+
Trichy Junction Road Overbridge Stage II to Open in June
ROADS & HIGHWAYS

Trichy Junction Road Overbridge Stage II to Open in June

The long-delayed Stage II of the Trichy Junction Road Overbridge (RoB) is scheduled for commissioning in June, with the State Highways Department (SHD) and Southern Railway (SR) expediting works on their respective sections. The completion target follows renewed coordination between the agencies and a concentrated effort to resolve earlier delays. Officials have prioritised the final structural and approach works to ensure the planned opening.

Railway sources indicated that a steel girder for the portion of the bridge above the tracks near Trichy Junction railway station had been procured and that one of the two spans for the bowstring bridge, modelled on the new Kollidam bridge, had been brought in from Katpadi. They added that assembling and welding operations had begun and that another span was expected soon. Heavy machinery, including a crane, was to be mobilised to place the span on supporting columns.

Concurrently, the State Highways Department accelerated construction of retaining walls and approach ramps for the RoB's multiple arms, focusing on timely completion of earthworks and concrete works. Work sequencing was adjusted to allow parallel progress on different arms and to reduce dependency on single critical tasks. The combined approach by SHD and SR aimed to maintain momentum and mitigate further schedule slippage ahead of June.

The project team assessed that opening Stage II would ease traffic congestion around Trichy Junction and improve connectivity for commuters and freight movements in the city. Contractors were instructed to maintain safety and quality controls while working to the compressed timetable. Authorities indicated that close monitoring and contingency arrangements were in place to address any remaining supply or logistical challenges before formal commissioning.

The long-delayed Stage II of the Trichy Junction Road Overbridge (RoB) is scheduled for commissioning in June, with the State Highways Department (SHD) and Southern Railway (SR) expediting works on their respective sections. The completion target follows renewed coordination between the agencies and a concentrated effort to resolve earlier delays. Officials have prioritised the final structural and approach works to ensure the planned opening. Railway sources indicated that a steel girder for the portion of the bridge above the tracks near Trichy Junction railway station had been procured and that one of the two spans for the bowstring bridge, modelled on the new Kollidam bridge, had been brought in from Katpadi. They added that assembling and welding operations had begun and that another span was expected soon. Heavy machinery, including a crane, was to be mobilised to place the span on supporting columns. Concurrently, the State Highways Department accelerated construction of retaining walls and approach ramps for the RoB's multiple arms, focusing on timely completion of earthworks and concrete works. Work sequencing was adjusted to allow parallel progress on different arms and to reduce dependency on single critical tasks. The combined approach by SHD and SR aimed to maintain momentum and mitigate further schedule slippage ahead of June. The project team assessed that opening Stage II would ease traffic congestion around Trichy Junction and improve connectivity for commuters and freight movements in the city. Contractors were instructed to maintain safety and quality controls while working to the compressed timetable. Authorities indicated that close monitoring and contingency arrangements were in place to address any remaining supply or logistical challenges before formal commissioning.

Next Story
Infrastructure Energy

Jyoti Structures expands manufacturing capacity in Nashik

The announcement Jyoti Structures (JSL) reported steady operational performance in 2025, supported by stable project execution across its power transmission portfolio. The company commissioned galvanisation operations at its second Nashik manufacturing unit, adding 33,000 MT of annual capacity. This increased aggregate tower manufacturing capability at Nashik to approximately 69,000 MT per annum, aimed at improving fabrication accuracy, scheduling control and delivery predictability. JSL also expanded its workforce to over 750 employees, onboarding more than 70 engineers during the year. C..

Next Story
Infrastructure Energy

TSPL Mega Health Camp Reaches 338 Residents in Mansa

Talwandi Sabo Power (TSPL), Punjab’s largest and North India’s largest private thermal power plant, organised a Mega Health Camp at Village Raipur, Mansa, under its flagship healthcare initiative Project SEHAT. The camp benefitted 338 community members through free consultations and diagnostic services.A team comprising a General Physician, Gynaecologist, Dermatologist and Dentist provided medical advice and treatment. Beneficiaries received free diagnostic tests including BP, HB, blood sugar, malaria, dengue and blood group tests, along with free medicines.The camp was inaugurated by Vill..

Next Story
Infrastructure Transport

Mumbai Coastal Road Musical Path Plays Jai Ho

Mumbai inaugurated India’s first musical path on the Coastal Road that plays the song Jai Ho for motorists. The civic administration said the installation used Hungarian technology and that the intention was to implement the concept of Sangeet Marg in future projects. A senior official suggested implementing a pilot on the Samruddhi Expressway, which connects Mumbai and Nagpur. City officials described the inauguration as a symbolic demonstration of collaboration between municipal authorities and foreign partners. The inauguration was attended by the Consul General of Hungary Ferenc Jari, f..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App