC has been roped in to complete some stalled projects in NCR. This is a significant move that, if applied in larger numbers, can have a real impact. “Moreover, even if NBCC picks up 50 per cent of overall stalled projects, the resultant construction activities would create significant employment for the EWS and LIG segments, which are also the key target segment for affordable housing,” he adds.
 
Additionally, with NBCC undertaking construction, the apprehensions of banks about funding construction would ease. With this provision, even when builders opt for bankruptcy, state authorities would intervene to safeguard the investments of homebuyers. However, buyers are still awaiting their final outcome of these interventions.

Despite the establishment of a regulatory mechanism, countless homebuyers have been left in the lurch by their builders. In fact, Rs 4,517.50 billion worth of housing is currently stuck in various stages of non-completion across top seven cities, according to data from real-estate services company ANAROCK.Most of these projects do not fall within the ambit of RERA as they were launched years before it was implemented. Also, with many states having diluted the Centre's original RERA rules, homebuyers have only the courts to approach, which is a notoriously tedious task in India.  Areas like the National Capital Region (NCR) and Mumbai Metropolitan Region (MMR) collectively account for 72 per cent of the total stuck housing units across the top seven cities worth Rs 3490.1 billion—nearly 77 per cent of the total worth of the stuck projects. In comparison, the main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units with a total worth of Rs 417.7 billion. Bengaluru has less than half the total delayed stock in Pune (86,700 units), while Chennai has the least project delays during this period, with around 8,650 units worth Rs 56.20 billion. “Besides the lack of will of some developers to complete their projects and preference for funds diversion, the tightening credit crunch has been a major factor contributing to this mounting problem,” observes Anuj Puri, Chairman, ANAROCK Property Consultants. “Also, every delayed project results in cost overruns, which compound the funding crunch even further. Lack of project clearances, for whatever reason, also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without requisite approvals in place, resulting in their projects getting stuck.”  As one of the possible solutions to this problem, the government-owned NBCC has been roped in to complete some stalled projects in NCR. This is a significant move that, if applied in larger numbers, can have a real impact. “Moreover, even if NBCC picks up 50 per cent of overall stalled projects, the resultant construction activities would create significant employment for the EWS and LIG segments, which are also the key target segment for affordable housing,” he adds. Additionally, with NBCC undertaking construction, the apprehensions of banks about funding construction would ease. With this provision, even when builders opt for bankruptcy, state authorities would intervene to safeguard the investments of homebuyers. However, buyers are still awaiting their final outcome of these interventions.

Next Story
Real Estate

Dharavi Reimagined Rs 957.9 Billion Makeover

Construction World got a sneak peek at the plan submitted and approved by the Maharashtra Government a few days ago. Here are a few insights from the plan. When we spoke to SVR Srinivas, CEO of the Dharavi Redevelopment Project, last month, the plans were still under wraps. Today, with the development blueprint in hand, the vision is beginning to take shape—with timelines, phases, and goals now clearly defined. Imagine Dharavi in 2031 — no longer a crowded slum but a thriving, green, and modern community with wide walkways, clean parks, and fast metro connections. This dream is becomi..

Next Story
Real Estate

Tall Expectations

Mumbai’s World Trade Centre Tower 1, completed in 1970, marked the start of tall building construction in India, going by the Council on Tall Buildings & Urban Habitat’s definition of tall buildings as structures with a height of at least 150 m. More than half a century later, the country has barely 273 tall buildings by the same definition, according to the CBRE report Sky is the Limit: Rise of Tall Buildings in India.Mumbai remains the centre of tall building construction in India, notes Sailesh Mahimtura, Chairman & Managing Director, Mahimtura Consultants, a fact corrobora..

Next Story
Real Estate

Cool Office

In a city clogged by traffic and long commutes, WoCO One emerges as a sustainable, commuter-friendly workplace. Spread across 3.6 acre, WoCO One (World of Cool Offices) reimagines the modern office for today’s workforce. More than just a place to work, it nurtures wellbeing and collaboration through open, airy layouts, cafés, lush verandas and multifunctional terraces designed to inspire and refresh.“Gurugram is moving towards sustainability and the walk-to-work model aligns seamlessly with that shift,” says Gagan Deep Singh, Founder Director, WoCO...To read read the full story Cli..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?