Thane: Mankoli bridge to open in April 2023
ROADS & HIGHWAYS

Thane: Mankoli bridge to open in April 2023

The Mankoli bridge being constructed on the creek between Retibunder Mothagaon on the Dombivali side and Mankoli on the Bhiwandi side will be opened for the public in April 2023, informed the Mumbai Metropolitan Region Development Authority (MMRDA) Commissioner SVR Srinivas. The bridge will reduce the time of commute between Thane-Dombivali from more than an hour to half an hour and will ease traffic congestion in the city.

A meeting was held between top Kalyan-Dombivali Municipal Corporation (KDMC) and MMRDA officials at the MMRDA office to discuss the current status of Mankoli bridge to review progress. Srinivas said the work on the bridge is in its final stages and the milestone addition will be completed by April 2023.

The foundation stone for the Mankoli bridge was laid by former Chief Minister Devendra Fadnavis on Sep 18, 2016. The completion time set for this bridge was 36 months. Fadnavis, at the time, appealed to the then MMRDA commissioner UPS Madan to complete the work with the help of available technical assistance within the next 18 months.

The Mankoli bridge being constructed on the creek between Retibunder Mothagaon on the Dombivali side and Mankoli on the Bhiwandi side will be opened for the public in April 2023, informed the Mumbai Metropolitan Region Development Authority (MMRDA) Commissioner SVR Srinivas. The bridge will reduce the time of commute between Thane-Dombivali from more than an hour to half an hour and will ease traffic congestion in the city. A meeting was held between top Kalyan-Dombivali Municipal Corporation (KDMC) and MMRDA officials at the MMRDA office to discuss the current status of Mankoli bridge to review progress. Srinivas said the work on the bridge is in its final stages and the milestone addition will be completed by April 2023. The foundation stone for the Mankoli bridge was laid by former Chief Minister Devendra Fadnavis on Sep 18, 2016. The completion time set for this bridge was 36 months. Fadnavis, at the time, appealed to the then MMRDA commissioner UPS Madan to complete the work with the help of available technical assistance within the next 18 months.

Next Story
Real Estate

ArisInfra Secures Rs 400 Million Mandate in Mumbai

ArisInfra Solutions Ltd., via its subsidiary ArisUnitern RE Solutions Private Limited, has secured a prestigious Development Management (DM) mandate from AVS Housing and Construction LLP (AVS Group) for Rudraksh Towers – Wing A. This premium residential development is located in Mulund, one of Mumbai’s most sought-after real estate micro-markets.The mandate carries a revenue potential exceeding Rs 400 million, with significant margin gains anticipated through ArisInfra’s integrated delivery model. This model provides a full-stack solution encompassing development management, project exec..

Next Story
Infrastructure Urban

Ganesh Narayanan Appointed MD & CEO of CA Grameen

CreditAccess Grameen Limited, India’s largest Non-Banking Financial Company-Micro Finance Institution (NBFC-MFI), has appointed Mr Ganesh Narayanan as Managing Director and Chief Executive Officer for a five-year term, effective 5 August 2025. This follows approval from the Reserve Bank of India (RBI), which formalises the appointments already endorsed by the company’s Board and shareholders during the Annual General Meeting.Mr Narayanan brings over 27 years of experience in banking and financial services, having previously held leadership roles at ICICI Bank, Fullerton India Credit Co. (n..

Next Story
Infrastructure Urban

Supreme Court Sets Rules on Regulatory Asset Recovery

The Hon’ble Supreme Court of India has, on 6 August 2025, pronounced its judgment and disposed of the Writ Petitions and Civil Appeals filed in 2014 by BSES Yamuna Power Limited and BSES Rajdhani Power Limited—both material subsidiaries of the company—regarding the recovery of Regulatory Assets.The petitions challenged non-cost-reflective tariffs, the unlawful creation of Regulatory Assets, and the delay in their liquidation. After extensive hearings involving State Governments and State Electricity Regulatory Commissions, the Court had reserved judgment on 20 February 2025.In its final ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?