Avinashi Flyover: Huge Iron Span to be Placed Over Railway Overbridge
RAILWAYS & METRO RAIL

Avinashi Flyover: Huge Iron Span to be Placed Over Railway Overbridge

A senior official from the Special Project Wing explained that a concrete deck of such length was not practical across active railway lines. Therefore, the department had decided to opt for a specially fabricated iron span.

With the span now ready, its installation is awaiting railway clearance. The Salem Division of Southern Railway has already given its approval, while the final clearance is still pending from the Southern Railway headquarters in Chennai. For the installation process, railway operations under the ROB will need to be suspended for at least five days.

The official also mentioned that once the iron span is installed, it will be reinforced with concrete to ensure structural stability and durability. The flyover will feature eight ramps — four entry and four exit points — strategically located at key junctions such as Anna Statue, Nava India, Hope College, and near the airport.

Signaling renewed momentum in the project, an internal auditing team from the State Highways Department recently conducted an inspection of the on-going work. The team, led by Ramesh, Superintending Engineer (Construction & Maintenance) from the Coimbatore Division, and Saravana Selvam, Divisional Engineer from the Pollachi Division, reviewed the site and evaluated the progress of the elevated corridor.

With the final phase of construction underway, residents of Coimbatore can soon anticipate significant relief from the chronic traffic congestion on Avinashi Road. Valued at Rs 16.21 billion, the project is not only a major infrastructure development but also stands as a testament to persistence in overcoming logistical and engineering challenges.


News source: New Indian Express

A senior official from the Special Project Wing explained that a concrete deck of such length was not practical across active railway lines. Therefore, the department had decided to opt for a specially fabricated iron span.With the span now ready, its installation is awaiting railway clearance. The Salem Division of Southern Railway has already given its approval, while the final clearance is still pending from the Southern Railway headquarters in Chennai. For the installation process, railway operations under the ROB will need to be suspended for at least five days.The official also mentioned that once the iron span is installed, it will be reinforced with concrete to ensure structural stability and durability. The flyover will feature eight ramps — four entry and four exit points — strategically located at key junctions such as Anna Statue, Nava India, Hope College, and near the airport.Signaling renewed momentum in the project, an internal auditing team from the State Highways Department recently conducted an inspection of the on-going work. The team, led by Ramesh, Superintending Engineer (Construction & Maintenance) from the Coimbatore Division, and Saravana Selvam, Divisional Engineer from the Pollachi Division, reviewed the site and evaluated the progress of the elevated corridor.With the final phase of construction underway, residents of Coimbatore can soon anticipate significant relief from the chronic traffic congestion on Avinashi Road. Valued at Rs 16.21 billion, the project is not only a major infrastructure development but also stands as a testament to persistence in overcoming logistical and engineering challenges.News source: New Indian Express

Next Story
Infrastructure Transport

Metro Line 2B Phase 1 to Boost Realty in Mumbai’s Eastern Suburbs

Mumbai’s real estate sector is set for a major boost as Phase 1 of Metro Line 2B, between Mandale and Diamond Garden, nears completion. The Mumbai Metropolitan Region Development Authority (MMRDA) has confirmed that mandatory rectifications are done, and inspections by the Commissioner of Metro Railway Safety (CMRS) have been carried out. The 5.39-km stretch with five stations forms part of the larger DN Nagar–Mandale corridor, designed to ease congestion and improve east–west connectivity. Passenger operations are expected by December 2025, with the full line slated for 2027. ..

Next Story
Resources

WattPower wins Best Inverter award at Global Solar Expo 2025

WattPower, a leading renewable energy solutions provider, has won the award for “Best Inverter in the Utility Segment” at the Global Solar Expo 2025. The recognition underscores the company’s commitment to delivering reliable, high-performance and future-ready solar solutions for large-scale projects. At the forefront of utility-scale solar, WattPower manufactures advanced string inverters that directly feed power into the Indian grid. With robust technology, high-quality components and comprehensive product lifecycle support, its solutions stand among the most sophisticated in the ..

Next Story
Real Estate

Awfis delivers 67,000 sq. ft. innovation hub for eBay in Bengaluru

Awfis Space Solutions, India’s largest flexible workspace provider and the first publicly listed workspace solutions platform, has partnered with eBay to establish a 67,000 sq. ft. innovation hub at Embassy Tech Village, Bengaluru. The mandate covers design, build and management of the new office, which will act as a strategic hub supporting diverse functions and accelerating eBay’s AI-first commerce strategy. The centre will focus on artificial intelligence, engineering, product development and applied research, strengthening eBay’s growth in India. Embassy Tech Village, North Beng..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?