Service Roads and Land Acquisition Fast-tracked to Ease Navale Bridge Congestion
ROADS & HIGHWAYS

Service Roads and Land Acquisition Fast-tracked to Ease Navale Bridge Congestion

Authorities have stepped up efforts to tackle congestion at Navale bridge, with the Pune Metropolitan Region Development Authority (PMRDA) directing swift action on land acquisition, utility shifting, and signal installation.

At a review meeting, officials from PMRDA, the district collectorate, and Pune Municipal Corporation (PMC) finalised plans to build 12-metre-wide service roads on both sides of the bridge. The National Highways Authority of India (NHAI) has proposed acquiring 7,384 sq m of land over a 615-metre stretch, with the collectorate tasked to complete the process within three months.

To avoid delays, PMRDA will fund the shifting of underground electricity cables belonging to MSEDCL, while the relocation of two major PMC water pipelines has been ordered within 15 days. Authorities also agreed to immediately install traffic signals to regulate vehicular movement.

“The works will address long-standing congestion at Navale bridge. Once complete, daily commuters and residents will see major relief from traffic jams,” said Jitendra Dudi, Pune district collector.

The review meeting was attended by metropolitan commissioner Yogesh Mhase, additional metropolitan commissioner Deepak Singla, chief engineer Rinaz Pathan, additional commissioner Himmat Kharade, and senior representatives of PMRDA, NHAI, PMC, and the public works department.

News source: Hindustan Times


Authorities have stepped up efforts to tackle congestion at Navale bridge, with the Pune Metropolitan Region Development Authority (PMRDA) directing swift action on land acquisition, utility shifting, and signal installation.At a review meeting, officials from PMRDA, the district collectorate, and Pune Municipal Corporation (PMC) finalised plans to build 12-metre-wide service roads on both sides of the bridge. The National Highways Authority of India (NHAI) has proposed acquiring 7,384 sq m of land over a 615-metre stretch, with the collectorate tasked to complete the process within three months.To avoid delays, PMRDA will fund the shifting of underground electricity cables belonging to MSEDCL, while the relocation of two major PMC water pipelines has been ordered within 15 days. Authorities also agreed to immediately install traffic signals to regulate vehicular movement.“The works will address long-standing congestion at Navale bridge. Once complete, daily commuters and residents will see major relief from traffic jams,” said Jitendra Dudi, Pune district collector.The review meeting was attended by metropolitan commissioner Yogesh Mhase, additional metropolitan commissioner Deepak Singla, chief engineer Rinaz Pathan, additional commissioner Himmat Kharade, and senior representatives of PMRDA, NHAI, PMC, and the public works department.News source: Hindustan Times

Next Story
Infrastructure Transport

Railways approves major upgrade for Telangana traction lines

The Ministry of Railways has approved the upgradation of the electric traction system in two crucial railway sections — Medchal–Mudkhed (225 km) and Mahbubnagar–Dhone (184 km). The projects, costing Rs 1.93 billion and Rs 1.23 billion respectively, will enhance the electric traction capacity from 1X25 KV to 2X25 KV. The work includes modifications to circuit breakers and switching stations, along with the installation of additional conductors. These routes serve as vital links between Northern and Southern India via Hyderabad. Once completed, the upgraded system will reduce voltage dro..

Next Story
Infrastructure Transport

Adani to invest Rs 425 billion more in Maharashtra’s Dighi Port

The Adani Group has committed to invest an additional Rs 425 billion in the Dighi Port project, located along Maharashtra’s coastal Konkan belt, government officials announced on Monday. Adani Ports and Special Economic Zone (APSEZ)-run Dighi Ports signed a memorandum of understanding (MoU) with the Maharashtra government to undertake the expansion of the port and related infrastructure. This new commitment comes as part of a broader investment initiative by the state. Chief Minister Devendra Fadnavis said the agreement is among 15 MoUs worth over Rs 560 billion signed during the opening d..

Next Story
Infrastructure Transport

HUDCO, JNPA sign Rs 50 billion deal for port development

In a strategic move, the Housing and Urban Development Corporation Ltd (HUDCO) has signed a Memorandum of Understanding (MoU) with the Jawaharlal Nehru Port Authority (JNPA) for an investment of Rs 50 billion to revamp and develop port infrastructure. The non-binding agreement is intended to strengthen cooperation on both existing and upcoming infrastructure projects, with a focus on development, financing, and refinancing of port facilities at the Jawaharlal Nehru Port. The MoU was formalised with the signatures of Sanjay Kulshrestha, Chairman and Managing Director of HUDCO, and Unmesh Shar..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?