Trichy IBT Link Road Delayed Until Early 2028
ROADS & HIGHWAYS

Trichy IBT Link Road Delayed Until Early 2028

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress.

In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible.

Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase.

District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

The Tiruchirappalli Corporation has revised the timeline for the Integrated Bus Terminus link road project, saying completion will take at least 18 more months and now extend close to early 2028. The project is designed to link the Panjapur Integrated Bus Terminus with major state and national highways serving Trichy and has been planned in three phases. Revised projections followed the identification of multiple hurdles in land acquisition and pending statutory approvals that have slowed progress. In Phase One, which covers the stretch between Panjapur and Karumandapam nodes and was sanctioned at Rs 817 mn, around 35 per cent of the work has been completed. Progress on this section has been held up by delays in obtaining approval from the Southern Railway for a Railway Road over Bridge (RoB) at E Pudur MGR Nagar and by restricted site access. Officials indicated that partial completion previously anticipated between October and December 2026 is no longer feasible. Phase Two, covering the Woraiyur–Kudamurutti checkpost section, has recorded about 15 per cent completion largely because land acquisition remains incomplete. Phase Three, the longest and most complex segment connecting densely populated Karumandapam and Woraiyur areas, has not yet received administrative sanction and includes five elevated stretches, one of them near the Woraiyur Kasivilangi fish market. Authorities warned that the project will not fully serve its intended purpose without the third phase. District Collector Pratik Tayal inspected works along the Koraiyar and Kudamurutti river banks and reviewed progress, while officials said land requirement for the scheme has been reduced from eight acres to about one acre though permission to enter sites and access issues persist. They reported that only about half of affected landowners have accepted the compensation package and that, excluding Phase Three, remaining work could be completed within a year once clearances are in place. A local road users trust representative urged the state government to fast?track clearances and funding to ease city congestion.

Related Stories

Gold Stories

Next Story
Products

Walplast reports strong Q1 growth

Walplast Products has reported strong year-on-year growth across key categories in its HomeSure portfolio during the April–June 2026 quarter, driven by product expansion, manufacturing capabilities and wider distribution.HomeSure GypEx Walbond recorded the highest growth at 157 per cent, followed by HomeSure GypEx Gypsum Plaster at 97 per cent and HomeSure TileEx Tile Adhesive at 75 per cent. Textures grew by 55 per cent, while HomeSure Wall Putty and HomeSure TileEx Tile Cleaner recorded 40 per cent growth each. HomeSure TileEx Cementitious Tile Grout grew by 25 per cent.The company has exp..

Next Story
Technology

Matrix Geo completes 314-km highway survey

Matrix Geo Solutions has completed a geospatial survey assignment covering approximately 314 km across five highway sections under LOT-2/HARYANA/Package-1 for RITES, on behalf of the National Highways Authority of India.The assignment formed part of consultancy services for preparing Detailed Project Reports for economic corridors, inter-corridor and feeder routes. The scope included Aerial and Mobile LiDAR surveys, UAV-based topographic mapping, Ground Penetrating Radar utility mapping, Final Location Survey, land acquisition support and digitisation of cadastral maps.The five sections covere..

Next Story
Real Estate

Sugee enters Thane with Lake District

Sugee Group has announced its entry into the Thane market with Sugee Lake District, a 52-acre waterfront development in Thane West that will bring together commercial, retail, hospitality and lifestyle spaces.Located opposite Korum Mall near Cadbury Junction in Khopat, the Eastern Express Highway-facing development will feature Grade A++ office spaces with views of Siddheshwar Lake and the city. The project will also include high-street retail, dining and a six-acre lakeview promenade.The development has been registered under the LEED green building rating system and has been designed by Archi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement