+
GERC proposes amendments in Gujarat rooftop net metering regulations
POWER & RENEWABLE ENERGY

GERC proposes amendments in Gujarat rooftop net metering regulations

Gujarat Electricity Regulatory Commission (GERC) has proposed changes to the 2016 Regulations on Net Metering Rooftop Solar Grid-Interactive Systems.

Net metering will now be allowed for loads up to 10 KW and gross metering for loads above 10 KW. The installed capacity must be between 1 kW and 1 MW.

The Ministry of Power recently amended the Electricity (Rights of Consumers) Rules, allowing prosumers to use net metering for loads up to 500 KW or the approved load, whichever is lower.

Rooftop projects set up by residential customers will be allowed regardless of the approved load, and captive and third-party projects will have no capacity restrictions.

The projects will be allowed up to the approved load or contracted demand for projects under the renewable energy certificate (REC) mechanism for captive or third-party sale.

Regardless of their approved load or contracted demand, consumers will be able to set up projects to meet their renewable purchase obligation (RPO) requirements.

For additional capacity, a new agreement must be signed under existing regulations.

The licensee must separately report the amount of electricity injected into the grid, electricity supplied by the distribution licensee, net billed electricity, and net exported energy after adjustments against consumption for each billing cycle.

If rooftop projects are set up with gross metering, the electricity generated and supplied by them will be shown separately on the bill at the rate set by the Commission.

In the case of gross metering, distribution licensees will purchase electricity at the rate set by the Commission in its order dated August 8, 2019, in response to Petition number 1802 of 2019.

The gross metering tariff will be the simple average of tariffs discovered in competitive bidding of projects outside the solar park in the six months leading up to 31 March, plus Rs 0.20 per kWh.

This applies to power purchase agreements (PPAs) signed between April and September. For projects signing PPAs from October to March, the same calculation as above will apply for six months up to 30 September, with an addition of Rs 0.20 per kWh.

The Rs 0.20 per kWh increase in tariff allows for Rs 0.12 per kWh in transmission loss savings and Rs 0.08 per kWh in compensation for high land costs, higher capital investment, and maintenance costs associated with small projects.

Image Source


Also read: Ministry of Power nods net metering for rooftop solar up to 500 kW

Also read: GERC nods amendments sought by GUVNL for power procurement by discoms

Gujarat Electricity Regulatory Commission (GERC) has proposed changes to the 2016 Regulations on Net Metering Rooftop Solar Grid-Interactive Systems. Net metering will now be allowed for loads up to 10 KW and gross metering for loads above 10 KW. The installed capacity must be between 1 kW and 1 MW. The Ministry of Power recently amended the Electricity (Rights of Consumers) Rules, allowing prosumers to use net metering for loads up to 500 KW or the approved load, whichever is lower. Rooftop projects set up by residential customers will be allowed regardless of the approved load, and captive and third-party projects will have no capacity restrictions. The projects will be allowed up to the approved load or contracted demand for projects under the renewable energy certificate (REC) mechanism for captive or third-party sale. Regardless of their approved load or contracted demand, consumers will be able to set up projects to meet their renewable purchase obligation (RPO) requirements. For additional capacity, a new agreement must be signed under existing regulations. The licensee must separately report the amount of electricity injected into the grid, electricity supplied by the distribution licensee, net billed electricity, and net exported energy after adjustments against consumption for each billing cycle. If rooftop projects are set up with gross metering, the electricity generated and supplied by them will be shown separately on the bill at the rate set by the Commission. In the case of gross metering, distribution licensees will purchase electricity at the rate set by the Commission in its order dated August 8, 2019, in response to Petition number 1802 of 2019. The gross metering tariff will be the simple average of tariffs discovered in competitive bidding of projects outside the solar park in the six months leading up to 31 March, plus Rs 0.20 per kWh. This applies to power purchase agreements (PPAs) signed between April and September. For projects signing PPAs from October to March, the same calculation as above will apply for six months up to 30 September, with an addition of Rs 0.20 per kWh. The Rs 0.20 per kWh increase in tariff allows for Rs 0.12 per kWh in transmission loss savings and Rs 0.08 per kWh in compensation for high land costs, higher capital investment, and maintenance costs associated with small projects. Image Source Also read: Ministry of Power nods net metering for rooftop solar up to 500 kW Also read: GERC nods amendments sought by GUVNL for power procurement by discoms

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement