Lohegaon Airport's New Terminal Faces Delays
AVIATION & AIRPORTS

Lohegaon Airport's New Terminal Faces Delays

The commissioning of the new terminal building at Lohegaon Airport has faced further delays and is now expected to be operational by mid-December or early January of the next year. The new building, with an estimated cost of Rs 4.75 billion, was initially scheduled to be commissioned this month. However, it has seen multiple revisions in its commissioning date since last December, missing several deadlines along the way.

Officials attributed the project's initial delay to the impact of the pandemic. They mentioned that the Airports Authority of India (AAI) headquarters had recommended additional arrangements for the building, taking into consideration congestion issues faced by major airports in the country. One of the key changes is the expansion of the security hold area, which will require the installation of more scanning machines. The number of machines will be increased from eight to twelve, necessitating additional space in the new building. The construction to accommodate these changes is underway, with completion expected by November, followed by testing.

The goal is to complete all the required work in one go to ensure a seamless experience for travellers. As for the integration of the new building with the existing one, the first phase has already been finished. The second phase is nearing completion, and a request for the building's inauguration has been submitted to the Prime Minister's Office.

Under the new plan, the arrival area on the first floor of the existing building will be integrated with the new structure and serve as a security hold area. The AAI's long-term plan involves redeveloping the existing building, after which both structures will operate fully.

The changing dates for the new terminal building have raised concerns, especially with the upcoming Diwali period, which is expected to see a surge in passenger traffic. The shift of operations to the new building was expected to be completed by now, but the delays have raised worries about the airport's capacity to handle increased crowds.

The commissioning of the new terminal building at Lohegaon Airport has faced further delays and is now expected to be operational by mid-December or early January of the next year. The new building, with an estimated cost of Rs 4.75 billion, was initially scheduled to be commissioned this month. However, it has seen multiple revisions in its commissioning date since last December, missing several deadlines along the way. Officials attributed the project's initial delay to the impact of the pandemic. They mentioned that the Airports Authority of India (AAI) headquarters had recommended additional arrangements for the building, taking into consideration congestion issues faced by major airports in the country. One of the key changes is the expansion of the security hold area, which will require the installation of more scanning machines. The number of machines will be increased from eight to twelve, necessitating additional space in the new building. The construction to accommodate these changes is underway, with completion expected by November, followed by testing. The goal is to complete all the required work in one go to ensure a seamless experience for travellers. As for the integration of the new building with the existing one, the first phase has already been finished. The second phase is nearing completion, and a request for the building's inauguration has been submitted to the Prime Minister's Office. Under the new plan, the arrival area on the first floor of the existing building will be integrated with the new structure and serve as a security hold area. The AAI's long-term plan involves redeveloping the existing building, after which both structures will operate fully. The changing dates for the new terminal building have raised concerns, especially with the upcoming Diwali period, which is expected to see a surge in passenger traffic. The shift of operations to the new building was expected to be completed by now, but the delays have raised worries about the airport's capacity to handle increased crowds.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement