Trichy IBT Link Road Delayed Until Early 2028
ROADS & HIGHWAYS

Trichy IBT Link Road Delayed Until Early 2028

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress.

In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible.

Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase.

District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress. In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible. Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase. District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

Related Stories

Gold Stories

Next Story
Products

Interio by Godrej launches modular workplace solutions

Interio by Godrej has launched Workscapes, a modular workplace solutions category designed to help organisations configure and adapt workspaces to changing requirements. The portfolio combines mobile and compatible furniture and support elements that can be rearranged across different work modes without changes to fixed layouts.Workscapes includes Collaboration Tables, Privacy Solutions, Mobile Markerboards and Space Dividers, Power Solutions, Storage and Support Elements, Meeting and Presentation Tools, and Seating Elements. The range is designed for focused work, collaboration, informal disc..

Next Story
Infrastructure Urban

CAFE-III Gives Auto Industry Investment Clarity

The government’s new Corporate Average Fuel Economy (CAFE-III) norms have provided the automobile industry with a clearer framework for technology investments, according to industry representatives. The framework seeks to balance environmental objectives with flexibility for manufacturers while encouraging the adoption of flex-fuel vehicles and biofuels. Society of Indian Automobile Manufacturers (SIAM) President Shenu Agarwal said the five-year framework would give automakers greater predictability to plan investments and accelerate innovation. He said the regulation established annual targ..

Next Story
Infrastructure Energy

Mines Ministry to Auction Two Offshore Mineral Blocks in Andaman Sea

The Ministry of Mines will launch an auction of two offshore mineral blocks in the Andaman Sea on Thursday, seeking to unlock India’s offshore mineral potential and strengthen long-term mineral resource security. The blocks will be offered under a composite licence, which permits exploration and development activities in accordance with the applicable regulatory framework. The ministry said the auction was intended to encourage systematic exploration, attract investment and promote the use of advanced technologies for offshore mineral exploration and development. The initiative is also aimed..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code