Priority corridor of the Bhopal metro on track
RAILWAYS & METRO RAIL

Priority corridor of the Bhopal metro on track

In 210 days, the four kilometer-long priority corridor of the Bhopal metro is set to become functional, for this ongoing project the first batch of 18 cm head-hardened rail track for the metro depot arrived on Saturday last week.

In the city, the movement of loaded tracks on heavy vehicles raised a lot of curious eyebrows. The 4-kilometer Bhopal corridor will receive 8,120 MT of track, while the 6.3-kilometer Indore metro, which will be completed in September, will require 8,425 MT.

These rail tracks will initially support approximately 50 coaches and cost INR 1380 million, putting the city metro's priority corridor on the right track. For now,coaches will ply on under construction metro stations and its support system.

By April, the track is expected to be laid. Signaling work is also being worked on simultaneously. According to sources, everything aligns with the project's financial aspect.Following the allocation of INR 7100 million that was made public in the MP budget on March 1.

MPMRCL will apply for the first trench of a loan from the European Investment Bank (EIB). It would help pay for 50 coaches. IIT Mumbai will be in charge of certifying the structural design of the segmental box-girder superstructures in Bhopal and Indore.

In 210 days, the four kilometer-long priority corridor of the Bhopal metro is set to become functional, for this ongoing project the first batch of 18 cm head-hardened rail track for the metro depot arrived on Saturday last week. In the city, the movement of loaded tracks on heavy vehicles raised a lot of curious eyebrows. The 4-kilometer Bhopal corridor will receive 8,120 MT of track, while the 6.3-kilometer Indore metro, which will be completed in September, will require 8,425 MT. These rail tracks will initially support approximately 50 coaches and cost INR 1380 million, putting the city metro's priority corridor on the right track. For now,coaches will ply on under construction metro stations and its support system. By April, the track is expected to be laid. Signaling work is also being worked on simultaneously. According to sources, everything aligns with the project's financial aspect.Following the allocation of INR 7100 million that was made public in the MP budget on March 1. MPMRCL will apply for the first trench of a loan from the European Investment Bank (EIB). It would help pay for 50 coaches. IIT Mumbai will be in charge of certifying the structural design of the segmental box-girder superstructures in Bhopal and Indore.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code