CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29
ROADS & HIGHWAYS

CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process.

Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes.

The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety.

The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process. Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes. The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety. The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

Next Story
Real Estate

ANDPL launches AI assistant for Dharavi residents

Adani Navbharat Developers (ANDPL), the special purpose vehicle implementing the Dharavi Redevelopment Project (DRP), has launched Dharavi Didi, a 24x7 AI-powered digital assistant to provide residents with official information on the redevelopment programme.Accessible through video calls, voice calls and WhatsApp, the platform enables residents to obtain information on surveys, eligibility, documentation, rehabilitation and project updates in Hindi, Marathi and English. Support for Tamil, Telugu and Gujarati is planned in the coming months.According to ANDPL, the initiative is intended to imp..

Next Story
Infrastructure Urban

Indobell Secures Domestic Order For Nodulated Wool

Indobell Insulations Limited (Indobell) has disclosed that it has secured a domestic order from Sundaram Brake Linings Limited (Sundaram Brake Linings) for the supply of nodulated wool valued at Rs 48.74 mn. The company submitted the disclosure to BSE Limited on 17 July 2026 under Regulation 30 of the SEBI Listing Obligations and Disclosure Requirements Regulations, 2015 and related circulars. The filing identified the purchaser as a domestic entity and described the contract as a standard supply agreement to be fulfilled over a specified timeline. The order carries payment terms of 45 days by..

Next Story
Infrastructure Urban

PTC Secures BrahMos Order For Strategic Missile Subsystem

PTC Industries Limited has received a landmark order from BrahMos Aerospace Private Limited for development, integration and supply of a strategic missile sub-system for the BrahMos programme. The order marks the company’s first major assignment in systems-level integration and represents a strategic move further downstream in the aerospace and defence value chain. The award reflects BrahMos Aerospace's confidence in PTC’s engineering depth, manufacturing discipline, quality systems and execution capability. The development opens a new chapter as PTC transitions from supplying critical mat..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement