Service Roads and Land Acquisition Fast-tracked to Ease Navale Bridge Congestion
ROADS & HIGHWAYS

Service Roads and Land Acquisition Fast-tracked to Ease Navale Bridge Congestion

Authorities have stepped up efforts to tackle congestion at Navale bridge, with the Pune Metropolitan Region Development Authority (PMRDA) directing swift action on land acquisition, utility shifting, and signal installation.

At a review meeting, officials from PMRDA, the district collectorate, and Pune Municipal Corporation (PMC) finalised plans to build 12-metre-wide service roads on both sides of the bridge. The National Highways Authority of India (NHAI) has proposed acquiring 7,384 sq m of land over a 615-metre stretch, with the collectorate tasked to complete the process within three months.

To avoid delays, PMRDA will fund the shifting of underground electricity cables belonging to MSEDCL, while the relocation of two major PMC water pipelines has been ordered within 15 days. Authorities also agreed to immediately install traffic signals to regulate vehicular movement.

“The works will address long-standing congestion at Navale bridge. Once complete, daily commuters and residents will see major relief from traffic jams,” said Jitendra Dudi, Pune district collector.

The review meeting was attended by metropolitan commissioner Yogesh Mhase, additional metropolitan commissioner Deepak Singla, chief engineer Rinaz Pathan, additional commissioner Himmat Kharade, and senior representatives of PMRDA, NHAI, PMC, and the public works department.

News source: Hindustan Times


Authorities have stepped up efforts to tackle congestion at Navale bridge, with the Pune Metropolitan Region Development Authority (PMRDA) directing swift action on land acquisition, utility shifting, and signal installation.At a review meeting, officials from PMRDA, the district collectorate, and Pune Municipal Corporation (PMC) finalised plans to build 12-metre-wide service roads on both sides of the bridge. The National Highways Authority of India (NHAI) has proposed acquiring 7,384 sq m of land over a 615-metre stretch, with the collectorate tasked to complete the process within three months.To avoid delays, PMRDA will fund the shifting of underground electricity cables belonging to MSEDCL, while the relocation of two major PMC water pipelines has been ordered within 15 days. Authorities also agreed to immediately install traffic signals to regulate vehicular movement.“The works will address long-standing congestion at Navale bridge. Once complete, daily commuters and residents will see major relief from traffic jams,” said Jitendra Dudi, Pune district collector.The review meeting was attended by metropolitan commissioner Yogesh Mhase, additional metropolitan commissioner Deepak Singla, chief engineer Rinaz Pathan, additional commissioner Himmat Kharade, and senior representatives of PMRDA, NHAI, PMC, and the public works department.News source: Hindustan Times

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement