CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29
ROADS & HIGHWAYS

CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process.

Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes.

The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety.

The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process. Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes. The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety. The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Asian Energy Services Q1 FY27 PAT Rises 129 Per Cent

Asian Energy Services Limited reported a 129 per cent year-on-year rise in net profit to Rs 128 million for Q1 FY27, compared with the corresponding quarter last year.Revenue increased 135 per cent year-on-year to Rs 2.71 billion, supported by continued momentum across its services business, disciplined execution and contributions from domestic and international operations. EBITDA grew 81 per cent year-on-year during the quarter.As of June 30, 2026, the company’s standalone order book stood at Rs 17.54 billion, with around 60 per cent coming from oil and gas services and 40 per cent from min..

Next Story
Infrastructure Urban

BioBTX to Build First Commercial-Scale Circular Chemicals Plant

Dutch circular chemistry technology developer BioBTX is building what it says will be the world’s first commercial-scale plant to convert mixed plastic waste into high-quality aromatic chemicals using its proprietary Integrated Catalytic Cracking Process (ICCP) technology.The facility will be built at Chemical Park Delfzijl on the northern coast of the Netherlands and is expected to create 35 jobs. Covestro, which has been a shareholder and strategic partner of BioBTX since 2024, holds a mid-single-digit million-euro investment in the company.BioBTX’s ICCP technology uses catalytic pyrolys..

Next Story
Real Estate

Awfis Q1 FY27 PAT Jumps 140% as Revenue Rises 27%

Awfis Space Solutions reported a 140 per cent year-on-year rise in consolidated profit after tax (PAT) to Rs 240 million for Q1 FY27, compared with Rs 100 million in the corresponding quarter last year.Revenue from operations increased 27 per cent to Rs 4.25 billion from Rs 3.35 billion, while EBITDA rose 28 per cent to Rs 1.62 billion. EBITDA margin improved to 38.2 per cent from 37.8 per cent. Profit before tax increased 135 per cent to Rs 240 million.The company's co-working business recorded 27 per cent year-on-year growth, supported by demand from enterprises, Global Capability Centres (G..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement