MAHSR Corridor from Maha to Sabarmati to Complete by 2029
RAILWAYS & METRO RAIL

MAHSR Corridor from Maha to Sabarmati to Complete by 2029

The entire Mumbai-Ahmedabad High Speed Rail (MAHSR) corridor is expected to be operational by December 2029, Railway Minister Ashwini Vaishnaw informed the Lok Sabha. The Gujarat segment from Vapi to Sabarmati is slated for completion by December 2027.
Covering 508 km and passing through Gujarat, Maharashtra, and Dadra & Nagar Haveli, the project includes 12 stations. Japan International Cooperation Agency (JICA) is funding 81% (Rs 88,000 crore) of the total Rs 1,08,000 crore cost, with the rest shared by the Railways and the two state governments.
As of June 30, a cumulative Rs 78,839 crore has been spent. Land acquisition in Maharashtra had delayed the project till 2021, but all 1,389.5 hectares have now been acquired.
Final location surveys, geotechnical investigations, and statutory clearances have been secured. Construction is progressing rapidly, with 392 km of piers, 329 km of girders cast, and 308 km of girders launched. Work on a 21-km undersea tunnel has also commenced.

The entire Mumbai-Ahmedabad High Speed Rail (MAHSR) corridor is expected to be operational by December 2029, Railway Minister Ashwini Vaishnaw informed the Lok Sabha. The Gujarat segment from Vapi to Sabarmati is slated for completion by December 2027.Covering 508 km and passing through Gujarat, Maharashtra, and Dadra & Nagar Haveli, the project includes 12 stations. Japan International Cooperation Agency (JICA) is funding 81% (Rs 88,000 crore) of the total Rs 1,08,000 crore cost, with the rest shared by the Railways and the two state governments.As of June 30, a cumulative Rs 78,839 crore has been spent. Land acquisition in Maharashtra had delayed the project till 2021, but all 1,389.5 hectares have now been acquired.Final location surveys, geotechnical investigations, and statutory clearances have been secured. Construction is progressing rapidly, with 392 km of piers, 329 km of girders cast, and 308 km of girders launched. Work on a 21-km undersea tunnel has also commenced.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code