Mahatransco Commissions 400 kV Line To Boost Mumbai Power Supply
POWER & RENEWABLE ENERGY

Mahatransco Commissions 400 kV Line To Boost Mumbai Power Supply

The Maharashtra State Electricity Transmission Company Limited (Mahatransco) has commissioned the Babhaleshwar–Kudus 400 kV double-circuit transmission line, reinforcing power supply across the Mumbai Metropolitan Region. The new corridor will enable up to 3,000 Megawatt (MW) of additional transfer capacity and reduce transmission losses by around five MW, improving voltage stability and efficiency in Mumbai, Thane, Palghar and Ahilyanagar districts. The line is expected to ease pressure on existing corridors and support rising electricity demand in the region.

The 228 km project was executed by Kalpataru Projects International Limited and involved the erection of 715 transmission towers, of which 485 towers with 304 circuit km of stringing were completed under the Nashik division and 230 towers with 152 circuit km were completed under the Vashi division. The scheme was originally approved in 2010 and had been slated for completion in 2013 but encountered technical and administrative hurdles that delayed delivery. Work was finally completed in March 2026 after the resolution of permissions and logistical issues.

Challenges during construction included securing clearances near the Giant Metrewave Radio Telescope in Pune district, addressing land compensation disputes, obtaining forest clearances and resolving right of way constraints. In densely forested stretches materials were transported manually and advanced hotline stringing techniques were deployed in critical sections to expedite work while ensuring safety. The addition is expected to reduce load on the Padghe–Babhaleshwar transmission corridor and provide an additional power source to the Kudus substation.

The project completion was overseen by the Chief Minister and Energy Minister, with support from the Minister of State for Energy, the Additional Chief Secretary for energy and the Mahatransco chairman and managing director, and involved coordination with Nashik and Vashi division officials, government agencies, police and forest departments. Mahatransco indicated the commissioning represents a significant enhancement of the state transmission network and will contribute to more reliable supply for the rapidly growing Mumbai region. Further operational adjustments are expected as the new line is integrated into the wider grid.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Maharashtra State Electricity Transmission Company Limited (Mahatransco) has commissioned the Babhaleshwar–Kudus 400 kV double-circuit transmission line, reinforcing power supply across the Mumbai Metropolitan Region. The new corridor will enable up to 3,000 Megawatt (MW) of additional transfer capacity and reduce transmission losses by around five MW, improving voltage stability and efficiency in Mumbai, Thane, Palghar and Ahilyanagar districts. The line is expected to ease pressure on existing corridors and support rising electricity demand in the region. The 228 km project was executed by Kalpataru Projects International Limited and involved the erection of 715 transmission towers, of which 485 towers with 304 circuit km of stringing were completed under the Nashik division and 230 towers with 152 circuit km were completed under the Vashi division. The scheme was originally approved in 2010 and had been slated for completion in 2013 but encountered technical and administrative hurdles that delayed delivery. Work was finally completed in March 2026 after the resolution of permissions and logistical issues. Challenges during construction included securing clearances near the Giant Metrewave Radio Telescope in Pune district, addressing land compensation disputes, obtaining forest clearances and resolving right of way constraints. In densely forested stretches materials were transported manually and advanced hotline stringing techniques were deployed in critical sections to expedite work while ensuring safety. The addition is expected to reduce load on the Padghe–Babhaleshwar transmission corridor and provide an additional power source to the Kudus substation. The project completion was overseen by the Chief Minister and Energy Minister, with support from the Minister of State for Energy, the Additional Chief Secretary for energy and the Mahatransco chairman and managing director, and involved coordination with Nashik and Vashi division officials, government agencies, police and forest departments. Mahatransco indicated the commissioning represents a significant enhancement of the state transmission network and will contribute to more reliable supply for the rapidly growing Mumbai region. Further operational adjustments are expected as the new line is integrated into the wider grid.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement