Rs 4,517.50 billion worth of housing stuck in stages of non-completion
Real Estate

Rs 4,517.50 billion worth of housing stuck in stages of non-completion

Despite the establishment of a regulatory mechanism, countless homebuyers have been left in the lurch by their builders. In fact, Rs 4,517.50 billion worth of housing is currently stuck in various stages of non-completion across top seven cities, according to data from real-estate services company ANAROCK.

Most of these projects do not fall within the ambit of RERA as they were launched years before it was implemented. Also, with many states having diluted the Centre's original RERA rules, homebuyers have only the courts to approach, which is a notoriously tedious task in India.
  
Areas like the National Capital Region (NCR) and Mumbai Metropolitan Region (MMR) collectively account for 72 per cent of the total stuck housing units across the top seven cities worth Rs 3490.1 billion—nearly 77 per cent of the total worth of the stuck projects. In comparison, the main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units with a total worth of Rs 417.7 billion. Bengaluru has less than half the total delayed stock in Pune (86,700 units), while Chennai has the least project delays during this period, with around 8,650 units worth Rs 56.20 billion.
 
“Besides the lack of will of some developers to complete their projects and preference for funds diversion, the tightening credit crunch has been a major factor contributing to this mounting problem,” observes Anuj Puri, Chairman, ANAROCK Property Consultants. “Also, every delayed project results in cost overruns, which compound the funding crunch even further. Lack of project clearances, for whatever reason, also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without requisite approvals in place, resulting in their projects getting stuck.” 
 
As one of the possible solutions to this problem, the government-owned NBCC has been roped in to complete some stalled projects in NCR. This is a significant move that, if applied in larger numbers, can have a real impact. “Moreover, even if NBCC picks up 50 per cent of overall stalled projects, the resultant construction activities would create significant employment for the EWS and LIG segments, which are also the key target segment for affordable housing,” he adds.
 
Additionally, with NBCC undertaking construction, the apprehensions of banks about funding construction would ease. With this provision, even when builders opt for bankruptcy, state authorities would intervene to safeguard the investments of homebuyers. However, buyers are still awaiting their final outcome of these interventions.

Despite the establishment of a regulatory mechanism, countless homebuyers have been left in the lurch by their builders. In fact, Rs 4,517.50 billion worth of housing is currently stuck in various stages of non-completion across top seven cities, according to data from real-estate services company ANAROCK.Most of these projects do not fall within the ambit of RERA as they were launched years before it was implemented. Also, with many states having diluted the Centre's original RERA rules, homebuyers have only the courts to approach, which is a notoriously tedious task in India.  Areas like the National Capital Region (NCR) and Mumbai Metropolitan Region (MMR) collectively account for 72 per cent of the total stuck housing units across the top seven cities worth Rs 3490.1 billion—nearly 77 per cent of the total worth of the stuck projects. In comparison, the main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units with a total worth of Rs 417.7 billion. Bengaluru has less than half the total delayed stock in Pune (86,700 units), while Chennai has the least project delays during this period, with around 8,650 units worth Rs 56.20 billion. “Besides the lack of will of some developers to complete their projects and preference for funds diversion, the tightening credit crunch has been a major factor contributing to this mounting problem,” observes Anuj Puri, Chairman, ANAROCK Property Consultants. “Also, every delayed project results in cost overruns, which compound the funding crunch even further. Lack of project clearances, for whatever reason, also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without requisite approvals in place, resulting in their projects getting stuck.”  As one of the possible solutions to this problem, the government-owned NBCC has been roped in to complete some stalled projects in NCR. This is a significant move that, if applied in larger numbers, can have a real impact. “Moreover, even if NBCC picks up 50 per cent of overall stalled projects, the resultant construction activities would create significant employment for the EWS and LIG segments, which are also the key target segment for affordable housing,” he adds. Additionally, with NBCC undertaking construction, the apprehensions of banks about funding construction would ease. With this provision, even when builders opt for bankruptcy, state authorities would intervene to safeguard the investments of homebuyers. However, buyers are still awaiting their final outcome of these interventions.

Next Story
Real Estate

BXB Estates Sets AED 110 Million Jumeirah Golf Estates Record

BXB Estates has completed an AED 110 million residential transaction at Jumeirah Golf Estates, setting a new sales record for the prestigious Dubai residential community.Negotiated by Alfie Tabrez, Managing Partner of BXB Estates, the deal surpassed the previous record of AED 58 million for a completed ready villa in the development.The six-bedroom residence offers 21,714 sq ft of built-up space on a 15,873-sq-ft plot. It features nine bathrooms, four living lounges, a home office, bar lounge, private cinema and rooftop terrace.The property also includes a dedicated wellness area comprising a ..

Next Story
Infrastructure Urban

SECR Floats Rs 6,019 Mn EPC Tender For Paradol Nagpur Link

South East Central Railway (SECR) has invited bids for an Engineering, Procurement and Construction (EPC) contract to build a new broad gauge single line between Paradol Takeoff Point and Nagpur Road Station in Chhattisgarh. The contract carries an estimated cost of Rs 6,019.0 mn and requires an earnest money deposit of Rs 120.4 mn. The work is framed as an EPC assignment intended to strengthen regional rail infrastructure. The tender, issued under number CAO-C-BSP-26-27-15, specifies a completion period of 730 days and a bid validity of 180 days. Two pre-bid meetings are scheduled for 24 Augu..

Next Story
Infrastructure Transport

Indian Railways Reports Nine Per Cent Rise In July Freight Loading

Indian Railways handled 141.3 million tonnes (141.3 mn t) of freight in July, marking a rise of nine per cent year on year. Freight loading maintained a positive trajectory across the network compared with the same month last year. Passenger traffic also increased in July, contributing to higher overall network utilisation. The July outcome continued a pattern of steady monthly gains, reflecting gradual improvement in industrial and logistics activity. The growth in freight volumes reflected stronger demand across multiple sectors and improvements in logistics and train turnarounds. Enhanced r..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement