Chennai Metro: Work under Adyar River to begin in Sept
RAILWAYS & METRO RAIL

Chennai Metro: Work under Adyar River to begin in Sept

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.

Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.

An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.

The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Get CW App