Trichy Junction Road Overbridge Stage II to Open in June
ROADS & HIGHWAYS

Trichy Junction Road Overbridge Stage II to Open in June

The long-delayed Stage II of the Trichy Junction Road Overbridge (RoB) is scheduled for commissioning in June, with the State Highways Department (SHD) and Southern Railway (SR) expediting works on their respective sections. The completion target follows renewed coordination between the agencies and a concentrated effort to resolve earlier delays. Officials have prioritised the final structural and approach works to ensure the planned opening.

Railway sources indicated that a steel girder for the portion of the bridge above the tracks near Trichy Junction railway station had been procured and that one of the two spans for the bowstring bridge, modelled on the new Kollidam bridge, had been brought in from Katpadi. They added that assembling and welding operations had begun and that another span was expected soon. Heavy machinery, including a crane, was to be mobilised to place the span on supporting columns.

Concurrently, the State Highways Department accelerated construction of retaining walls and approach ramps for the RoB's multiple arms, focusing on timely completion of earthworks and concrete works. Work sequencing was adjusted to allow parallel progress on different arms and to reduce dependency on single critical tasks. The combined approach by SHD and SR aimed to maintain momentum and mitigate further schedule slippage ahead of June.

The project team assessed that opening Stage II would ease traffic congestion around Trichy Junction and improve connectivity for commuters and freight movements in the city. Contractors were instructed to maintain safety and quality controls while working to the compressed timetable. Authorities indicated that close monitoring and contingency arrangements were in place to address any remaining supply or logistical challenges before formal commissioning.

The long-delayed Stage II of the Trichy Junction Road Overbridge (RoB) is scheduled for commissioning in June, with the State Highways Department (SHD) and Southern Railway (SR) expediting works on their respective sections. The completion target follows renewed coordination between the agencies and a concentrated effort to resolve earlier delays. Officials have prioritised the final structural and approach works to ensure the planned opening. Railway sources indicated that a steel girder for the portion of the bridge above the tracks near Trichy Junction railway station had been procured and that one of the two spans for the bowstring bridge, modelled on the new Kollidam bridge, had been brought in from Katpadi. They added that assembling and welding operations had begun and that another span was expected soon. Heavy machinery, including a crane, was to be mobilised to place the span on supporting columns. Concurrently, the State Highways Department accelerated construction of retaining walls and approach ramps for the RoB's multiple arms, focusing on timely completion of earthworks and concrete works. Work sequencing was adjusted to allow parallel progress on different arms and to reduce dependency on single critical tasks. The combined approach by SHD and SR aimed to maintain momentum and mitigate further schedule slippage ahead of June. The project team assessed that opening Stage II would ease traffic congestion around Trichy Junction and improve connectivity for commuters and freight movements in the city. Contractors were instructed to maintain safety and quality controls while working to the compressed timetable. Authorities indicated that close monitoring and contingency arrangements were in place to address any remaining supply or logistical challenges before formal commissioning.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement