Cochin Smart City Mission: Smart roads to be completed by September
SMART CITIES

Cochin Smart City Mission: Smart roads to be completed by September

The Cochin Smart Mission (CSML) is planning to complete major road works in Ernakulam by September.

The City Level Advisory Forum (CLAF) meeting discussed the project progress and the problems encountered during the implementation of the project.

While presenting the details at the fourth CLAF, Jafar Malik, the CSML CEO, told the CLAF members that due to the contractor's poor performance, growth in the road works of West Kochi was impacted.

It was also mentioned in the meeting that there had been a delay in executing the smart city projects because of the Covid pandemic and various other reasons.

The members of CLAF said CSML has to make up for the ruined time and facilitate the implementation of the ongoing projects.

CLAF advised conducting individual meetings with ward councillors and extended their support for making sure the projects are finished successfully.

During the meeting, CLAF members noted that taking up the sewerage project in Mattancherry might not be practical due to the pandemic and offered a joint meeting to decide the plan for moving ahead.

It was suggested to transfer the fund allotted to CSML for the Canal rejuvenation to the Operation Breakthrough. It would enable the company to take up the rejuvenation projects of the Rameswaram Kalvathy canal and Mullassery canal.

The members recommended CSML explore the chance of restoring non-starter projects with new ones that enhance the city's infrastructure and give Smart solutions to the problems of its citizens.

The foundation works of Syed Calvathy School and Mohammed Bridge are in process. The market rehabilitation project is likely to be finished by July, and the tender for the new market structure would also be awarded this month. By mid-July, the Marine Drive Walkway will be finished.

Image Source


Also read: Smart roads in Cochin to be developed despite Covid-19

Also read: Smart City scheme: Aurangabad on the verge of modernisation

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

The Cochin Smart Mission (CSML) is planning to complete major road works in Ernakulam by September. The City Level Advisory Forum (CLAF) meeting discussed the project progress and the problems encountered during the implementation of the project. While presenting the details at the fourth CLAF, Jafar Malik, the CSML CEO, told the CLAF members that due to the contractor's poor performance, growth in the road works of West Kochi was impacted. It was also mentioned in the meeting that there had been a delay in executing the smart city projects because of the Covid pandemic and various other reasons. The members of CLAF said CSML has to make up for the ruined time and facilitate the implementation of the ongoing projects. CLAF advised conducting individual meetings with ward councillors and extended their support for making sure the projects are finished successfully. During the meeting, CLAF members noted that taking up the sewerage project in Mattancherry might not be practical due to the pandemic and offered a joint meeting to decide the plan for moving ahead. It was suggested to transfer the fund allotted to CSML for the Canal rejuvenation to the Operation Breakthrough. It would enable the company to take up the rejuvenation projects of the Rameswaram Kalvathy canal and Mullassery canal. The members recommended CSML explore the chance of restoring non-starter projects with new ones that enhance the city's infrastructure and give Smart solutions to the problems of its citizens. The foundation works of Syed Calvathy School and Mohammed Bridge are in process. The market rehabilitation project is likely to be finished by July, and the tender for the new market structure would also be awarded this month. By mid-July, the Marine Drive Walkway will be finished. Image Source Also read: Smart roads in Cochin to be developed despite Covid-19 Also read: Smart City scheme: Aurangabad on the verge of modernisation

Next Story
Infrastructure Urban

Delivering metals in 24 hours with AI

India’s metal supply chain has long struggled with delays, fragmentation and lack of transparency, forcing purchase teams to chase vendors and juggle uncertain stock. Enlight Metals is tackling these inefficiencies with an AI-powered aggregation platform, multilingual voice-enabled procurement and strategically located dark stores that enable 24-hour delivery – transforming how OEMs, EPCs and infrastructure players source their metals. In a conversation with CW, Dhananjay Goel, Director, and Vedant Goel, Director, shares how the company is reshaping procurement. What problem..

Next Story
Infrastructure Urban

Silvin's CPVC Additive Gets NSF® Certification for Safety

Silvin Additives, a prominent manufacturer of PVC and CPVC additives, has secured the NSF® Guideline 533 certification for its CPVC Super1Pack formulation. This certification affirms the additive’s compliance with stringent international health and safety standards for products intended for drinking water applications.Awarded by NSF, a globally respected public health and safety authority based in Michigan, United States, the certification is granted only after rigorous product testing and inspection. NSF® Guideline 533 specifically assesses the safety of chemical ingredients used in produ..

Next Story
Infrastructure Urban

Mitsubishi Halts Offshore Wind Projects in Japan

Mitsubishi Corporation (MC) has announced its decision to withdraw from three major offshore wind projects off the coast of Japan due to a significant shift in global business conditions. The projects were being developed through a consortium led by its subsidiary, Mitsubishi Corporation Offshore Wind Ltd., and were located off the shores of Noshiro City, Mitane Town, and Oga City in Akita Prefecture; Yurihonjo City in Akita Prefecture; and Choshi City in Chiba Prefecture.The company stated that following a review initiated in February 2025, it concluded the projects were no longer viable. The..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?