Chennai Metro: Work under Adyar River to begin in Sept
RAILWAYS & METRO RAIL

Chennai Metro: Work under Adyar River to begin in Sept

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.

Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.

An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.

The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Commencing this September, construction activities will initiate beneath the Adyar vicinity, adjacent to the Greenways Road Metro Station. The upcoming project involves the utilisation of a tunnel boring apparatus to excavate a tunnel spanning 400 m in length, positioned at a depth of 20 m beneath the river's surface.Back in February, the excavation process kicked off as the tunnel boring machine known as Kaveri embarked on its journey beneath the RA Puram corporation playground. Currently, the machine has covered a distance of 120 m, with its destination set to be the river. Once this endeavour is concluded, the resultant tunnel will seamlessly link the Greenways Road Metro Station with the Adyar Junction Station, effectively stretching across a distance of 1.2 km.An engineer working on-site has informed that the tunnel boring machine is presently advancing at a pace of 1.5 m per day. This deliberate pace is imperative due to the presence of various structures situated above ground, including a petrol station and a college. Accelerating the machine's speed could potentially give rise to structural issues and damages.The tunnel boring machine will persist in its subterranean voyage, traversing beneath Durgabai Deshmukh Road and navigating under the Adyar River in the vicinity of the Thiru. Vi.Ka Bridge, prior to ultimately reaching the station presently under construction at Adyar Junction.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement