Lohegaon Airport's New Terminal Faces Delays
AVIATION & AIRPORTS

Lohegaon Airport's New Terminal Faces Delays

The commissioning of the new terminal building at Lohegaon Airport has faced further delays and is now expected to be operational by mid-December or early January of the next year. The new building, with an estimated cost of Rs 4.75 billion, was initially scheduled to be commissioned this month. However, it has seen multiple revisions in its commissioning date since last December, missing several deadlines along the way.

Officials attributed the project's initial delay to the impact of the pandemic. They mentioned that the Airports Authority of India (AAI) headquarters had recommended additional arrangements for the building, taking into consideration congestion issues faced by major airports in the country. One of the key changes is the expansion of the security hold area, which will require the installation of more scanning machines. The number of machines will be increased from eight to twelve, necessitating additional space in the new building. The construction to accommodate these changes is underway, with completion expected by November, followed by testing.

The goal is to complete all the required work in one go to ensure a seamless experience for travellers. As for the integration of the new building with the existing one, the first phase has already been finished. The second phase is nearing completion, and a request for the building's inauguration has been submitted to the Prime Minister's Office.

Under the new plan, the arrival area on the first floor of the existing building will be integrated with the new structure and serve as a security hold area. The AAI's long-term plan involves redeveloping the existing building, after which both structures will operate fully.

The changing dates for the new terminal building have raised concerns, especially with the upcoming Diwali period, which is expected to see a surge in passenger traffic. The shift of operations to the new building was expected to be completed by now, but the delays have raised worries about the airport's capacity to handle increased crowds.

The commissioning of the new terminal building at Lohegaon Airport has faced further delays and is now expected to be operational by mid-December or early January of the next year. The new building, with an estimated cost of Rs 4.75 billion, was initially scheduled to be commissioned this month. However, it has seen multiple revisions in its commissioning date since last December, missing several deadlines along the way. Officials attributed the project's initial delay to the impact of the pandemic. They mentioned that the Airports Authority of India (AAI) headquarters had recommended additional arrangements for the building, taking into consideration congestion issues faced by major airports in the country. One of the key changes is the expansion of the security hold area, which will require the installation of more scanning machines. The number of machines will be increased from eight to twelve, necessitating additional space in the new building. The construction to accommodate these changes is underway, with completion expected by November, followed by testing. The goal is to complete all the required work in one go to ensure a seamless experience for travellers. As for the integration of the new building with the existing one, the first phase has already been finished. The second phase is nearing completion, and a request for the building's inauguration has been submitted to the Prime Minister's Office. Under the new plan, the arrival area on the first floor of the existing building will be integrated with the new structure and serve as a security hold area. The AAI's long-term plan involves redeveloping the existing building, after which both structures will operate fully. The changing dates for the new terminal building have raised concerns, especially with the upcoming Diwali period, which is expected to see a surge in passenger traffic. The shift of operations to the new building was expected to be completed by now, but the delays have raised worries about the airport's capacity to handle increased crowds.

Next Story
Infrastructure Urban

Centre Disburses Over Rs 24,610 mn in XV Finance Commission Grants

The Union Government has released XV Finance Commission tied grants during the financial year 2025–26 to rural local bodies in Chhattisgarh, Gujarat, Madhya Pradesh, Punjab and Sikkim and has released withheld portions of tied and untied grants to Himachal Pradesh, Odisha and Tripura. The total disbursal exceeded Rs 24,610 mn, with figures expressed in million (mn) thereafter. The releases cover allocations pertaining to different financial years and aim to strengthen rural local governance. State-wise disbursements included Rs 3,324.6 mn for Punjab, Rs 9,432.7 mn for Madhya Pradesh, Rs 3,47..

Next Story
Infrastructure Urban

Centre Releases Over Rs 15 bn as XV FC Grants to Rural Bodies

The Union Government has released over Rs 15 bn in grants recommended by the Fifteenth Finance Commission (XV FC) to strengthen Panchayati Raj Institutions (PRIs) and Rural Local Bodies (RLBs) in six states. The funds comprise tied and untied grants disbursed in FY 2025–26. Telangana received Rs 2.48 bn as the first instalment of untied grants for FY 2025–26, benefitting 12600 Gram Panchayats (GPs). Uttarakhand received Rs 913.1 mn as the second instalment and an additional Rs 18.4 mn of a withheld first instalment was released to a further 216 GPs. Mizoram is included among beneficiary st..

Next Story
Infrastructure Energy

Government Assures Fuel Supplies And Seafarer Safety Amid West Asia Developments

The Government of India has stepped up coordinated measures to maintain stability in critical sectors as developments in West Asia continue to unfold. It has prioritised uninterrupted energy supplies, safeguarded maritime operations and extended consular assistance to nationals. Central authorities are working with State and Union territory administrations to ensure timely information dissemination and operational continuity. Refineries are reported to be operating at high capacity with adequate inventories of petrol and diesel, and domestic LPG production has been increased to support consump..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement