Highway construction slows to 20.43 km/day in Apr-Jul period
ROADS & HIGHWAYS

Highway construction slows to 20.43 km/day in Apr-Jul period

The pace of national highway (NH) construction in the country has slowed to 20.43 km a day during the first four months of the current financial year, according to official data.

While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country.

"The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22," the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022.

According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country.

The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22.

See also:
How new HAM criteria puts all on equal footing
NHAI to begin work on elevated highway in Chennai Port


The pace of national highway (NH) construction in the country has slowed to 20.43 km a day during the first four months of the current financial year, according to official data. While the pace had touched a record 37 km per day in 2020-21, it slowed to 28.64 km a day in 2021-22 due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country. The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22, the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022. According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period. The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country. The official target of highway construction has been kept at 12,000 km for the current financial year. The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22. See also: How new HAM criteria puts all on equal footingNHAI to begin work on elevated highway in Chennai Port

Next Story
Products

unWOOD transforms plastic waste into durable wood alternative

unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood—without the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. “Any application that introduces plastics into areas where it cannot be..

Next Story
Real Estate

India's first AI-integrated campus announced in Noida

Yashoda Hospital and Bhutani Infra have announced plans to develop India’s first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel—all operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..

Next Story
Infrastructure Urban

Postal Dept Unveils Stamp Honouring 125 Years of Kodaikanal Observatory

The Department of Posts is proud to release a commemorative postage stamp celebrating 125 years of the Kodaikanal Solar Observatory (KSO). Recognising the legacy of the KSO through this special stamp is a fitting tribute to one of India’s most significant scientific institutions and highlights the nation’s long-standing contribution to global science.The Commemorative stamp was released by S Rajendra Kumar, Chief Postmaster General, Karnataka Circle in the gracious presence of A S Kiran Kumar, Chairperson, Governing Council, IIA and Former Chairman, ISRO and other esteemed guests at Indian..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?