Underwater tunnel works of Mumbai’s coastal road project delayed
ROADS & HIGHWAYS

Underwater tunnel works of Mumbai’s coastal road project delayed

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed.

So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected.

Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year.

The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments.

Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months.

This was supposed to happen early next year. There appears to be a chance of a delay now.

While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed.

The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore.

Image Source


Also read: Mumbai coastal road project 36% completed: BMC

Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed. So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected. Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year. The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments. Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months. This was supposed to happen early next year. There appears to be a chance of a delay now. While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed. The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore. Image Source Also read: Mumbai coastal road project 36% completed: BMC Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Related Stories

Gold Stories

Next Story
Infrastructure Urban

KONE Opens India's First Digital Experience Centre in Pune

KONE, a global elevator and escalator manufacturer, has inaugurated its first Digital Experience Centre (DEC) in India, located in Pune. The facility aims to showcase how artificial intelligence (AI), connectivity and data-driven technologies can enhance customer experiences and improve building operations.The centre was inaugurated by Jussi Herlin, Executive Vice Chair, KONE Corporation; Philippe Delorme, President and CEO, KONE; and Nandan Nilekani, Co-founder and Chairman of the Board, Infosys.Designed as an interactive customer environment, the facility demonstrates digital solutions cover..

Next Story
Infrastructure Urban

CII GreenCo Launches Circularity Guidelines for Indian Industry

The Confederation of Indian Industry (CII) GreenCo Council has launched the CII GreenCo Circularity Guidelines – Pilot Version at the 17th CII GreenCo Waste & Resource Management Summit 2026 in Chennai. The initiative aims to strengthen resource efficiency, waste reduction and circular economy practices across Indian manufacturing and process industries.The guidelines introduce a structured framework with circularity indices covering raw materials, consumables, packaging and other resource inputs. These indicators will help industries assess existing practices, identify opportunities to ..

Next Story
Infrastructure Energy

Global Electronics Association Launches IPC-1783-CO2E Standard

The Global Electronics Association has introduced IPC-1783-CO2E, a new international standard aimed at improving consistency, transparency and comparability in product carbon footprint reporting across the electronics manufacturing industry.The standard, titled International Standard for Data Collection and Reporting of CO2 Equivalent (CO2e) Emissions for the Electronics Manufacturing Supply Chain, provides industry-specific guidance for collecting, estimating and reporting carbon emissions data.With increasing regulatory requirements and customer expectations, electronics manufacturers face c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code