+
ICRA: Time for a Hybrid Toll Model in road sector
ROADS & HIGHWAYS

ICRA: Time for a Hybrid Toll Model in road sector

There has been a lot of debate in recent times about the need for the National Highways Authority of India (NHAI) to focus on asset monetisation and tap alternate funding avenues viz. toll-operate-transfer (TOT) and infrastructure investment trusts (InvITs) given the huge funding requirement for the ongoing Bharatmala Pariyojana programme. ICRA, in its earlier observation on this subject, has already highlighted the importance of speeding up the TOT awards and other fund-raising initiatives to meet the large funding requirements of the ambitious programme. However, the progress on both these fronts has been slow till date. To add to this, the share of the build-operate-transfer (BOT) (Toll) projects in the overall awards has declined sharply (being made primarily through the EPC/hybrid annuity mode); thereby increasing the financial burden on the NHAI. To overcome this, the NHAI may revert to the BOT (Toll) mode of project awarding. According to ICRA, the risk-sharing is not balanced enough, giving rise to the need to devise a new one.

Elaborating on why BOT (Toll) model may not have many takers in its current form, Mr. Rajeshwar Burla, VP & Associate Head, Corporate Ratings, ICRA said, “Risk averseness of road developers has increased over the last few years. Even today, many developers’ balance sheets cannot support huge equity investments towards BOT projects. Further, the transportation sector is undergoing transformational change with alternate modes viz. dedicated freight corridor and inland waterways which would result in a modal shift from road to these modes over the medium to long term. In addition, the road network itself is undergoing significant changes with some of the economic corridors under Bharatmala competing with few existing stretches. Overall, these factors would make the traffic forecasting extremely challenging. Therefore, BOT (Toll) model in its current form may not have many takers. Achieving financial closure also would be a challenge given these uncertainties.”

In the past, what made NHAI shift away from BOT (Toll) to BOT (HAM)? With stressed balance sheets many developers shied away from BOT (Toll) projects. Until FY2014, the mode of project award was determined based on the waterfall mechanism that explored BOT (Toll) first followed by BOT (HAM) and then EPC depending on the traffic density along the project stretch. This process slowed down the awards due to weak private sector participation. Thus, in the absence of private sector participation, shifting to EPC mode and restarting the award process was time consuming which was primary reason for low awards in FY2013 and FY2014. This process was subsequently scrapped, the committee headed by Secretary of Ministry of Road Transport and Highways (MoRTH) now decides on the mode (BOT/EPC) of project awards. One of the reasons why BOT (HAM) was successful in attracting private sector participation was due to low upfront equity requirements when compared to conventional BOT projects.

On increasing financial burden for NHAI, compliance to the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR) has led to increase in compensation by four times the market value in rural areas and twice the market value in urban areas. This in turn has led to a steep increase in land acquisition cost to upwards of Rs. 2.50 crore per hectare currently (as against Rs. 0.90 crore per hectare in FY2014). Land acquisition cost alone accounts for more than 30% of the total expenses of NHAI. Further, with around 90-92% of the awards over last few years through engineering procurement and construction (EPC, wherein NHAI has to fund 100% upfront) and BOT (HAM, wherein NHAI has to fund 40% upfront and remaining 60% over a period of 15 years) modes, the financial burden on NHAI has continued to remain high. The total debt for NHAI has increased by more than 2.4 times to Rs.1.79 lakh crore as on March 31, 2019 from Rs. 75,385 crore as on March 31, 2017.
In this context, NHAI is left with two options – a) to go slow on project awards or b) increase the mix of BOT (Toll) awards. Given the ambitious targets of Bharatmala programme, NHAI will be required to increase the mix of BOT (Toll) awards.

Mr. Burla added, “The risk sharing is not balanced in the current BOT (Toll) model. Therefore, it is time to devise a new model on the lines of BOT (HAM) to reduce the upfront equity contribution for private developers to an extent. Also, the new model should have provision to re-negotiate contracts to protect the returns of developers in case of lower-than-anticipated traffic performance especially given the challenges in traffic forecasting currently on account of likely shift to other competing modes.”

On NH awards and execution, awards were at a five-year low in FY2019 at 5,493 km (68% lower than 17,055 km awarded in FY2018) as against the target of 20,000 km for MoRTH. This was largely due to land acquisition related challenges and the general elections. However, execution remained healthy at 10,855 km in FY2019; around 10% higher than FY2018. The execution target for FY2020 has been set at 11,000 km.    

There has been a lot of debate in recent times about the need for the National Highways Authority of India (NHAI) to focus on asset monetisation and tap alternate funding avenues viz. toll-operate-transfer (TOT) and infrastructure investment trusts (InvITs) given the huge funding requirement for the ongoing Bharatmala Pariyojana programme. ICRA, in its earlier observation on this subject, has already highlighted the importance of speeding up the TOT awards and other fund-raising initiatives to meet the large funding requirements of the ambitious programme. However, the progress on both these fronts has been slow till date. To add to this, the share of the build-operate-transfer (BOT) (Toll) projects in the overall awards has declined sharply (being made primarily through the EPC/hybrid annuity mode); thereby increasing the financial burden on the NHAI. To overcome this, the NHAI may revert to the BOT (Toll) mode of project awarding. According to ICRA, the risk-sharing is not balanced enough, giving rise to the need to devise a new one.Elaborating on why BOT (Toll) model may not have many takers in its current form, Mr. Rajeshwar Burla, VP & Associate Head, Corporate Ratings, ICRA said, “Risk averseness of road developers has increased over the last few years. Even today, many developers’ balance sheets cannot support huge equity investments towards BOT projects. Further, the transportation sector is undergoing transformational change with alternate modes viz. dedicated freight corridor and inland waterways which would result in a modal shift from road to these modes over the medium to long term. In addition, the road network itself is undergoing significant changes with some of the economic corridors under Bharatmala competing with few existing stretches. Overall, these factors would make the traffic forecasting extremely challenging. Therefore, BOT (Toll) model in its current form may not have many takers. Achieving financial closure also would be a challenge given these uncertainties.”In the past, what made NHAI shift away from BOT (Toll) to BOT (HAM)? With stressed balance sheets many developers shied away from BOT (Toll) projects. Until FY2014, the mode of project award was determined based on the waterfall mechanism that explored BOT (Toll) first followed by BOT (HAM) and then EPC depending on the traffic density along the project stretch. This process slowed down the awards due to weak private sector participation. Thus, in the absence of private sector participation, shifting to EPC mode and restarting the award process was time consuming which was primary reason for low awards in FY2013 and FY2014. This process was subsequently scrapped, the committee headed by Secretary of Ministry of Road Transport and Highways (MoRTH) now decides on the mode (BOT/EPC) of project awards. One of the reasons why BOT (HAM) was successful in attracting private sector participation was due to low upfront equity requirements when compared to conventional BOT projects.On increasing financial burden for NHAI, compliance to the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR) has led to increase in compensation by four times the market value in rural areas and twice the market value in urban areas. This in turn has led to a steep increase in land acquisition cost to upwards of Rs. 2.50 crore per hectare currently (as against Rs. 0.90 crore per hectare in FY2014). Land acquisition cost alone accounts for more than 30% of the total expenses of NHAI. Further, with around 90-92% of the awards over last few years through engineering procurement and construction (EPC, wherein NHAI has to fund 100% upfront) and BOT (HAM, wherein NHAI has to fund 40% upfront and remaining 60% over a period of 15 years) modes, the financial burden on NHAI has continued to remain high. The total debt for NHAI has increased by more than 2.4 times to Rs.1.79 lakh crore as on March 31, 2019 from Rs. 75,385 crore as on March 31, 2017.In this context, NHAI is left with two options – a) to go slow on project awards or b) increase the mix of BOT (Toll) awards. Given the ambitious targets of Bharatmala programme, NHAI will be required to increase the mix of BOT (Toll) awards.Mr. Burla added, “The risk sharing is not balanced in the current BOT (Toll) model. Therefore, it is time to devise a new model on the lines of BOT (HAM) to reduce the upfront equity contribution for private developers to an extent. Also, the new model should have provision to re-negotiate contracts to protect the returns of developers in case of lower-than-anticipated traffic performance especially given the challenges in traffic forecasting currently on account of likely shift to other competing modes.”On NH awards and execution, awards were at a five-year low in FY2019 at 5,493 km (68% lower than 17,055 km awarded in FY2018) as against the target of 20,000 km for MoRTH. This was largely due to land acquisition related challenges and the general elections. However, execution remained healthy at 10,855 km in FY2019; around 10% higher than FY2018. The execution target for FY2020 has been set at 11,000 km.    

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App