Highway construction in India increases 25% in Q1 FY22
ROADS & HIGHWAYS

Highway construction in India increases 25% in Q1 FY22

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day.

In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before.

The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal.

Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders.

The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season.

Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded.

Image Source


Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana

Also read: Govt relentlessly working to make highways the mainstay of economy

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day. In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before. The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal. Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders. The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season. Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded. Image Source Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana Also read: Govt relentlessly working to make highways the mainstay of economy

Next Story
Infrastructure Urban

DCPC Prepares for Special Campaign 5.0 with Focus on E-Waste

The Department of Chemicals and Petrochemicals (DCPC), Ministry of Chemicals and Fertilisers, is gearing up for Special Campaign 5.0, to be held from 2nd to 31st October 2025. The initiative will focus on e-waste disposal as per MoEFCC’s E-Waste Management Rules 2022, space optimisation, and enhancing workplace efficiency across field offices.Special Campaign 4.0, conducted between October 2023 and October 2024, delivered notable results in record management, grievance redressal, scrap disposal, and cleanliness drives.Key outcomes of Special Campaign 4.0Records management: 2,443 physical fil..

Next Story
Real Estate

BlackRock India Leases 1.4 Lakh Sq Ft in Bengaluru

BlackRock Services India, the domestic arm of global asset manager BlackRock, has leased 1.4 lakh sq ft of office space at IndiQube Symphony in Bengaluru, according to Propstack data. The 10-year deal is valued at around Rs 4.10 billion.The lease, among the largest transactions in India’s co-working sector, highlights the growing preference of global institutions for flexible office providers. The agreement, commencing October 1, 2025, covers ground plus five floors in KNG Tower 1 at Ashoknagar, MG Road — one of Bengaluru’s prime commercial hubs.As per the lease document, BlackRock will ..

Next Story
Infrastructure Transport

L&T Bags Rs 25–50 Bn Order for Mumbai-Ahmedabad Bullet Train Track Works

Larsen & Toubro’s (L&T) Transportation Infrastructure business has secured an order valued between Rs 25 crore and Rs 50 billion from the National High Speed Rail Corporation Limited (NHSRCL) for the Mumbai-Ahmedabad High Speed Rail (MAHSR) corridor.The contract, Package T1, involves the design, supply, construction, testing, and commissioning of 156 route km of high-speed ballastless track on a Design-Build Lump Sum Price basis. The stretch runs from Mumbai’s Bandra-Kurla Complex to Zaroli village in Gujarat and includes 21 km of underground track and 135 km of elevated viaduct.Se..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?