Chennai Metro: Work under Adyar River to begin in Sept
RAILWAYS & METRO RAIL

Chennai Metro: Work under Adyar River to begin in Sept

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.

Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.

An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.

The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement