New rail tunnels of WDFC to be constructed by June 2022
RAILWAYS & METRO RAIL

New rail tunnels of WDFC to be constructed by June 2022

Mumbai will observe the emergence of new rail tunnels for two different multi-crore railway projects.

The belly of the many centuries-old Western ghats is being torn open for the development of tunnels and laying rail lines for the Dedicated Freight Corridor that is getting impetus.

One of the longest rail tunnels will be carved open by utilising explosives. Simultaneously on Sunday, one of the significant works for linking the new tunnel between Kalwa and Mumbra was conducted during the 18 hours block.

The Western Dedicated Freight Corridor (WDFC) is making progress to complete the work by the June 2022 deadline. For this, one of the significant works that are drilling a hole in the Western Ghats has achieved its final stages and will be cut open on Tuesday.

As per the authorities from Dedicated Freight Corridor Corporation of India (DFCCIL), executing this project, they will be utilising several kilograms of explosives that will be detonated to attain tunnel-breakthrough.

It is a huge milestone since such a crucial work of constructing the tunnels after exploding and cutting a mountain has not been done for decades. Similar activity was conducted in June during rains. They will be documenting it by utilising drones to record it, as per an official from DFCCIL.

There are two tunnels of 430 m and 320 m, both having a height and breadth of 8 to 10 m that have been dug. Till Dadri, there would not be another tunnel after this one coming on the Vasai-Virar stretch. They will reach a breakthrough on the 320 m long one while the other tunnel is ready.

After this, another significant work is the launching of girders on Ulhas River for a similar DFC corridor. Presently, there is a violation from buildings and slums on a few kilometers that need to be cleared for this project. Once done, the track laying on the 100 km odd long route is likely to begin from March next year.

Image Source

Mumbai will observe the emergence of new rail tunnels for two different multi-crore railway projects. The belly of the many centuries-old Western ghats is being torn open for the development of tunnels and laying rail lines for the Dedicated Freight Corridor that is getting impetus. One of the longest rail tunnels will be carved open by utilising explosives. Simultaneously on Sunday, one of the significant works for linking the new tunnel between Kalwa and Mumbra was conducted during the 18 hours block. The Western Dedicated Freight Corridor (WDFC) is making progress to complete the work by the June 2022 deadline. For this, one of the significant works that are drilling a hole in the Western Ghats has achieved its final stages and will be cut open on Tuesday. As per the authorities from Dedicated Freight Corridor Corporation of India (DFCCIL), executing this project, they will be utilising several kilograms of explosives that will be detonated to attain tunnel-breakthrough. It is a huge milestone since such a crucial work of constructing the tunnels after exploding and cutting a mountain has not been done for decades. Similar activity was conducted in June during rains. They will be documenting it by utilising drones to record it, as per an official from DFCCIL. There are two tunnels of 430 m and 320 m, both having a height and breadth of 8 to 10 m that have been dug. Till Dadri, there would not be another tunnel after this one coming on the Vasai-Virar stretch. They will reach a breakthrough on the 320 m long one while the other tunnel is ready. After this, another significant work is the launching of girders on Ulhas River for a similar DFC corridor. Presently, there is a violation from buildings and slums on a few kilometers that need to be cleared for this project. Once done, the track laying on the 100 km odd long route is likely to begin from March next year. Image Source

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?