ECoR completes 700 m escape tunnel for railway project in Boudh, Odisha
RAILWAYS & METRO RAIL

ECoR completes 700 m escape tunnel for railway project in Boudh, Odisha

The engineering team of East Coast Railway (ECoR) has reached a significant milestone by excavating a 700-metre-long escape tunnel for the Khurda Road-Balangir rail link project in Boudh district.

ECoR's construction division created the escape tunnel from National Highway-57, connecting it to the 4,185-metre-long tunnel being built in the Adhenigarh-Charichhak section within a reserve forest under the Madhapur range in Boudh. The excavation was completed on Tuesday. This escape tunnel will facilitate the early completion of the main tunnel and boost the long-pending project, which was sanctioned in 1994. Out of the 301 km Khurda Road-Balangir project, 152.8 km has been completed to date. Indian Railways has been constructing the line from both Khurda Road and Balangir ends to ensure its timely completion.

So far, 105.8 km from Khurda Road to Daspalla and 47 km from Balangir to Sonepur have been commissioned. Additionally, the 28.76 km stretch from Sonepur to Jharmunda has been completed. The segment from Sonepur to Purunakatak, covering around 73 km, is expected to be finished within the next few months.

The Ministry of Railways is closely monitoring the Khurda Road-Balangir project. New lines are being laid from both ends to expedite work and complete the project as soon as possible.

The engineering team of East Coast Railway (ECoR) has reached a significant milestone by excavating a 700-metre-long escape tunnel for the Khurda Road-Balangir rail link project in Boudh district. ECoR's construction division created the escape tunnel from National Highway-57, connecting it to the 4,185-metre-long tunnel being built in the Adhenigarh-Charichhak section within a reserve forest under the Madhapur range in Boudh. The excavation was completed on Tuesday. This escape tunnel will facilitate the early completion of the main tunnel and boost the long-pending project, which was sanctioned in 1994. Out of the 301 km Khurda Road-Balangir project, 152.8 km has been completed to date. Indian Railways has been constructing the line from both Khurda Road and Balangir ends to ensure its timely completion. So far, 105.8 km from Khurda Road to Daspalla and 47 km from Balangir to Sonepur have been commissioned. Additionally, the 28.76 km stretch from Sonepur to Jharmunda has been completed. The segment from Sonepur to Purunakatak, covering around 73 km, is expected to be finished within the next few months. The Ministry of Railways is closely monitoring the Khurda Road-Balangir project. New lines are being laid from both ends to expedite work and complete the project as soon as possible.

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement