CAG Flags Deviations In Chennai Smart City Projects
SMART CITIES

CAG Flags Deviations In Chennai Smart City Projects

The Comptroller and Auditor General of India flagged deviations in implementation of Smart Cities Mission projects in Chennai after a performance audit covering April 2016 to March 2024. The audit, tabled in the Tamil Nadu Legislative Assembly on September eight, found that several projects were dropped, unplanned work was undertaken and funds were spent outside the designated Smart City area. The audit report examined project selection, execution and financial compliance across municipal and state implementing agencies.

Of the 48 projects planned for Chennai with an approved cost of Rs 13.66 billion (bn), eight projects worth Rs 2,790.3 million (mn) were not implemented. The audit also identified that 13 projects involving an expenditure of Rs 763.2 million (mn) were carried out beyond the approved Area Based Development zone. Shortcomings were observed in documentation of project scope and in adherence to procurement and monitoring protocols.

The CAG report noted instances where project deliverables were either modified without formal approval or where parallel works were executed outside the Smart City plan, leading to potential duplication and inefficiencies. It indicated lapses in periodic review and performance measurement that undermined planned outcomes and value for money. The audit assessed reasons for cancellations and deviations, attributing many to inadequate planning and weak coordination among implementing agencies.

The report recommended strengthening project appraisal and zoning controls, enhancing internal controls and instituting stricter monitoring and reporting mechanisms by municipal authorities and the state government. It urged timely reconciliation of accounts and recovery or reallocation of funds where projects were not completed as approved. The findings are expected to inform legislative oversight and corrective action by state authorities promptly.

The Comptroller and Auditor General of India flagged deviations in implementation of Smart Cities Mission projects in Chennai after a performance audit covering April 2016 to March 2024. The audit, tabled in the Tamil Nadu Legislative Assembly on September eight, found that several projects were dropped, unplanned work was undertaken and funds were spent outside the designated Smart City area. The audit report examined project selection, execution and financial compliance across municipal and state implementing agencies. Of the 48 projects planned for Chennai with an approved cost of Rs 13.66 billion (bn), eight projects worth Rs 2,790.3 million (mn) were not implemented. The audit also identified that 13 projects involving an expenditure of Rs 763.2 million (mn) were carried out beyond the approved Area Based Development zone. Shortcomings were observed in documentation of project scope and in adherence to procurement and monitoring protocols. The CAG report noted instances where project deliverables were either modified without formal approval or where parallel works were executed outside the Smart City plan, leading to potential duplication and inefficiencies. It indicated lapses in periodic review and performance measurement that undermined planned outcomes and value for money. The audit assessed reasons for cancellations and deviations, attributing many to inadequate planning and weak coordination among implementing agencies. The report recommended strengthening project appraisal and zoning controls, enhancing internal controls and instituting stricter monitoring and reporting mechanisms by municipal authorities and the state government. It urged timely reconciliation of accounts and recovery or reallocation of funds where projects were not completed as approved. The findings are expected to inform legislative oversight and corrective action by state authorities promptly.

Related Stories

Gold Stories

Next Story
Real Estate

Japanese companies expand GCC operations in India

More than 100 Japanese companies have established or are expanding Global Capability Centres (GCCs) in India, with a growing focus on artificial intelligence (AI), engineering, digital innovation, product development, cybersecurity and advanced analytics. The shift marks an expansion beyond traditional back-office and operational support functions towards higher-value technology and innovation activities.Japanese companies are increasingly using their Indian GCCs to support digital transformation, address talent shortages and contribute to global business strategies. These centres are taking o..

Next Story
Real Estate

India’s flexible office stock projected to reach 160 million sq ft by 2030

India retained its position as the world's most mature flexible office market, scoring 100 per cent on Cushman & Wakefield's Flexible Office Market Maturity Index, according to the firm's Global Trends in Flexible Office 2026 report.India's flexible office inventory reached 88.7 million sq ft (MSF) in H1 2026, accounting for 10.5 per cent of the country's total office stock. The report projects this to exceed 100 MSF in 2026 and reach approximately 160 MSF by 2030.Flexible office operators leased 8.5 MSF across India's top eight cities in H1 2026, their strongest first-half performance to ..

Next Story
Infrastructure Urban

K2 Infragen appoints Abhishek Sharma as DGM, supply chain

K2 Infragen has appointed Abhishek Sharma as Deputy General Manager, Supply Chain Management. He will oversee procurement planning, vendor partnerships and coordination with project teams.Sharma brings nearly two decades of experience in infrastructure procurement across railways, highways, expressways and hydropower. His experience includes procurement responsibilities associated with the Delhi–Meerut Expressway and the Delhi–Vadodara greenfield corridor. ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code