Trichy IBT Link Road Delayed Until Early 2028
ROADS & HIGHWAYS

Trichy IBT Link Road Delayed Until Early 2028

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress.

In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible.

Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase.

District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress. In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible. Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase. District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

Next Story
Infrastructure Transport

Railways To Operate Over 300 Special Trains For Rath Yatra

Union Railway Minister Ashwini Vaishnaw announced that Indian Railways (IR) will operate more than 300 special trains for the annual Jagannath Rath Yatra in Odisha and over 100 special trains during the Onam festival in Keralam. He flagged off the Nanded–Mumbai and Tanakpur–Nanded Express trains and inaugurated the extension of the Tanakpur–Pilibhit service up to Shahjahanpur via video conference from Rail Sadan in Bhubaneswar. He noted that the summer season, which concluded on 30 June, had seen a record 15,000 special trains. Vaishnaw stated that the newly launched services are intende..

Next Story
Infrastructure Transport

Vande Bharat Express To Start From Tripura Soon

Tripura Chief Minister Manik Saha said the Vande Bharat Express will commence operations from Tripura in the coming days after he flagged off the Agartala–Karimganj MEMU service at Agartala Railway Station. He recalled the rail history of the state, noting that a metre-gauge service first arrived in 1964 and that broad gauge reached Agartala in 2008 following national projects and later upgrades under the Act East policy. The event was described as a milestone for regional connectivity and the MEMU was presented as the first electric passenger train to originate from Tripura.\n\nSaha said he..

Next Story
Infrastructure Urban

MEMU Suspension Disrupts Commuters Between Vadodara And Dahod

The Vadodara–Dahod Mainline Electric Multiple Unit (MEMU) service has been temporarily suspended for 26 days after its rake was diverted to Odisha to manage the surge in passenger traffic during the annual Rath Yatra in Puri. Indian Railways redeployed several MEMU rakes from different zones to meet the additional travel demand for the festival scheduled from the seventh of July to the second of August. As a result, train numbers 69233 and 69234 operating between Vadodara and Dahod will remain cancelled for the duration. Railway authorities advised passengers to use alternative train service..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement