Kolkata Metro Orange Line Clears Six Year Chingrighata Delay
RAILWAYS & METRO RAIL

Kolkata Metro Orange Line Clears Six Year Chingrighata Delay

Kolkata Metro’s Orange Line has closed a long-standing viaduct gap at Chingrighata after more than six years of delays, completing a critical section that had impeded progress on the New Garia to Airport corridor. The work at the busy intersection will facilitate remaining construction and testing along the route. Rail Vikas Nigam Ltd is overseeing the 32-kilometre corridor and led the operations to finish the stalled segment.

On Sunday engineers placed the final 31 metre concrete deck slab, closing the 366 metre gap and enabling structural continuity across the crossing. The new viaduct rises about 12 metre above the road and the project team completed the girder launching at the intersection within roughly 90 days. The contractor also hoisted the national flag on the completed span to mark the milestone.

The Chingrighata bottleneck reflected a complex mix of technical and administrative obstacles centred on Pier 318, which was planned near the centre of the crossing. The sequence of milestones began in 2020 when work first encountered difficulties, with an IIT Kharagpur design approval arriving in August 2020 and a state no objection certificate issued in May 2023. Subsequent road works completed in December 2024 and traffic arrangements enabled girder erection in mid-May 2026.

Police clearance had been a further hurdle, with delays of about fifteen months before Kolkata Police approved traffic plans and litigation repeatedly brought the matter before the Calcutta High Court for status updates. With traffic diversions and approvals in place, the contractor completed the remaining launching and slab works to close the gap. The general manager said the organisation was working towards a 31 December deadline to open the Beleghata to IT Centre section, which would cut travel time between New Garia and Sector V to about 30 minutes. The cleared bottleneck removes one of the longest-running obstacles on the Orange Line and should ease construction of the remaining stretches.

Kolkata Metro’s Orange Line has closed a long-standing viaduct gap at Chingrighata after more than six years of delays, completing a critical section that had impeded progress on the New Garia to Airport corridor. The work at the busy intersection will facilitate remaining construction and testing along the route. Rail Vikas Nigam Ltd is overseeing the 32-kilometre corridor and led the operations to finish the stalled segment. On Sunday engineers placed the final 31 metre concrete deck slab, closing the 366 metre gap and enabling structural continuity across the crossing. The new viaduct rises about 12 metre above the road and the project team completed the girder launching at the intersection within roughly 90 days. The contractor also hoisted the national flag on the completed span to mark the milestone. The Chingrighata bottleneck reflected a complex mix of technical and administrative obstacles centred on Pier 318, which was planned near the centre of the crossing. The sequence of milestones began in 2020 when work first encountered difficulties, with an IIT Kharagpur design approval arriving in August 2020 and a state no objection certificate issued in May 2023. Subsequent road works completed in December 2024 and traffic arrangements enabled girder erection in mid-May 2026. Police clearance had been a further hurdle, with delays of about fifteen months before Kolkata Police approved traffic plans and litigation repeatedly brought the matter before the Calcutta High Court for status updates. With traffic diversions and approvals in place, the contractor completed the remaining launching and slab works to close the gap. The general manager said the organisation was working towards a 31 December deadline to open the Beleghata to IT Centre section, which would cut travel time between New Garia and Sector V to about 30 minutes. The cleared bottleneck removes one of the longest-running obstacles on the Orange Line and should ease construction of the remaining stretches.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Gopalan Metals Enters Building Wires Segment

Gopalan Metals (India) has recently launched Gopalan Wires and Cables, marking its entry into the building wires segment for residential, commercial and industrial applications.The product portfolio currently includes Flame Retardant (FR) and Flame Retardant Low Smoke and Halogen (FRLS-H) PVC house wires. The products are manufactured at the company’s Hoskote facility in Karnataka, which has a production capacity of around 6,000 km of building wires per month.Gopalan Wires and Cables will cater to electrical dealers, distributors, contractors, builders, infrastructure projects, OEMs and end ..

Next Story
Real Estate

KONE India Opens New Office in Jabalpur

KONE India has recently inaugurated a new office in Jabalpur, strengthening its presence and customer reach across Central Madhya Pradesh.The office will serve customers in Rewa, Satna, Singrauli and Katni, while also expanding the company’s reach into emerging markets such as Shahdol and Seoni. It will provide local sales, service and installation support to address growing customer requirements across the region.Amit Gossain, Managing Director, KONE India, said, “Jabalpur is an important market for us, and this new office brings us closer to our customers in the area. As the region conti..

Next Story
Infrastructure Urban

Greenr Opens 12th Outlet at Oberoi Garden City, Goregaon

Greenr has recently opened its newest outlet at Cafés. Restaurants. Bars. within International Business Park, Oberoi Garden City, Goregaon, marking its 12th location in India and further strengthening its presence in Mumbai.The outlet brings together Greenr’s plant-forward food, specialty coffee and community-focused experiences in a format designed for professionals, residents and visitors. The space is intended to support dining, coffee meetings, informal work sessions and social interactions throughout the day.Greenr’s offering combines globally inspired vegetarian cuisine with wellnes..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement