+
Kanpur Metro: Third TBM Lowered for Underground Construction
RAILWAYS & METRO RAIL

Kanpur Metro: Third TBM Lowered for Underground Construction

The process of fully descending all components of the third Tunnel Boring Machine (TBM) into the launching shaft beneath the ongoing construction of Kanpur Central Metro station has been successfully accomplished. The final segment of the TBM, known as the 'Tail Shield', was carefully placed into the 18-meter deep, 21-meter long, and 25-meter wide launching shaft.

This TBM marks the third machine employed in the Kanpur Metro Rail project and holds the distinction of being the pioneer TBM for the subterranean section connecting Kanpur Central and Transport Nagar. This particular machine will facilitate the construction of an approximately 1250-meter tunnel along the 'Upline' from Kanpur Central to Nayaganj.

In the imminent future, an additional TBM will be lowered into the Kanpur Central-Transport Nagar underground stretch, spanning around 4.24 kilometers, for excavation work in the 'downline'.

The procedure for positioning the TBM within the launching shaft of the in-progress Kanpur Central Metro station commenced with the initial lowering of the approximately 120-ton 'front shield'. Subsequently, the cutterhead, middle shield, and screw conveyor were sequentially introduced below the surface. Once within the launching shaft, these TBM components will be meticulously aligned, and mechanical elements and wiring will be interconnected to finalize the assembly. Following this process, the TBM machine will be stationed along the 'upline' to forge a tunnel spanning 1250 meters. Subsequently, the machine will be initiated for excavation in the forthcoming days.

See also:
9 Bidders for Kanpur Metro Line-2’s KNPCC-11 Underground Work
Elevated, underground sections archives key milestones at Kanpur Metro


The process of fully descending all components of the third Tunnel Boring Machine (TBM) into the launching shaft beneath the ongoing construction of Kanpur Central Metro station has been successfully accomplished. The final segment of the TBM, known as the 'Tail Shield', was carefully placed into the 18-meter deep, 21-meter long, and 25-meter wide launching shaft. This TBM marks the third machine employed in the Kanpur Metro Rail project and holds the distinction of being the pioneer TBM for the subterranean section connecting Kanpur Central and Transport Nagar. This particular machine will facilitate the construction of an approximately 1250-meter tunnel along the 'Upline' from Kanpur Central to Nayaganj. In the imminent future, an additional TBM will be lowered into the Kanpur Central-Transport Nagar underground stretch, spanning around 4.24 kilometers, for excavation work in the 'downline'. The procedure for positioning the TBM within the launching shaft of the in-progress Kanpur Central Metro station commenced with the initial lowering of the approximately 120-ton 'front shield'. Subsequently, the cutterhead, middle shield, and screw conveyor were sequentially introduced below the surface. Once within the launching shaft, these TBM components will be meticulously aligned, and mechanical elements and wiring will be interconnected to finalize the assembly. Following this process, the TBM machine will be stationed along the 'upline' to forge a tunnel spanning 1250 meters. Subsequently, the machine will be initiated for excavation in the forthcoming days. See also: 9 Bidders for Kanpur Metro Line-2’s KNPCC-11 Underground WorkElevated, underground sections archives key milestones at Kanpur Metro

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement