Mahatransco Commissions 400 kV Line To Boost Mumbai Power Supply
POWER & RENEWABLE ENERGY

Mahatransco Commissions 400 kV Line To Boost Mumbai Power Supply

The Maharashtra State Electricity Transmission Company Limited (Mahatransco) has commissioned the Babhaleshwar–Kudus 400 kV double-circuit transmission line, reinforcing power supply across the Mumbai Metropolitan Region. The new corridor will enable up to 3,000 Megawatt (MW) of additional transfer capacity and reduce transmission losses by around five MW, improving voltage stability and efficiency in Mumbai, Thane, Palghar and Ahilyanagar districts. The line is expected to ease pressure on existing corridors and support rising electricity demand in the region.

The 228 km project was executed by Kalpataru Projects International Limited and involved the erection of 715 transmission towers, of which 485 towers with 304 circuit km of stringing were completed under the Nashik division and 230 towers with 152 circuit km were completed under the Vashi division. The scheme was originally approved in 2010 and had been slated for completion in 2013 but encountered technical and administrative hurdles that delayed delivery. Work was finally completed in March 2026 after the resolution of permissions and logistical issues.

Challenges during construction included securing clearances near the Giant Metrewave Radio Telescope in Pune district, addressing land compensation disputes, obtaining forest clearances and resolving right of way constraints. In densely forested stretches materials were transported manually and advanced hotline stringing techniques were deployed in critical sections to expedite work while ensuring safety. The addition is expected to reduce load on the Padghe–Babhaleshwar transmission corridor and provide an additional power source to the Kudus substation.

The project completion was overseen by the Chief Minister and Energy Minister, with support from the Minister of State for Energy, the Additional Chief Secretary for energy and the Mahatransco chairman and managing director, and involved coordination with Nashik and Vashi division officials, government agencies, police and forest departments. Mahatransco indicated the commissioning represents a significant enhancement of the state transmission network and will contribute to more reliable supply for the rapidly growing Mumbai region. Further operational adjustments are expected as the new line is integrated into the wider grid.

The Maharashtra State Electricity Transmission Company Limited (Mahatransco) has commissioned the Babhaleshwar–Kudus 400 kV double-circuit transmission line, reinforcing power supply across the Mumbai Metropolitan Region. The new corridor will enable up to 3,000 Megawatt (MW) of additional transfer capacity and reduce transmission losses by around five MW, improving voltage stability and efficiency in Mumbai, Thane, Palghar and Ahilyanagar districts. The line is expected to ease pressure on existing corridors and support rising electricity demand in the region. The 228 km project was executed by Kalpataru Projects International Limited and involved the erection of 715 transmission towers, of which 485 towers with 304 circuit km of stringing were completed under the Nashik division and 230 towers with 152 circuit km were completed under the Vashi division. The scheme was originally approved in 2010 and had been slated for completion in 2013 but encountered technical and administrative hurdles that delayed delivery. Work was finally completed in March 2026 after the resolution of permissions and logistical issues. Challenges during construction included securing clearances near the Giant Metrewave Radio Telescope in Pune district, addressing land compensation disputes, obtaining forest clearances and resolving right of way constraints. In densely forested stretches materials were transported manually and advanced hotline stringing techniques were deployed in critical sections to expedite work while ensuring safety. The addition is expected to reduce load on the Padghe–Babhaleshwar transmission corridor and provide an additional power source to the Kudus substation. The project completion was overseen by the Chief Minister and Energy Minister, with support from the Minister of State for Energy, the Additional Chief Secretary for energy and the Mahatransco chairman and managing director, and involved coordination with Nashik and Vashi division officials, government agencies, police and forest departments. Mahatransco indicated the commissioning represents a significant enhancement of the state transmission network and will contribute to more reliable supply for the rapidly growing Mumbai region. Further operational adjustments are expected as the new line is integrated into the wider grid.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Ramky Infrastructure Q1 FY27 Revenue Rises 24.3%

Ramky Infrastructure Limited reported a 24.3% year-on-year increase in consolidated revenue from operations to Rs 471.2 crore for Q1 FY27, compared with Rs 3.79 billion in the corresponding quarter of FY26.Standalone revenue from operations rose 27.5% YoY to Rs 4.51 billion from Rs 3.54 billion, while total standalone income increased 35% to Rs 5.32 billion.Consolidated profit before tax stood at Rs 540.9 million during the quarter. The company highlighted a sharp sequential improvement compared with a pre-exceptional loss of Rs 190.1 million in Q4 FY26.Two of the three projects awarded during..

Next Story
Technology

LTTS Launches AgenticIQ AI Platform for Engineering

L&T Technology Services (LTTS) has launched AgenticIQ, an end-to-end agentic AI platform designed for engineering and manufacturing organisations.The platform is aimed at helping enterprises move beyond isolated AI pilots by enabling autonomous, multi-agent workflows across engineering, product development, manufacturing, industrial operations and customer experience.AgenticIQ is built on LTTS’ Engineering Intelligence portfolio and converts existing engineering capabilities into specialised, reusable AI agents. Its planning-first architecture is embedded into engineering and production ..

Next Story
Infrastructure Urban

Walplast Invests in Vura Bau Chemie to Expand Portfolio

Walplast Products Pvt. Ltd. has announced a strategic majority investment in Vura Bau Chemie LLP as part of its plans to strengthen and expand its building and construction materials portfolio.Vura Bau Chemie offers a specialised range of tile adhesives, waterproofing solutions and stone-care products. The investment is aligned with Walplast’s long-term strategy to expand its presence across the building materials value chain and address evolving requirements in India’s construction industry.The transaction will strengthen Walplast’s offerings in the tile adhesives and waterproofing segm..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement