CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29
ROADS & HIGHWAYS

CSU And NHIDCL Sign Roadmap To Complete Delayed NH-29

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process.

Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes.

The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety.

The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

At Pfutsero, the Chakhesang Students’ Union, the National Highways & Infrastructure Development Corporation Limited and the EPC contractor M/S Ratna Infrastructure Projects Pvt. Ltd. signed a six-point agreement to expedite completion of the NH-29 two-lane Kohima-Jessami Road Package II project. The pact was formalised on June 22 at the Tourist Complex after a 14-day ultimatum issued by the CSU on June 2 expired on June 16, with the student body pressing for action over delays and deteriorating road conditions. The agreement sets responsibilities for the contractor and the highways authority and establishes a structured review process. Under the terms the contractor must undertake emergency repairs within 48 hours of notice and mobilise machinery and manpower within 72 hours to address critical defects. The parties set a target to complete all physical works by September 24, 2026, and placed routine maintenance responsibility with the EPC contractor, including liability for damages arising from poor upkeep. This allocation is intended to secure sustained performance rather than temporary fixes. The signatories committed to joint inspections every 20 days, with the next review scheduled for July 13, and to record progress at each visit. The meeting highlighted the badly damaged stretch between Chakhaba and Kikruma, described as virtually unmotorable in places and posing safety risks. The pact requires emergency restoration of that section, including filling potholes and clearing clogged drainage systems to improve commuter safety. The agreement includes an enforcement clause that non-compliance would render the arrangement null and void and hold NHIDCL and the contractor responsible for any subsequent action initiated by the CSU. It was signed by M.S.N. Murthy for Ratna Infrastructure Projects and by Povozo Soho, president of the Chakhesang Students’ Union, in the presence of Rajesh Kumar, senior resident maintenance engineer, NHIDCL. The CSU said the measure aimed to ensure accountability and restore a vital highway that serves as a lifeline for residents of Phek district and beyond.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code