CERC Restores 400 MW Project Connectivity In Madhya Pradesh
ECONOMY & POLICY

CERC Restores 400 MW Project Connectivity In Madhya Pradesh

The Central Electricity Regulatory Commission (CERC) has restored connectivity for a 400 Megawatt (MW) renewable energy project developed by ACME Cleantech Solutions Private Limited in Madhya Pradesh after setting aside a revocation by the Central Transmission Utility of India Limited (CTUIL). The dispute related to a request to change the project source from solar to wind following amendments to the General Network Access regulations.

ACME initially received an in-principle connectivity grant for a solar project linked to the Pachora Pooling Station and applied to convert to wind under provisions introduced by the Third Amendment to the GNA Regulations in September 2025. CTUIL delayed processing while calculating available non-solar access capacity and directed ACME to submit land documents related to the original solar project before October 2025. ACME instead submitted land documents for the proposed wind project, which CTUIL rejected.

On four December 2025 CTUIL revoked the connectivity approval and warned that ACME’s bank guarantee of Rs 400 mn could be encashed, prompting the developer to seek urgent relief in the Delhi High Court. The court ordered maintenance of the status quo and the matter was taken up by the CERC for detailed consideration. ACME told the Commission that it had progressed work on the wind project, including investment in wind turbines and securing lease deeds for 44 project locations.

The developer reported completion of foundation work at 31 sites and argued that delays by CTUIL in issuing the final connectivity grant had prevented timely implementation of changes. The Commission observed that the Third Amendment had been introduced to provide flexibility to renewable energy developers and that they should not be penalised for administrative delays during transition to the new framework. CERC set aside the revocation, restored connectivity and directed CTUIL to process the application for source change, issue the final connectivity grant and evaluate the submitted land documents.

The Central Electricity Regulatory Commission (CERC) has restored connectivity for a 400 Megawatt (MW) renewable energy project developed by ACME Cleantech Solutions Private Limited in Madhya Pradesh after setting aside a revocation by the Central Transmission Utility of India Limited (CTUIL). The dispute related to a request to change the project source from solar to wind following amendments to the General Network Access regulations. ACME initially received an in-principle connectivity grant for a solar project linked to the Pachora Pooling Station and applied to convert to wind under provisions introduced by the Third Amendment to the GNA Regulations in September 2025. CTUIL delayed processing while calculating available non-solar access capacity and directed ACME to submit land documents related to the original solar project before October 2025. ACME instead submitted land documents for the proposed wind project, which CTUIL rejected. On four December 2025 CTUIL revoked the connectivity approval and warned that ACME’s bank guarantee of Rs 400 mn could be encashed, prompting the developer to seek urgent relief in the Delhi High Court. The court ordered maintenance of the status quo and the matter was taken up by the CERC for detailed consideration. ACME told the Commission that it had progressed work on the wind project, including investment in wind turbines and securing lease deeds for 44 project locations. The developer reported completion of foundation work at 31 sites and argued that delays by CTUIL in issuing the final connectivity grant had prevented timely implementation of changes. The Commission observed that the Third Amendment had been introduced to provide flexibility to renewable energy developers and that they should not be penalised for administrative delays during transition to the new framework. CERC set aside the revocation, restored connectivity and directed CTUIL to process the application for source change, issue the final connectivity grant and evaluate the submitted land documents.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement