Pune flyover construction faces hurdle as metro pillar maps delayed
ROADS & HIGHWAYS

Pune flyover construction faces hurdle as metro pillar maps delayed

The Pune Municipal Corporation (PMC) is facing a potential obstacle in the construction of the flyover on Sinhagad Road. The flyover ramps are situated at six designated locations where pillars for the metro station need to be erected. However, the progress has come to a standstill as the necessary maps for the construction have not been received by the corporation.

The PMC has been diligently following up on the erection of the pillars and has engaged in discussions with Mahametro, the organisation responsible for the metro project. Joint site inspections involving officials from both entities have been assured by Mahametro, and they have promised to promptly provide the required maps.

The purpose of constructing the flyover on Sinhagad Road is to alleviate traffic congestion. The project stretches from Rajaram Bridge to Funtime Theatre and is expected to be completed by 2025. At the same time, Mahametro has proposed a metro project connecting Khadakwasla to Hadapsar-Kharadi, with the Detailed Project Plan (DPR) already submitted to the Municipal Corporation for approval from the Standing Committee. Concurrently, progress is underway for the construction of the flyover.

The flyover comprises three ramps in the Rajaram Bridge area and three ramps near Funtime Theatre, Manikbaug, and Vitthalwadi. The metro station pillars are planned to be erected at the termination points of these ramps. Recognizing the potential hindrance the flyover ramps could pose to future metro work, ongoing discussions have taken place between the Municipal Corporation and Mahametro over the past few months regarding the construction of the metro pillars. An online meeting was held to address the matter, but significant progress has yet to be made.

To expedite the process, officials from the municipality and Mahametro conducted a site inspection on Wednesday, May 17. Following the inspection, Mahametro will prepare the necessary maps and plans for the pillars. In the meantime, the Municipal Corporation continues to make progress on the construction of the flyover pillars. Municipal officials are optimistic that once Mahametro provides the maps, the work can proceed smoothly.

The project involves constructing 31 pillars at an estimated cost of Rs 110 million. According to Mahametro, the municipality will erect the metro station pillars at the designated locations during the flyover construction. The recent site inspection has paved the way for timely provision of maps to the municipality.

Also Read
India Makes History: 100 km road constructed in 100 hours
NHAI issues tender for NH 56 expansion in Gujrat


The Pune Municipal Corporation (PMC) is facing a potential obstacle in the construction of the flyover on Sinhagad Road. The flyover ramps are situated at six designated locations where pillars for the metro station need to be erected. However, the progress has come to a standstill as the necessary maps for the construction have not been received by the corporation. The PMC has been diligently following up on the erection of the pillars and has engaged in discussions with Mahametro, the organisation responsible for the metro project. Joint site inspections involving officials from both entities have been assured by Mahametro, and they have promised to promptly provide the required maps. The purpose of constructing the flyover on Sinhagad Road is to alleviate traffic congestion. The project stretches from Rajaram Bridge to Funtime Theatre and is expected to be completed by 2025. At the same time, Mahametro has proposed a metro project connecting Khadakwasla to Hadapsar-Kharadi, with the Detailed Project Plan (DPR) already submitted to the Municipal Corporation for approval from the Standing Committee. Concurrently, progress is underway for the construction of the flyover. The flyover comprises three ramps in the Rajaram Bridge area and three ramps near Funtime Theatre, Manikbaug, and Vitthalwadi. The metro station pillars are planned to be erected at the termination points of these ramps. Recognizing the potential hindrance the flyover ramps could pose to future metro work, ongoing discussions have taken place between the Municipal Corporation and Mahametro over the past few months regarding the construction of the metro pillars. An online meeting was held to address the matter, but significant progress has yet to be made. To expedite the process, officials from the municipality and Mahametro conducted a site inspection on Wednesday, May 17. Following the inspection, Mahametro will prepare the necessary maps and plans for the pillars. In the meantime, the Municipal Corporation continues to make progress on the construction of the flyover pillars. Municipal officials are optimistic that once Mahametro provides the maps, the work can proceed smoothly. The project involves constructing 31 pillars at an estimated cost of Rs 110 million. According to Mahametro, the municipality will erect the metro station pillars at the designated locations during the flyover construction. The recent site inspection has paved the way for timely provision of maps to the municipality. Also Read India Makes History: 100 km road constructed in 100 hoursNHAI issues tender for NH 56 expansion in Gujrat

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->