Chennai Metro: Work under Adyar River to begin in Sept
RAILWAYS & METRO RAIL

Chennai Metro: Work under Adyar River to begin in Sept

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.

Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.

An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.

The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Next Story
Resources

G R Infraprojects Founder Vinod Agarwal Passes Away

Vinod Kumar Agarwal, Founder and Promoter of G R Infraprojects, has passed away. He had been associated with the company since its inception in 1995. His vision, determination and entrepreneurial acumen laid the foundation for the company and helped shape its growth into a leading name in India’s infrastructure sector.Agarwal served as Managing Director from 2008 to 2021 and later as Chairman and Whole-time Director from 2021 to 2025. He stepped down from the office of Director on 10 November 2025. During his leadership tenure, the company moved through significant phases of growth, operatio..

Next Story
Infrastructure Energy

Centre Prioritising Energy Security With Coal Gasification

Union minister for Coal and Mines G Kishan Reddy said the Centre is prioritising energy security through a strategic shift to coal gasification and has announced incentives totalling Rs 460 billion (bn) to support the effort. He said more than 35 companies will start coal gasification activities in India within two months and that the government is encouraging firms that bring technology to close the domestic technology gap. The minister described the initiative as aimed at reducing import dependence and developing indigenous capacity. India has the fifth-largest coal reserve in the world, and..

Next Story
Infrastructure Urban

BHEL and Coal India Invest Rs 250 bn in Odisha Gasification

Bharat Heavy Electricals (BHEL) and Coal India (CIL) are jointly investing Rs 250 billion in a coal gasification project in Odisha, with the Prime Minister laying the foundation stone in Jharsuguda. Union Coal and Mines Minister G Kishan Reddy described the initiative as a transformative shift in coal utilisation that will open industrial avenues for the state. The project moves coal beyond conventional power generation to industrial feedstocks. Coal gasification will convert coal into synthesis gas, a versatile feedstock for chemicals, fertilisers and synthetic fuels, and the technology is ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement