 Highway construction in India increases 25% in Q1 FY22
ROADS & HIGHWAYS

Highway construction in India increases 25% in Q1 FY22

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day.

In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before.

The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal.

Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders.

The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season.

Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded.

Image Source


Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana

Also read: Govt relentlessly working to make highways the mainstay of economy

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day. In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before. The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal. Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders. The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season. Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded. Image Source Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana Also read: Govt relentlessly working to make highways the mainstay of economy

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code