CERC Restores 400 MW Project Connectivity In Madhya Pradesh
ECONOMY & POLICY

CERC Restores 400 MW Project Connectivity In Madhya Pradesh

The Central Electricity Regulatory Commission (CERC) has restored connectivity for a 400 Megawatt (MW) renewable energy project developed by ACME Cleantech Solutions Private Limited in Madhya Pradesh after setting aside a revocation by the Central Transmission Utility of India Limited (CTUIL). The dispute related to a request to change the project source from solar to wind following amendments to the General Network Access regulations.

ACME initially received an in-principle connectivity grant for a solar project linked to the Pachora Pooling Station and applied to convert to wind under provisions introduced by the Third Amendment to the GNA Regulations in September 2025. CTUIL delayed processing while calculating available non-solar access capacity and directed ACME to submit land documents related to the original solar project before October 2025. ACME instead submitted land documents for the proposed wind project, which CTUIL rejected.

On four December 2025 CTUIL revoked the connectivity approval and warned that ACME’s bank guarantee of Rs 400 mn could be encashed, prompting the developer to seek urgent relief in the Delhi High Court. The court ordered maintenance of the status quo and the matter was taken up by the CERC for detailed consideration. ACME told the Commission that it had progressed work on the wind project, including investment in wind turbines and securing lease deeds for 44 project locations.

The developer reported completion of foundation work at 31 sites and argued that delays by CTUIL in issuing the final connectivity grant had prevented timely implementation of changes. The Commission observed that the Third Amendment had been introduced to provide flexibility to renewable energy developers and that they should not be penalised for administrative delays during transition to the new framework. CERC set aside the revocation, restored connectivity and directed CTUIL to process the application for source change, issue the final connectivity grant and evaluate the submitted land documents.

The Central Electricity Regulatory Commission (CERC) has restored connectivity for a 400 Megawatt (MW) renewable energy project developed by ACME Cleantech Solutions Private Limited in Madhya Pradesh after setting aside a revocation by the Central Transmission Utility of India Limited (CTUIL). The dispute related to a request to change the project source from solar to wind following amendments to the General Network Access regulations. ACME initially received an in-principle connectivity grant for a solar project linked to the Pachora Pooling Station and applied to convert to wind under provisions introduced by the Third Amendment to the GNA Regulations in September 2025. CTUIL delayed processing while calculating available non-solar access capacity and directed ACME to submit land documents related to the original solar project before October 2025. ACME instead submitted land documents for the proposed wind project, which CTUIL rejected. On four December 2025 CTUIL revoked the connectivity approval and warned that ACME’s bank guarantee of Rs 400 mn could be encashed, prompting the developer to seek urgent relief in the Delhi High Court. The court ordered maintenance of the status quo and the matter was taken up by the CERC for detailed consideration. ACME told the Commission that it had progressed work on the wind project, including investment in wind turbines and securing lease deeds for 44 project locations. The developer reported completion of foundation work at 31 sites and argued that delays by CTUIL in issuing the final connectivity grant had prevented timely implementation of changes. The Commission observed that the Third Amendment had been introduced to provide flexibility to renewable energy developers and that they should not be penalised for administrative delays during transition to the new framework. CERC set aside the revocation, restored connectivity and directed CTUIL to process the application for source change, issue the final connectivity grant and evaluate the submitted land documents.

Next Story
Building Material

Enlight Metals to Expand Raipur Plant Capacity

Enlight Metals has announced plans to expand the production capacity of its Raipur manufacturing facility from around 1,200 tonnes to nearly 4,000 tonnes.The expansion is aimed at strengthening the company’s ability to serve rising demand across industrial, infrastructure and contract manufacturing requirements.Located in Raipur, Chhattisgarh, the facility serves as a key manufacturing hub for Enlight Metals. The planned capacity enhancement is expected to improve supply capabilities, operational efficiency and the company’s ability to handle larger project requirements.The facility includ..

Next Story
Infrastructure Urban

Hindustan Zinc Partners Sulfozyme for Zinc Park Project

Hindustan Zinc has signed a Memorandum of Understanding with Sulfozyme Agro India under its Zinc Industrial Park initiative at Khankhala in Bhilwara district, Rajasthan. The partnership aims to strengthen India’s downstream zinc sector through sustainable metal recovery, resource efficiency and industrial development.Under the agreement, Sulfozyme Agro will establish proposed operations at the Zinc Industrial Park to process zinc-based materials into value-added products for industrial and downstream applications.Hindustan Zinc will support the venture through assured raw material linkage an..

Next Story
Infrastructure Urban

Cortec MCI Technology Restores Croatia Monuments

Cortec’s Migrating Corrosion Inhibitor technology has been used in restoration works for historic monuments in Croatia, including the Church of St Donatus in Zadar and the medieval city walls of Ilok.The Church of St Donatus, one of the most significant pre-Romanesque churches in Europe, is listed in the Register of Cultural Goods of the Republic of Croatia and is under UNESCO protection. The monument required urgent rehabilitation after 3D scanning analysis identified critical issues in the church walls, main structure and roof.The reinforced concrete support structure beneath the roof, ins..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement