CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29
ROADS & HIGHWAYS

CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process.

Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes.

The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety.

The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process. Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes. The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety. The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

Next Story
Infrastructure Transport

Third Railway Line Between Tatanagar And Adityapur Likely By September

The third railway line between Tatanagar and Adityapur is expected to be commissioned by September as work on the corridor advances, according to railway sources. The project to add a fourth line on the busy route is progressing and has been allocated Rs 50.89 billion (bn) in funding. The allocation underscores the focus on increasing capacity and easing congestion on the corridor. Relevant timetables are being adjusted to integrate the new capacity into regular operations. Construction activity has involved track laying, formation work and signalling upgrades along strategic stretches, with m..

Next Story
Infrastructure Transport

Indian Railways Approves Rs 2.7 bn Kavach Rollout in Odisha

Indian Railways has approved a Rs 2.7 billion (Rs 2.7 bn) plan to install the Kavach train collision avoidance system on 631 route kilometres in the East Coast Railway zone. The Ministry of Railways said the work will form part of a wider Kavach deployment programme that relies on an LTE based communication backbone rather than a standalone installation. The approval marks the latest stage in the steady expansion of the indigenous safety technology across the national network. The decision aims to enhance safety and reliability on corridors serving Odisha and adjoining areas. The project will ..

Next Story
Infrastructure Transport

Indian Railways Accelerates Modernisation Drive

Indian Railways utilised nearly 30 per cent of its capital expenditure budget for FY2026-27 within the first two months of the financial year, spending more than Rs 840 billion (bn) in April and May against a planned outlay of Rs 2.93 trillion (tn) for the year. The Union Budget allocated Rs 2.93 tn in total capex, comprising Rs 2.81 tn through gross budgetary support and Rs 120 bn from extra-budgetary resources. The early absorption indicates robust project execution and an aggressive infrastructure push. A significant share of the spending is being channelled towards track infrastructure, in..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement