Trichy IBT Link Road Delayed Until Early 2028
ROADS & HIGHWAYS

Trichy IBT Link Road Delayed Until Early 2028

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress.

In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible.

Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase.

District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress. In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible. Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase. District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

Next Story
Infrastructure Transport

Surya Roshni delivers customised lighting for NCRTC RRTS stations

Surya Roshni has supplied customised indoor lighting solutions for 18 elevated stations on the National Capital Region Transport Corporation's (NCRTC) Rapid Rail Transit System (RRTS), strengthening its presence in India's infrastructure lighting segment.The project involved the design and deployment of lighting systems for platforms, concourses, foot overbridges (FOBs) and back-of-house (BOH) areas. According to the company, the luminaires were developed specifically to meet NCRTC's design, operational and performance requirements rather than using standard products.Surya introduced two custo..

Next Story
Real Estate

Hilton debuts Tapestry Collection brand in Vietnam

Hilton has opened NHAAN Resort & Spa Hoi An, Tapestry Collection by Hilton, marking the debut of the Tapestry Collection brand in Vietnam and expanding its lifestyle hospitality portfolio in Southeast Asia.Located along the Co Co River in Cam Thanh village, the 174-key resort provides access to Hoi An Ancient Town, Cua Dai Beach and the Cam Thanh Nipa Forest. The property has been designed by Vietnamese architect Vo Trong Nghia, incorporating biophilic architecture, locally sourced materials and riverfront landscapes.The resort offers a mix of guest rooms and suites, including family-frien..

Next Story
Building Material

Electrent expands lithium energy storage system portfolio

Electrent Energy has expanded its lithium-based energy storage portfolio with the launch of the ESS 850 and ESS 1050, targeting compact and maintenance-free power backup solutions for Indian homes.The new systems integrate a Home UPS and a LiFePO4 lithium battery into a single unit, extending the company's product range following the launch of its ESS 1350 and ESS 2500 models.Designed for apartments and smaller homes, the ESS 850 provides up to 1 hour 15 minutes of backup, while the ESS 1050 offers up to 1 hour 45 minutes on a typical 400 W household load. The systems can power essential appli..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement