Trichy IBT Link Road Project Delayed Until 2028
RAILWAYS & METRO RAIL

Trichy IBT Link Road Project Delayed Until 2028

The Tiruchirappalli Corporation's Integrated Bus Terminus (IBT) link road project has been delayed and is now expected to be completed in early 2028 instead of the earlier target of late 2026. The revision follows setbacks in land acquisition, pending statutory railway approvals and the absence of administrative sanction for the final phase, which have slowed construction activity around the city transport hub.

The link road is being developed to connect the Panjapur Integrated Bus Terminus with major state and national highways passing through Tiruchirappalli. Once finished, the corridor is intended to improve access to the bus terminus, reduce congestion on existing city roads and facilitate smoother movement of passenger and commercial traffic.

The project is divided into three phases. Phase I, connecting Panjapur and Karumandapam, was sanctioned at Rs 817 mn and has about 35 per cent of the work completed, but progress has slowed because approval is still pending from the Southern Railway for a road overbridge near E Pudur MGR Nagar. Phase II, covering the Woraiyur–Kudamurutti checkpost stretch, has reached around 15 per cent completion and is held up mainly by delays in acquiring land required for the alignment.

The third and longest phase, connecting Karumandapam and Woraiyur, has not received administrative sanction and comprises multiple elevated stretches designed to ease traffic through densely populated areas, including an elevated segment near the Woraiyur Kasivilangi fish market. District Collector Pratik Tayal recently reviewed progress and inspected works along the Koraiyar and Kudamurutti riverbanks. The proposed corridor will eventually link the Trichy–Madurai National Highway and the Trichy–Karur National Highway, improving regional connectivity.

The IBT link road is considered a key supporting infrastructure project for the Panjapur IBT and is expected to improve traffic distribution, shorten bus travel times and enhance connectivity between the western and southern corridors of the city. Work on the approved phases will continue while authorities seek to expedite land acquisition, secure railway approvals and obtain administrative clearance for the remaining section to meet the revised early 2028 target.

The Tiruchirappalli Corporation's Integrated Bus Terminus (IBT) link road project has been delayed and is now expected to be completed in early 2028 instead of the earlier target of late 2026. The revision follows setbacks in land acquisition, pending statutory railway approvals and the absence of administrative sanction for the final phase, which have slowed construction activity around the city transport hub. The link road is being developed to connect the Panjapur Integrated Bus Terminus with major state and national highways passing through Tiruchirappalli. Once finished, the corridor is intended to improve access to the bus terminus, reduce congestion on existing city roads and facilitate smoother movement of passenger and commercial traffic. The project is divided into three phases. Phase I, connecting Panjapur and Karumandapam, was sanctioned at Rs 817 mn and has about 35 per cent of the work completed, but progress has slowed because approval is still pending from the Southern Railway for a road overbridge near E Pudur MGR Nagar. Phase II, covering the Woraiyur–Kudamurutti checkpost stretch, has reached around 15 per cent completion and is held up mainly by delays in acquiring land required for the alignment. The third and longest phase, connecting Karumandapam and Woraiyur, has not received administrative sanction and comprises multiple elevated stretches designed to ease traffic through densely populated areas, including an elevated segment near the Woraiyur Kasivilangi fish market. District Collector Pratik Tayal recently reviewed progress and inspected works along the Koraiyar and Kudamurutti riverbanks. The proposed corridor will eventually link the Trichy–Madurai National Highway and the Trichy–Karur National Highway, improving regional connectivity. The IBT link road is considered a key supporting infrastructure project for the Panjapur IBT and is expected to improve traffic distribution, shorten bus travel times and enhance connectivity between the western and southern corridors of the city. Work on the approved phases will continue while authorities seek to expedite land acquisition, secure railway approvals and obtain administrative clearance for the remaining section to meet the revised early 2028 target.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code