Delhi-Amritsar-Katra Expressway Ready From Balsua To Raya
ROADS & HIGHWAYS

Delhi-Amritsar-Katra Expressway Ready From Balsua To Raya

The Delhi-Amritsar-Katra expressway is ready from Balsua in Punjab up to the Ring Road at Raya and is planned to open for pilgrims of the annual Amarnath yatra in June. The 670 km corridor from Bahadurgarh in Delhi to Katra via Amritsar will reduce travel time from Delhi to Amritsar to four hours and from Delhi to Katra to six hours. The carriageway will have six lanes extendable up to eight.

National Highway Authority of India (NHAI) officials said the overall project is unlikely to meet the December 2026 deadline and is expected to be commissioned in March 2027. Delays were attributed to late sanctioning of railway bridges, Operation Sindhoor, and heavy rains and floods that disrupted work on a 147 km stretch in Jammu and Kashmir. Workforce shortages and land acquisition constraints also hindered progress despite intensified resource mobilisation.

The project comprises Package 14 of about 44.60 km from Balsua near Dinanagar to Hiranagar costing Rs 30.44 bn, including Rs 19.39 bn for civil works, and Package 15 covering 35.15 km from Hiranagar to Raya Morh valued at Rs 27.15 bn with Rs 18.7 bn civil cost. Package 16 stretches 20.38 km from Raya Morh to Kunjwani, includes a seven km spur to the new Jammu airport and the River Tawi fourth bridge, costs Rs 19.17 bn with Rs 17.65 bn civil component. Physical progress on these packages is about 85 per cent, 90 per cent and 95 per cent.

Work on major river bridges including Ravi, Ujh, Tarnah and Basantar is nearly complete and the Devak bridge near All India Institute of Medical Sciences (AIIMS) Vijaypur has opened to traffic. Some railway bridge matters remain under active consideration and land issues near Nomain in Katra are sub judice. The Ministry of Road Transport and Highways (MoRTH) recorded project cost escalation from Rs 250 bn to Rs 389.05 bn, a rise of 55.62 per cent, and with 273 km of 670 km complete authorities are targeting a phased opening to boost tourism, trade and regional mobility.

The Delhi-Amritsar-Katra expressway is ready from Balsua in Punjab up to the Ring Road at Raya and is planned to open for pilgrims of the annual Amarnath yatra in June. The 670 km corridor from Bahadurgarh in Delhi to Katra via Amritsar will reduce travel time from Delhi to Amritsar to four hours and from Delhi to Katra to six hours. The carriageway will have six lanes extendable up to eight. National Highway Authority of India (NHAI) officials said the overall project is unlikely to meet the December 2026 deadline and is expected to be commissioned in March 2027. Delays were attributed to late sanctioning of railway bridges, Operation Sindhoor, and heavy rains and floods that disrupted work on a 147 km stretch in Jammu and Kashmir. Workforce shortages and land acquisition constraints also hindered progress despite intensified resource mobilisation. The project comprises Package 14 of about 44.60 km from Balsua near Dinanagar to Hiranagar costing Rs 30.44 bn, including Rs 19.39 bn for civil works, and Package 15 covering 35.15 km from Hiranagar to Raya Morh valued at Rs 27.15 bn with Rs 18.7 bn civil cost. Package 16 stretches 20.38 km from Raya Morh to Kunjwani, includes a seven km spur to the new Jammu airport and the River Tawi fourth bridge, costs Rs 19.17 bn with Rs 17.65 bn civil component. Physical progress on these packages is about 85 per cent, 90 per cent and 95 per cent. Work on major river bridges including Ravi, Ujh, Tarnah and Basantar is nearly complete and the Devak bridge near All India Institute of Medical Sciences (AIIMS) Vijaypur has opened to traffic. Some railway bridge matters remain under active consideration and land issues near Nomain in Katra are sub judice. The Ministry of Road Transport and Highways (MoRTH) recorded project cost escalation from Rs 250 bn to Rs 389.05 bn, a rise of 55.62 per cent, and with 273 km of 670 km complete authorities are targeting a phased opening to boost tourism, trade and regional mobility.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code