Cochin Smart City Mission: Smart roads to be completed by September
SMART CITIES

Cochin Smart City Mission: Smart roads to be completed by September

The Cochin Smart Mission (CSML) is planning to complete major road works in Ernakulam by September.

The City Level Advisory Forum (CLAF) meeting discussed the project progress and the problems encountered during the implementation of the project.

While presenting the details at the fourth CLAF, Jafar Malik, the CSML CEO, told the CLAF members that due to the contractor's poor performance, growth in the road works of West Kochi was impacted.

It was also mentioned in the meeting that there had been a delay in executing the smart city projects because of the Covid pandemic and various other reasons.

The members of CLAF said CSML has to make up for the ruined time and facilitate the implementation of the ongoing projects.

CLAF advised conducting individual meetings with ward councillors and extended their support for making sure the projects are finished successfully.

During the meeting, CLAF members noted that taking up the sewerage project in Mattancherry might not be practical due to the pandemic and offered a joint meeting to decide the plan for moving ahead.

It was suggested to transfer the fund allotted to CSML for the Canal rejuvenation to the Operation Breakthrough. It would enable the company to take up the rejuvenation projects of the Rameswaram Kalvathy canal and Mullassery canal.

The members recommended CSML explore the chance of restoring non-starter projects with new ones that enhance the city's infrastructure and give Smart solutions to the problems of its citizens.

The foundation works of Syed Calvathy School and Mohammed Bridge are in process. The market rehabilitation project is likely to be finished by July, and the tender for the new market structure would also be awarded this month. By mid-July, the Marine Drive Walkway will be finished.

Image Source


Also read: Smart roads in Cochin to be developed despite Covid-19

Also read: Smart City scheme: Aurangabad on the verge of modernisation

The Cochin Smart Mission (CSML) is planning to complete major road works in Ernakulam by September. The City Level Advisory Forum (CLAF) meeting discussed the project progress and the problems encountered during the implementation of the project. While presenting the details at the fourth CLAF, Jafar Malik, the CSML CEO, told the CLAF members that due to the contractor's poor performance, growth in the road works of West Kochi was impacted. It was also mentioned in the meeting that there had been a delay in executing the smart city projects because of the Covid pandemic and various other reasons. The members of CLAF said CSML has to make up for the ruined time and facilitate the implementation of the ongoing projects. CLAF advised conducting individual meetings with ward councillors and extended their support for making sure the projects are finished successfully. During the meeting, CLAF members noted that taking up the sewerage project in Mattancherry might not be practical due to the pandemic and offered a joint meeting to decide the plan for moving ahead. It was suggested to transfer the fund allotted to CSML for the Canal rejuvenation to the Operation Breakthrough. It would enable the company to take up the rejuvenation projects of the Rameswaram Kalvathy canal and Mullassery canal. The members recommended CSML explore the chance of restoring non-starter projects with new ones that enhance the city's infrastructure and give Smart solutions to the problems of its citizens. The foundation works of Syed Calvathy School and Mohammed Bridge are in process. The market rehabilitation project is likely to be finished by July, and the tender for the new market structure would also be awarded this month. By mid-July, the Marine Drive Walkway will be finished. Image Source Also read: Smart roads in Cochin to be developed despite Covid-19 Also read: Smart City scheme: Aurangabad on the verge of modernisation

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code