Underwater tunnel works of Mumbai’s coastal road project delayed
ROADS & HIGHWAYS

Underwater tunnel works of Mumbai’s coastal road project delayed

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed.

So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected.

Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year.

The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments.

Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months.

This was supposed to happen early next year. There appears to be a chance of a delay now.

While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed.

The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore.

Image Source


Also read: Mumbai coastal road project 36% completed: BMC

Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed. So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected. Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year. The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments. Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months. This was supposed to happen early next year. There appears to be a chance of a delay now. While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed. The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore. Image Source Also read: Mumbai coastal road project 36% completed: BMC Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Next Story
Real Estate

Heena Lalwani Buys Rs 1.13 Billion Juhu Apartment

Heena Lalwani, promoter of Aatman Innovations Private Limited, has purchased a luxury apartment worth Rs 1.13 billion in Mumbai’s upscale Juhu locality, according to property registration documents accessed by Zapkey.com.The 9,862 sq ft apartment, located on the 10th floor of Lodha Developers’ Avalon Tower, was acquired at Rs 115,000 per sq ft and comes with five car parking spaces. The deal, registered on 18 August 2025, also included the payment of Rs 68 million in stamp duty and a Rs 30,000 registration fee.Lodha Developers did not respond to queries regarding the transaction, while the..

Next Story
Real Estate

Godrej Buys KPHB Land for Rs 7 Billion in E-Auction

An acre of prime land in Kukatpally Housing Board (KPHB), Hyderabad, was auctioned for Rs 7 billion, with the Telangana Housing Board generating Rs 5.47 billion from the sale of 7.8 acres through e-auction on 20 August 2025.The auction notification was issued last month, attracting bids from Godrej Properties, Aurobindo Realty, Prestige Estates, and Ashoka Builders, according to Board vice-chairman V.P. Gautham. With an offset price of Rs 4 billion per acre, the three-hour auction saw 46 bid increases, before Godrej Properties acquired the land.Revenue generated from the auction will be utilis..

Next Story
Real Estate

HMDA to Auction 93 Prime Plots in September

The Hyderabad Metropolitan Development Authority (HMDA) is preparing to conduct a three-day auction of prime open plots across Hyderabad, Rangareddy, and Medchal-Malkajgiri districts this September.According to official reports, the e-auction will take place on 17, 18, and 19 September, offering 93 plots. Of these, 70 are located in the Bachupally HMDA layout, with the remainder spread across Turkayamjal, Kokapet, Poppalguda, Chandanagar, Bairagiguda, Gandi Maisamma, Suraram, Medipally, and Bachupally village.The highest upset price has been fixed at Rs 175,000 per square yard for a land parce..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?