Pune flyover construction faces hurdle as metro pillar maps delayed
ROADS & HIGHWAYS

Pune flyover construction faces hurdle as metro pillar maps delayed

The Pune Municipal Corporation (PMC) is facing a potential obstacle in the construction of the flyover on Sinhagad Road. The flyover ramps are situated at six designated locations where pillars for the metro station need to be erected. However, the progress has come to a standstill as the necessary maps for the construction have not been received by the corporation.

The PMC has been diligently following up on the erection of the pillars and has engaged in discussions with Mahametro, the organisation responsible for the metro project. Joint site inspections involving officials from both entities have been assured by Mahametro, and they have promised to promptly provide the required maps.

The purpose of constructing the flyover on Sinhagad Road is to alleviate traffic congestion. The project stretches from Rajaram Bridge to Funtime Theatre and is expected to be completed by 2025. At the same time, Mahametro has proposed a metro project connecting Khadakwasla to Hadapsar-Kharadi, with the Detailed Project Plan (DPR) already submitted to the Municipal Corporation for approval from the Standing Committee. Concurrently, progress is underway for the construction of the flyover.

The flyover comprises three ramps in the Rajaram Bridge area and three ramps near Funtime Theatre, Manikbaug, and Vitthalwadi. The metro station pillars are planned to be erected at the termination points of these ramps. Recognizing the potential hindrance the flyover ramps could pose to future metro work, ongoing discussions have taken place between the Municipal Corporation and Mahametro over the past few months regarding the construction of the metro pillars. An online meeting was held to address the matter, but significant progress has yet to be made.

To expedite the process, officials from the municipality and Mahametro conducted a site inspection on Wednesday, May 17. Following the inspection, Mahametro will prepare the necessary maps and plans for the pillars. In the meantime, the Municipal Corporation continues to make progress on the construction of the flyover pillars. Municipal officials are optimistic that once Mahametro provides the maps, the work can proceed smoothly.

The project involves constructing 31 pillars at an estimated cost of Rs 110 million. According to Mahametro, the municipality will erect the metro station pillars at the designated locations during the flyover construction. The recent site inspection has paved the way for timely provision of maps to the municipality.

Also Read
India Makes History: 100 km road constructed in 100 hours
NHAI issues tender for NH 56 expansion in Gujrat


The Pune Municipal Corporation (PMC) is facing a potential obstacle in the construction of the flyover on Sinhagad Road. The flyover ramps are situated at six designated locations where pillars for the metro station need to be erected. However, the progress has come to a standstill as the necessary maps for the construction have not been received by the corporation. The PMC has been diligently following up on the erection of the pillars and has engaged in discussions with Mahametro, the organisation responsible for the metro project. Joint site inspections involving officials from both entities have been assured by Mahametro, and they have promised to promptly provide the required maps. The purpose of constructing the flyover on Sinhagad Road is to alleviate traffic congestion. The project stretches from Rajaram Bridge to Funtime Theatre and is expected to be completed by 2025. At the same time, Mahametro has proposed a metro project connecting Khadakwasla to Hadapsar-Kharadi, with the Detailed Project Plan (DPR) already submitted to the Municipal Corporation for approval from the Standing Committee. Concurrently, progress is underway for the construction of the flyover. The flyover comprises three ramps in the Rajaram Bridge area and three ramps near Funtime Theatre, Manikbaug, and Vitthalwadi. The metro station pillars are planned to be erected at the termination points of these ramps. Recognizing the potential hindrance the flyover ramps could pose to future metro work, ongoing discussions have taken place between the Municipal Corporation and Mahametro over the past few months regarding the construction of the metro pillars. An online meeting was held to address the matter, but significant progress has yet to be made. To expedite the process, officials from the municipality and Mahametro conducted a site inspection on Wednesday, May 17. Following the inspection, Mahametro will prepare the necessary maps and plans for the pillars. In the meantime, the Municipal Corporation continues to make progress on the construction of the flyover pillars. Municipal officials are optimistic that once Mahametro provides the maps, the work can proceed smoothly. The project involves constructing 31 pillars at an estimated cost of Rs 110 million. According to Mahametro, the municipality will erect the metro station pillars at the designated locations during the flyover construction. The recent site inspection has paved the way for timely provision of maps to the municipality. Also Read India Makes History: 100 km road constructed in 100 hoursNHAI issues tender for NH 56 expansion in Gujrat

Next Story
Infrastructure Energy

Udangudi Thermal Plant’s First Unit Synced to Grid

The first 660 MW unit of the Udangudi Supercritical Thermal Power Project in Tamil Nadu has finally been synchronised with the grid, marking a long-awaited milestone for the state’s power sector. The project, being developed at a cost of Rs 13,076 crore by Tamil Nadu Power Generation and Distribution Corporation Ltd (TNGPCL), was originally scheduled for commissioning in 2021 but faced repeated delays due to court disputes and the COVID-19 pandemic.The synchronisation took place at 7.56 pm on Thursday, when the unit produced 42 MW during its initial trial run. Officials noted that the plant ..

Next Story
Infrastructure Transport

Kandla Port to Expand Operations Beyond Gujarat

In a strategic shift, Kandla Port, managed by the Deendayal Port Authority (DPA), is preparing to expand its operations beyond Gujarat for the first time. The authority has confirmed that it is exploring opportunities to manage both public and private terminals in Maharashtra and Karnataka.Kandla Port, located in Gujarat’s Kutch district, has traditionally been one of India’s busiest ports, handling more than 150 million tonnes of cargo in the last financial year. About 60 per cent of this was petroleum, oil, and lubricants, while the remainder included timber, food grains, chemicals, and ..

Next Story
Infrastructure Transport

Mumbai Port Seeks Nod to Reclaim Sea at Jawahar Dweep

The Mumbai Port Authority (MbPA) has proposed reclaiming 4.14 hectares of sea at Jawahar Dweep, also known as Butcher Island, to build additional crude oil storage facilities. The proposal, which will be placed before the Maharashtra Coastal Zone Management Authority for clearance, aims to improve turnaround times for ships handling petroleum and chemical cargo.Officials argue that the move is essential, as liquid petroleum and chemicals account for nearly 70 per cent of the port’s cargo. Currently, oil unloaded at Mumbai Port is piped to refineries in Mahul, but limited storage capacity has..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?