 Highway construction in India increases 25% in Q1 FY22
ROADS & HIGHWAYS

Highway construction in India increases 25% in Q1 FY22

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day.

In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before.

The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal.

Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders.

The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season.

Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded.

Image Source


Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana

Also read: Govt relentlessly working to make highways the mainstay of economy

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day. In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before. The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal. Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders. The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season. Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded. Image Source Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana Also read: Govt relentlessly working to make highways the mainstay of economy

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?