+
Lohegaon Airport's New Terminal Faces Delays
AVIATION & AIRPORTS

Lohegaon Airport's New Terminal Faces Delays

The commissioning of the new terminal building at Lohegaon Airport has faced further delays and is now expected to be operational by mid-December or early January of the next year. The new building, with an estimated cost of Rs 4.75 billion, was initially scheduled to be commissioned this month. However, it has seen multiple revisions in its commissioning date since last December, missing several deadlines along the way.

Officials attributed the project's initial delay to the impact of the pandemic. They mentioned that the Airports Authority of India (AAI) headquarters had recommended additional arrangements for the building, taking into consideration congestion issues faced by major airports in the country. One of the key changes is the expansion of the security hold area, which will require the installation of more scanning machines. The number of machines will be increased from eight to twelve, necessitating additional space in the new building. The construction to accommodate these changes is underway, with completion expected by November, followed by testing.

The goal is to complete all the required work in one go to ensure a seamless experience for travellers. As for the integration of the new building with the existing one, the first phase has already been finished. The second phase is nearing completion, and a request for the building's inauguration has been submitted to the Prime Minister's Office.

Under the new plan, the arrival area on the first floor of the existing building will be integrated with the new structure and serve as a security hold area. The AAI's long-term plan involves redeveloping the existing building, after which both structures will operate fully.

The changing dates for the new terminal building have raised concerns, especially with the upcoming Diwali period, which is expected to see a surge in passenger traffic. The shift of operations to the new building was expected to be completed by now, but the delays have raised worries about the airport's capacity to handle increased crowds.

The commissioning of the new terminal building at Lohegaon Airport has faced further delays and is now expected to be operational by mid-December or early January of the next year. The new building, with an estimated cost of Rs 4.75 billion, was initially scheduled to be commissioned this month. However, it has seen multiple revisions in its commissioning date since last December, missing several deadlines along the way. Officials attributed the project's initial delay to the impact of the pandemic. They mentioned that the Airports Authority of India (AAI) headquarters had recommended additional arrangements for the building, taking into consideration congestion issues faced by major airports in the country. One of the key changes is the expansion of the security hold area, which will require the installation of more scanning machines. The number of machines will be increased from eight to twelve, necessitating additional space in the new building. The construction to accommodate these changes is underway, with completion expected by November, followed by testing. The goal is to complete all the required work in one go to ensure a seamless experience for travellers. As for the integration of the new building with the existing one, the first phase has already been finished. The second phase is nearing completion, and a request for the building's inauguration has been submitted to the Prime Minister's Office. Under the new plan, the arrival area on the first floor of the existing building will be integrated with the new structure and serve as a security hold area. The AAI's long-term plan involves redeveloping the existing building, after which both structures will operate fully. The changing dates for the new terminal building have raised concerns, especially with the upcoming Diwali period, which is expected to see a surge in passenger traffic. The shift of operations to the new building was expected to be completed by now, but the delays have raised worries about the airport's capacity to handle increased crowds.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App