Contractors in race to construct new Parliament House
Cement

Contractors in race to construct new Parliament House

While the Lok Sabha with 541 seats has been provided with the Sansad Bhavan or Parliament House which has a seating capacity of 790, only 261 members attended Parliament during February early this year before the nation was hit by the Coronavirus.

That said, plans are afoot to construct the new Parliament building within a larger complex with a seating capacity of over 1,000. The Central Public Works Department (CPWD) had invited prequalification bids in a two-bid system under the Central Vista Project to construct the new Parliament building adjacent to the current building. With a built-up area of approximately 60,000 m sq on plot number 118 of the Parliament House Estate, the new building will be a triangular-shaped construction.

Contractors in for the bid

Seven firms had showed interest in the construction of the new Parliament building after prequalification bids. The total cost of the project has seen an 18.8 per cent cost escalation to Rs 9.22 billion from Rs 7.76 billion. The cost has gone up because of additional infrastructure requirements and an increase in the size of various facilities that are part of the project. The Government has set a 2022 deadline to complete the new building.

While developmental work will be looked after by CPWD, last year it chose HCP Design, Planning & Management (HCPDPM), an Ahmedabad-based architecture firm, as the project consultant. After revisiting the masterplan for the central Delhi area, HCPDPM is now responsible for coming up with new designs and/or alterations required for the project. The cost of consultancy has been set at Rs 2.30 billion.

For the complete list of contractors, who have participated in the bid, click here!

The bid laid out eligibility criteria based on the firm’s past work, such as having built an assembly hall of minimum 1,000 capacity and a building with a basement as well as experience of ongoing projects, average monthly turnover and net worth, among major other factors.

The submissions of bids are verified on the basis of similar work completed in the past seven years and ongoing projects, as well as tentative plans to indicate manpower requirement, sourcing of materials, and establishment of facilities, such as for fabrication, among others.

Design and plan

Construction on the new Parliament building, which will comprise halls with greater seating capacity for the Lok Sabha and the Rajya Sabha, offices for members of Parliament, as well as an open-to-sky courtyard and dining facilities, is likely to begin after the Parliament’s winter session.Designed to accommodate over 1,000 members of Parliaments, in addition to private chambers for all MPs, the building will have offices for ministers and secretaries. According to Bimal Patel, the architect in charge of the redesign of the Central Vista, the plan also includes the creation of a separate lounge for lawmakers. Currently, the Central Hall functions as one, although it is not designed for the purpose.

The current design foresees a triangular complex, with a tricoloured beam lighting up the sky overhead. Members of Parliament will sit in broad two-seater benches in comfort, accessible from either side, which can accommodate up to three MPs when a joint session is held. The redevelopment plan also aims to converting North Block and South Blocks into museums, redesign Rajpath and create a Central Secretariat.

The plan takes inspiration from Parliaments of several countries, including Cuba, Egypt, Singapore and Germany. MPs have often complained of lack of space, especially during joint sessions—that is the main focus of the seating arrangement of the new design. Windows of unequal sizes are being made in the central hall to reflect the diversity of the country.

Visual and acoustic factors are being kept in mind when it comes to technological designing. To ensure clarity of presentation and minimise the problem of echoing, better audio and visual equipment is to be used. There will also be in-built translation systems.Further, the buildings will be fitted with solar panels and low electricity consuming electronic sittings, and will have dedicated parking areas.

Construction work is expected to be completed by the end of 2022. The proposed work is prestigious and therefore requires highly skilled craftsmanship and labour. The bid document also specified that 50 per cent of the workers will need to be skilled in work of stone masonry, carving, fresco and furniture, and that adequate health and safety measures would need to be taken in view of the prevailing COVID-19 pandemic.

What’s in for the contractor?

The Centre will provide land free of cost to the contractor for establishing a labour camp within the Delhi-NCR area. The contractor will make his own arrangement of transportation of labour from the labour camp to site for working in three shifts.

CPWD has additionally modified the prequalification bid and stated that the contractor, in collaboration with CPWD,will arrange on-site skill training for at least 30 per cent of unskilled workers through reputed institutions like the CPWD National Training Academy, CIDC, ITI, National Institute of Construction Management (NICMAR), the National Academy of Construction or any similar reputed and recognised institute managed or certified by a state or the Central Government.

The modernisation will require vacating the buildings for over a year. Over four dozen Central Government ministries and departments, employing over 70,000 employees, are scattered across Delhi.

Hopefully, by 2022 – the deadline for completion of the project – the COVID-19 pandemic will be well behind us. And for our lawmakers, it will be business as usual, in magnificent, new premises.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

While the Lok Sabha with 541 seats has been provided with the Sansad Bhavan or Parliament House which has a seating capacity of 790, only 261 members attended Parliament during February early this year before the nation was hit by the Coronavirus.That said, plans are afoot to construct the new Parliament building within a larger complex with a seating capacity of over 1,000. The Central Public Works Department (CPWD) had invited prequalification bids in a two-bid system under the Central Vista Project to construct the new Parliament building adjacent to the current building. With a built-up area of approximately 60,000 m sq on plot number 118 of the Parliament House Estate, the new building will be a triangular-shaped construction.Contractors in for the bidSeven firms had showed interest in the construction of the new Parliament building after prequalification bids. The total cost of the project has seen an 18.8 per cent cost escalation to Rs 9.22 billion from Rs 7.76 billion. The cost has gone up because of additional infrastructure requirements and an increase in the size of various facilities that are part of the project. The Government has set a 2022 deadline to complete the new building.While developmental work will be looked after by CPWD, last year it chose HCP Design, Planning & Management (HCPDPM), an Ahmedabad-based architecture firm, as the project consultant. After revisiting the masterplan for the central Delhi area, HCPDPM is now responsible for coming up with new designs and/or alterations required for the project. The cost of consultancy has been set at Rs 2.30 billion.For the complete list of contractors, who have participated in the bid, click here! The bid laid out eligibility criteria based on the firm’s past work, such as having built an assembly hall of minimum 1,000 capacity and a building with a basement as well as experience of ongoing projects, average monthly turnover and net worth, among major other factors.The submissions of bids are verified on the basis of similar work completed in the past seven years and ongoing projects, as well as tentative plans to indicate manpower requirement, sourcing of materials, and establishment of facilities, such as for fabrication, among others.Design and planConstruction on the new Parliament building, which will comprise halls with greater seating capacity for the Lok Sabha and the Rajya Sabha, offices for members of Parliament, as well as an open-to-sky courtyard and dining facilities, is likely to begin after the Parliament’s winter session.Designed to accommodate over 1,000 members of Parliaments, in addition to private chambers for all MPs, the building will have offices for ministers and secretaries. According to Bimal Patel, the architect in charge of the redesign of the Central Vista, the plan also includes the creation of a separate lounge for lawmakers. Currently, the Central Hall functions as one, although it is not designed for the purpose.The current design foresees a triangular complex, with a tricoloured beam lighting up the sky overhead. Members of Parliament will sit in broad two-seater benches in comfort, accessible from either side, which can accommodate up to three MPs when a joint session is held. The redevelopment plan also aims to converting North Block and South Blocks into museums, redesign Rajpath and create a Central Secretariat.The plan takes inspiration from Parliaments of several countries, including Cuba, Egypt, Singapore and Germany. MPs have often complained of lack of space, especially during joint sessions—that is the main focus of the seating arrangement of the new design. Windows of unequal sizes are being made in the central hall to reflect the diversity of the country.Visual and acoustic factors are being kept in mind when it comes to technological designing. To ensure clarity of presentation and minimise the problem of echoing, better audio and visual equipment is to be used. There will also be in-built translation systems.Further, the buildings will be fitted with solar panels and low electricity consuming electronic sittings, and will have dedicated parking areas.Construction work is expected to be completed by the end of 2022. The proposed work is prestigious and therefore requires highly skilled craftsmanship and labour. The bid document also specified that 50 per cent of the workers will need to be skilled in work of stone masonry, carving, fresco and furniture, and that adequate health and safety measures would need to be taken in view of the prevailing COVID-19 pandemic.What’s in for the contractor?The Centre will provide land free of cost to the contractor for establishing a labour camp within the Delhi-NCR area. The contractor will make his own arrangement of transportation of labour from the labour camp to site for working in three shifts.CPWD has additionally modified the prequalification bid and stated that the contractor, in collaboration with CPWD,will arrange on-site skill training for at least 30 per cent of unskilled workers through reputed institutions like the CPWD National Training Academy, CIDC, ITI, National Institute of Construction Management (NICMAR), the National Academy of Construction or any similar reputed and recognised institute managed or certified by a state or the Central Government.The modernisation will require vacating the buildings for over a year. Over four dozen Central Government ministries and departments, employing over 70,000 employees, are scattered across Delhi.Hopefully, by 2022 – the deadline for completion of the project – the COVID-19 pandemic will be well behind us. And for our lawmakers, it will be business as usual, in magnificent, new premises.

Next Story
Infrastructure Urban

Krystal Wins Rs 3.6 Billion Welfare Services Contract

Krystal Integrated Services Ltd (KISL) has secured a Rs 3.6 billion contract from the Commissionerate of Social Welfare, Pune, marking a major development in the company’s portfolio of public sector facility management services.The contract spans five years and includes mechanised housekeeping and outsourced manpower services for a vast network of social welfare institutions across Maharashtra. These include hostels, residential schools, welfare homes, training institutes, and administrative offices.In a statement, KISL underlined the critical impact of the agreement, noting that it will dir..

Next Story
Infrastructure Energy

NLCIL Mines Win Top Honours in 2023–24 Star Ratings

NLC India Limited (NLCIL), a Navratna Central Public Sector Enterprise (CPSE) under the Ministry of Coal, has once again cemented its position as a leader in sustainable and responsible mining, with all five of its operating mines receiving prestigious Star Ratings for 2023–24 from the Ministry of Coal.The Star Rating scheme, introduced in 2019, evaluates mines across seven key parameters, including operational efficiency, environmental stewardship, safety, technological adoption, rehabilitation, and worker welfare. Since the inception of the framework, NLCIL has ensured 100 per cent partici..

Next Story
Infrastructure Energy

GST on Coal Raised to 18 per cent, Compensation Cess Removed

The Goods and Services Tax (GST) Council has approved a hike in the GST rate on coal and lignite from 5 per cent to 18 per cent, while simultaneously removing the additional compensation cess of Rs 400 per tonne, previously levied at 40 per cent. The decision, taken on 3 September, is expected to rationalise the tax structure without raising the overall cost burden on power producers or consumers.According to a statement from the Union government, the move is unlikely to impact electricity prices, as the tax adjustment is designed to be revenue-neutral for buyers. The removal of the cess is ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?