Mahatransco Commissions 400 kV Line To Boost Mumbai Power Supply
POWER & RENEWABLE ENERGY

Mahatransco Commissions 400 kV Line To Boost Mumbai Power Supply

The Maharashtra State Electricity Transmission Company Limited (Mahatransco) has commissioned the Babhaleshwar–Kudus 400 kV double-circuit transmission line, reinforcing power supply across the Mumbai Metropolitan Region. The new corridor will enable up to 3,000 Megawatt (MW) of additional transfer capacity and reduce transmission losses by around five MW, improving voltage stability and efficiency in Mumbai, Thane, Palghar and Ahilyanagar districts. The line is expected to ease pressure on existing corridors and support rising electricity demand in the region.

The 228 km project was executed by Kalpataru Projects International Limited and involved the erection of 715 transmission towers, of which 485 towers with 304 circuit km of stringing were completed under the Nashik division and 230 towers with 152 circuit km were completed under the Vashi division. The scheme was originally approved in 2010 and had been slated for completion in 2013 but encountered technical and administrative hurdles that delayed delivery. Work was finally completed in March 2026 after the resolution of permissions and logistical issues.

Challenges during construction included securing clearances near the Giant Metrewave Radio Telescope in Pune district, addressing land compensation disputes, obtaining forest clearances and resolving right of way constraints. In densely forested stretches materials were transported manually and advanced hotline stringing techniques were deployed in critical sections to expedite work while ensuring safety. The addition is expected to reduce load on the Padghe–Babhaleshwar transmission corridor and provide an additional power source to the Kudus substation.

The project completion was overseen by the Chief Minister and Energy Minister, with support from the Minister of State for Energy, the Additional Chief Secretary for energy and the Mahatransco chairman and managing director, and involved coordination with Nashik and Vashi division officials, government agencies, police and forest departments. Mahatransco indicated the commissioning represents a significant enhancement of the state transmission network and will contribute to more reliable supply for the rapidly growing Mumbai region. Further operational adjustments are expected as the new line is integrated into the wider grid.

The Maharashtra State Electricity Transmission Company Limited (Mahatransco) has commissioned the Babhaleshwar–Kudus 400 kV double-circuit transmission line, reinforcing power supply across the Mumbai Metropolitan Region. The new corridor will enable up to 3,000 Megawatt (MW) of additional transfer capacity and reduce transmission losses by around five MW, improving voltage stability and efficiency in Mumbai, Thane, Palghar and Ahilyanagar districts. The line is expected to ease pressure on existing corridors and support rising electricity demand in the region. The 228 km project was executed by Kalpataru Projects International Limited and involved the erection of 715 transmission towers, of which 485 towers with 304 circuit km of stringing were completed under the Nashik division and 230 towers with 152 circuit km were completed under the Vashi division. The scheme was originally approved in 2010 and had been slated for completion in 2013 but encountered technical and administrative hurdles that delayed delivery. Work was finally completed in March 2026 after the resolution of permissions and logistical issues. Challenges during construction included securing clearances near the Giant Metrewave Radio Telescope in Pune district, addressing land compensation disputes, obtaining forest clearances and resolving right of way constraints. In densely forested stretches materials were transported manually and advanced hotline stringing techniques were deployed in critical sections to expedite work while ensuring safety. The addition is expected to reduce load on the Padghe–Babhaleshwar transmission corridor and provide an additional power source to the Kudus substation. The project completion was overseen by the Chief Minister and Energy Minister, with support from the Minister of State for Energy, the Additional Chief Secretary for energy and the Mahatransco chairman and managing director, and involved coordination with Nashik and Vashi division officials, government agencies, police and forest departments. Mahatransco indicated the commissioning represents a significant enhancement of the state transmission network and will contribute to more reliable supply for the rapidly growing Mumbai region. Further operational adjustments are expected as the new line is integrated into the wider grid.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code