Highway construction slows to 20.43 km/day in Apr-Jul period
ROADS & HIGHWAYS

Highway construction slows to 20.43 km/day in Apr-Jul period

The pace of national highway (NH) construction in the country has slowed to 20.43 km a day during the first four months of the current financial year, according to official data.

While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country.

"The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22," the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022.

According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country.

The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22.

See also:
How new HAM criteria puts all on equal footing
NHAI to begin work on elevated highway in Chennai Port


"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The pace of national highway (NH) construction in the country has slowed to 20.43 km a day during the first four months of the current financial year, according to official data. While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country. The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22, the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022. According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country. The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22. See also: How new HAM criteria puts all on equal footingNHAI to begin work on elevated highway in Chennai Port

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement