Trichy IBT Link Road Project Delayed Until 2028
RAILWAYS & METRO RAIL

Trichy IBT Link Road Project Delayed Until 2028

The Tiruchirappalli Corporation's Integrated Bus Terminus (IBT) link road project has been delayed and is now expected to be completed in early 2028 instead of the earlier target of late 2026. The revision follows setbacks in land acquisition, pending statutory railway approvals and the absence of administrative sanction for the final phase, which have slowed construction activity around the city transport hub.

The link road is being developed to connect the Panjapur Integrated Bus Terminus with major state and national highways passing through Tiruchirappalli. Once finished, the corridor is intended to improve access to the bus terminus, reduce congestion on existing city roads and facilitate smoother movement of passenger and commercial traffic.

The project is divided into three phases. Phase I, connecting Panjapur and Karumandapam, was sanctioned at Rs 817 mn and has about 35 per cent of the work completed, but progress has slowed because approval is still pending from the Southern Railway for a road overbridge near E Pudur MGR Nagar. Phase II, covering the Woraiyur–Kudamurutti checkpost stretch, has reached around 15 per cent completion and is held up mainly by delays in acquiring land required for the alignment.

The third and longest phase, connecting Karumandapam and Woraiyur, has not received administrative sanction and comprises multiple elevated stretches designed to ease traffic through densely populated areas, including an elevated segment near the Woraiyur Kasivilangi fish market. District Collector Pratik Tayal recently reviewed progress and inspected works along the Koraiyar and Kudamurutti riverbanks. The proposed corridor will eventually link the Trichy–Madurai National Highway and the Trichy–Karur National Highway, improving regional connectivity.

The IBT link road is considered a key supporting infrastructure project for the Panjapur IBT and is expected to improve traffic distribution, shorten bus travel times and enhance connectivity between the western and southern corridors of the city. Work on the approved phases will continue while authorities seek to expedite land acquisition, secure railway approvals and obtain administrative clearance for the remaining section to meet the revised early 2028 target.

The Tiruchirappalli Corporation's Integrated Bus Terminus (IBT) link road project has been delayed and is now expected to be completed in early 2028 instead of the earlier target of late 2026. The revision follows setbacks in land acquisition, pending statutory railway approvals and the absence of administrative sanction for the final phase, which have slowed construction activity around the city transport hub. The link road is being developed to connect the Panjapur Integrated Bus Terminus with major state and national highways passing through Tiruchirappalli. Once finished, the corridor is intended to improve access to the bus terminus, reduce congestion on existing city roads and facilitate smoother movement of passenger and commercial traffic. The project is divided into three phases. Phase I, connecting Panjapur and Karumandapam, was sanctioned at Rs 817 mn and has about 35 per cent of the work completed, but progress has slowed because approval is still pending from the Southern Railway for a road overbridge near E Pudur MGR Nagar. Phase II, covering the Woraiyur–Kudamurutti checkpost stretch, has reached around 15 per cent completion and is held up mainly by delays in acquiring land required for the alignment. The third and longest phase, connecting Karumandapam and Woraiyur, has not received administrative sanction and comprises multiple elevated stretches designed to ease traffic through densely populated areas, including an elevated segment near the Woraiyur Kasivilangi fish market. District Collector Pratik Tayal recently reviewed progress and inspected works along the Koraiyar and Kudamurutti riverbanks. The proposed corridor will eventually link the Trichy–Madurai National Highway and the Trichy–Karur National Highway, improving regional connectivity. The IBT link road is considered a key supporting infrastructure project for the Panjapur IBT and is expected to improve traffic distribution, shorten bus travel times and enhance connectivity between the western and southern corridors of the city. Work on the approved phases will continue while authorities seek to expedite land acquisition, secure railway approvals and obtain administrative clearance for the remaining section to meet the revised early 2028 target.

Related Stories

Gold Stories

Next Story
Products

Walplast reports strong Q1 growth

Walplast Products has reported strong year-on-year growth across key categories in its HomeSure portfolio during the April–June 2026 quarter, driven by product expansion, manufacturing capabilities and wider distribution.HomeSure GypEx Walbond recorded the highest growth at 157 per cent, followed by HomeSure GypEx Gypsum Plaster at 97 per cent and HomeSure TileEx Tile Adhesive at 75 per cent. Textures grew by 55 per cent, while HomeSure Wall Putty and HomeSure TileEx Tile Cleaner recorded 40 per cent growth each. HomeSure TileEx Cementitious Tile Grout grew by 25 per cent.The company has exp..

Next Story
Technology

Matrix Geo completes 314-km highway survey

Matrix Geo Solutions has completed a geospatial survey assignment covering approximately 314 km across five highway sections under LOT-2/HARYANA/Package-1 for RITES, on behalf of the National Highways Authority of India.The assignment formed part of consultancy services for preparing Detailed Project Reports for economic corridors, inter-corridor and feeder routes. The scope included Aerial and Mobile LiDAR surveys, UAV-based topographic mapping, Ground Penetrating Radar utility mapping, Final Location Survey, land acquisition support and digitisation of cadastral maps.The five sections covere..

Next Story
Real Estate

Sugee enters Thane with Lake District

Sugee Group has announced its entry into the Thane market with Sugee Lake District, a 52-acre waterfront development in Thane West that will bring together commercial, retail, hospitality and lifestyle spaces.Located opposite Korum Mall near Cadbury Junction in Khopat, the Eastern Express Highway-facing development will feature Grade A++ office spaces with views of Siddheshwar Lake and the city. The project will also include high-street retail, dining and a six-acre lakeview promenade.The development has been registered under the LEED green building rating system and has been designed by Archi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement