Juniper Commissions 145.99 MWp Solar Project in Maharashtra State
POWER & RENEWABLE ENERGY

Juniper Commissions 145.99 MWp Solar Project in Maharashtra State

Juniper Green Energy announced that it had commissioned its 145.99 MWp solar power project at Chapalgaon in Maharashtra, which will supply electricity to the Maharashtra State Electricity Distribution Company (MSEDCL).

The plant was commissioned on May 22, 2025, completing the project 19 months ahead of the Scheduled Commercial Operation Date and only 2.5 months after the power purchase agreement (PPA) was signed on March 7, 2025. The project is set to operate at its full capacity of 145.99 MWp from the commissioning date.

Ankush Malik, CEO of Juniper Green Energy, explained that early land acquisition and site development, thorough technical and environmental due diligence, securing grid connection permits, and the readiness of transmission lines and infrastructure ensured a smooth process and contributed to their success.

Juniper Green Energy is an independent renewable energy power producer in India, specialising in the development, construction, and operation of utility-scale solar, wind, and hybrid renewable energy projects.

Juniper Green Energy announced that it had commissioned its 145.99 MWp solar power project at Chapalgaon in Maharashtra, which will supply electricity to the Maharashtra State Electricity Distribution Company (MSEDCL).The plant was commissioned on May 22, 2025, completing the project 19 months ahead of the Scheduled Commercial Operation Date and only 2.5 months after the power purchase agreement (PPA) was signed on March 7, 2025. The project is set to operate at its full capacity of 145.99 MWp from the commissioning date.Ankush Malik, CEO of Juniper Green Energy, explained that early land acquisition and site development, thorough technical and environmental due diligence, securing grid connection permits, and the readiness of transmission lines and infrastructure ensured a smooth process and contributed to their success.Juniper Green Energy is an independent renewable energy power producer in India, specialising in the development, construction, and operation of utility-scale solar, wind, and hybrid renewable energy projects.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App