Underwater tunnel works of Mumbai’s coastal road project delayed
ROADS & HIGHWAYS

Underwater tunnel works of Mumbai’s coastal road project delayed

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed.

So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected.

Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year.

The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments.

Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months.

This was supposed to happen early next year. There appears to be a chance of a delay now.

While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed.

The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore.

Image Source


Also read: Mumbai coastal road project 36% completed: BMC

Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed. So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected. Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year. The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments. Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months. This was supposed to happen early next year. There appears to be a chance of a delay now. While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed. The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore. Image Source Also read: Mumbai coastal road project 36% completed: BMC Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement