Highway construction slows to 20.43 km/day in Apr-Jul period
ROADS & HIGHWAYS

Highway construction slows to 20.43 km/day in Apr-Jul period

The pace of national highway (NH) construction in the country has slowed to 20.43 km a day during the first four months of the current financial year, according to official data.

While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country.

"The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22," the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022.

According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country.

The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22.

See also:
How new HAM criteria puts all on equal footing
NHAI to begin work on elevated highway in Chennai Port


The pace of national highway (NH) construction in the country has slowed to 20.43 km a day during the first four months of the current financial year, according to official data. While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country. The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22, the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022. According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country. The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22. See also: How new HAM criteria puts all on equal footingNHAI to begin work on elevated highway in Chennai Port

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?