Highway construction in India increases 25% in Q1 FY22
ROADS & HIGHWAYS

Highway construction in India increases 25% in Q1 FY22

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day.

In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before.

The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal.

Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders.

The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season.

Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded.

Image Source


Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana

Also read: Govt relentlessly working to make highways the mainstay of economy

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Construction of highways in India witnessed a 25% increase in the first quarter of the current FY to 2,284 km at 25.37 km per day. In the April-June period of 2019-20, highway construction was 23.29 km per day. The construction speed registered in the first three months of the current fiscal year was even higher than before. The highest record accomplished in 2020-21 FY was 34.4 km per day. However, the construction pace in the first three months in the current fiscal is way behind as compared to 2020-21 fiscal. Analysts attributed the record construction previous fiscal to a slew of industry-friendly actions that the government had proactively practised throughout the pandemic year, including those to make sure better cash flow to the builders. The second wave of the Covid-19 hit the nation from the start of April. The speed of highway construction usually reaches its peak after the festive season. Throughout the April-June time of the current fiscal, project awards also marginally grew to 1,681 km from 1,658 km in the same period last fiscal. However, in the same period of 2019-20, just 743 km project length was awarded. Image Source Also read: MoRTH approves highway projects worth Rs 6,393 cr in Haryana Also read: Govt relentlessly working to make highways the mainstay of economy

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement