ECoR completes 700 m escape tunnel for railway project in Boudh, Odisha
RAILWAYS & METRO RAIL

ECoR completes 700 m escape tunnel for railway project in Boudh, Odisha

The engineering team of East Coast Railway (ECoR) has reached a significant milestone by excavating a 700-metre-long escape tunnel for the Khurda Road-Balangir rail link project in Boudh district.

ECoR's construction division created the escape tunnel from National Highway-57, connecting it to the 4,185-metre-long tunnel being built in the Adhenigarh-Charichhak section within a reserve forest under the Madhapur range in Boudh. The excavation was completed on Tuesday. This escape tunnel will facilitate the early completion of the main tunnel and boost the long-pending project, which was sanctioned in 1994. Out of the 301 km Khurda Road-Balangir project, 152.8 km has been completed to date. Indian Railways has been constructing the line from both Khurda Road and Balangir ends to ensure its timely completion.

So far, 105.8 km from Khurda Road to Daspalla and 47 km from Balangir to Sonepur have been commissioned. Additionally, the 28.76 km stretch from Sonepur to Jharmunda has been completed. The segment from Sonepur to Purunakatak, covering around 73 km, is expected to be finished within the next few months.

The Ministry of Railways is closely monitoring the Khurda Road-Balangir project. New lines are being laid from both ends to expedite work and complete the project as soon as possible.

The engineering team of East Coast Railway (ECoR) has reached a significant milestone by excavating a 700-metre-long escape tunnel for the Khurda Road-Balangir rail link project in Boudh district. ECoR's construction division created the escape tunnel from National Highway-57, connecting it to the 4,185-metre-long tunnel being built in the Adhenigarh-Charichhak section within a reserve forest under the Madhapur range in Boudh. The excavation was completed on Tuesday. This escape tunnel will facilitate the early completion of the main tunnel and boost the long-pending project, which was sanctioned in 1994. Out of the 301 km Khurda Road-Balangir project, 152.8 km has been completed to date. Indian Railways has been constructing the line from both Khurda Road and Balangir ends to ensure its timely completion. So far, 105.8 km from Khurda Road to Daspalla and 47 km from Balangir to Sonepur have been commissioned. Additionally, the 28.76 km stretch from Sonepur to Jharmunda has been completed. The segment from Sonepur to Purunakatak, covering around 73 km, is expected to be finished within the next few months. The Ministry of Railways is closely monitoring the Khurda Road-Balangir project. New lines are being laid from both ends to expedite work and complete the project as soon as possible.

Next Story
Real Estate

RBI Rate Cut Boosts Confidence Across Housing Market

Industry Context and Market DynamicsThe real estate industry has welcomed the RBI’s rate cut as a timely boost to affordability and demand. With home prices having risen steadily across major markets, even a marginal reduction in interest rates meaningfully strengthens purchasing power, especially for first-time and mid-income buyers.Ashish Jerath, President – Sales & Marketing, Smartworld Developers, observes:“The RBI’s 25-basis-point cut, bringing the repo rate down to 5.25%, is a timely boost for the real estate sector. Lower interest rates reduce borrowing costs, enabling homeb..

Next Story
Infrastructure Transport

BMC Resumes Rs 170 Billion Road Works, Targets 80 per cent By Jan 2026

Following the withdrawal of the southwest monsoon in October, the Brihanmumbai Municipal Corporation (BMC) has restarted work on 645 roads—covering 297.49 kilometres—under its large-scale concretisation programme. Data shows that more than 60 per cent of the resumed works are located in the western suburbs. Officials said the civic body aims to complete concretisation on 80 per cent of the roads where fresh work has begun by January 2026. Launched in 2022, the Rs 170 billion project seeks to concretise 700 kilometres of roads across Mumbai. All civil works were halted during the monsoon ..

Next Story
Infrastructure Urban

India Pushes Digital Shift In Urban Land Mapping

The Department of Land Resources (DoLR) under the Ministry of Rural Development has convened a National Symposium on NAKSHA – the National Geospatial Knowledge-based Land Survey of Urban Habitations – to advance India’s transition to modern, technology-driven land mapping. Speaking at the inaugural session, Secretary Manoj Joshi underscored the urgent need to move revenue departments away from outdated, tape-based methods and rough hand-drawn sketches. He stressed that adopting latitude–longitude-based digital mapping and GIS-linked registration systems is essential for economic stabi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App