+
Trichy Junction Road Overbridge Stage II to Open in June
ROADS & HIGHWAYS

Trichy Junction Road Overbridge Stage II to Open in June

The long-delayed Stage II of the Trichy Junction Road Overbridge (RoB) is scheduled for commissioning in June, with the State Highways Department (SHD) and Southern Railway (SR) expediting works on their respective sections. The completion target follows renewed coordination between the agencies and a concentrated effort to resolve earlier delays. Officials have prioritised the final structural and approach works to ensure the planned opening.

Railway sources indicated that a steel girder for the portion of the bridge above the tracks near Trichy Junction railway station had been procured and that one of the two spans for the bowstring bridge, modelled on the new Kollidam bridge, had been brought in from Katpadi. They added that assembling and welding operations had begun and that another span was expected soon. Heavy machinery, including a crane, was to be mobilised to place the span on supporting columns.

Concurrently, the State Highways Department accelerated construction of retaining walls and approach ramps for the RoB's multiple arms, focusing on timely completion of earthworks and concrete works. Work sequencing was adjusted to allow parallel progress on different arms and to reduce dependency on single critical tasks. The combined approach by SHD and SR aimed to maintain momentum and mitigate further schedule slippage ahead of June.

The project team assessed that opening Stage II would ease traffic congestion around Trichy Junction and improve connectivity for commuters and freight movements in the city. Contractors were instructed to maintain safety and quality controls while working to the compressed timetable. Authorities indicated that close monitoring and contingency arrangements were in place to address any remaining supply or logistical challenges before formal commissioning.

The long-delayed Stage II of the Trichy Junction Road Overbridge (RoB) is scheduled for commissioning in June, with the State Highways Department (SHD) and Southern Railway (SR) expediting works on their respective sections. The completion target follows renewed coordination between the agencies and a concentrated effort to resolve earlier delays. Officials have prioritised the final structural and approach works to ensure the planned opening. Railway sources indicated that a steel girder for the portion of the bridge above the tracks near Trichy Junction railway station had been procured and that one of the two spans for the bowstring bridge, modelled on the new Kollidam bridge, had been brought in from Katpadi. They added that assembling and welding operations had begun and that another span was expected soon. Heavy machinery, including a crane, was to be mobilised to place the span on supporting columns. Concurrently, the State Highways Department accelerated construction of retaining walls and approach ramps for the RoB's multiple arms, focusing on timely completion of earthworks and concrete works. Work sequencing was adjusted to allow parallel progress on different arms and to reduce dependency on single critical tasks. The combined approach by SHD and SR aimed to maintain momentum and mitigate further schedule slippage ahead of June. The project team assessed that opening Stage II would ease traffic congestion around Trichy Junction and improve connectivity for commuters and freight movements in the city. Contractors were instructed to maintain safety and quality controls while working to the compressed timetable. Authorities indicated that close monitoring and contingency arrangements were in place to address any remaining supply or logistical challenges before formal commissioning.

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement