Land Acquisition for Nanded-Wardha Rail Reaches 90% Completion
RAILWAYS & METRO RAIL

Land Acquisition for Nanded-Wardha Rail Reaches 90% Completion

Approximately 90% of the land acquisition required for the Nanded-Wardha rail route has already been accomplished. This railway route is of vital importance as it will establish crucial connectivity between the Marathwada and Vidarbha regions. The total length of this rail route is 284.6 kilometers, and it comes with a financial allocation of Rs 34.45 billion.

According to the Central Railway (CR) spokesperson, "A total of 2,139 hectares of land is necessary for the Nanded-Wardha rail line, and nearly 1,912 hectares have already been procured. The process to acquire the remaining 227 hectares is currently underway."

The completion of this new railway line is expected to significantly enhance rail connectivity between Hingoli and Nanded in Marathwada and Wardha, Yavatmal, and Washim districts in Vidarbha. This development is anticipated to have a positive impact on the socio-economic growth of these regions. The funding for the project is divided, with the Indian Railways covering 60% of the costs and the state government responsible for the remaining 40%. Additionally, the Deoli station, situated 15 kilometers from Wardha, was inaugurated on August 25.

CR authorities have reported, "The Wardha-Deoli-Bhidi-Kalamb section (38.6 kilometers) of the Wardha-Nanded rail route is nearing completion." So far, 35 major bridges on the route have been successfully constructed, and work on 79 minor bridges and road underbridges has also been completed.

Railway activist Gautam Nahata emphasized the urgency of expediting the Wardha-Nanded rail project. He stated, "Both the Marathwada and Vidarbha regions in the state are considered underdeveloped, and improved rail connectivity would play a pivotal role in their socio-economic advancement."

See also:
Nashik-Pune rail project beacons a new corridor
Maharashtra govt approves survey for Jalna-Nanded expressway construction

Approximately 90% of the land acquisition required for the Nanded-Wardha rail route has already been accomplished. This railway route is of vital importance as it will establish crucial connectivity between the Marathwada and Vidarbha regions. The total length of this rail route is 284.6 kilometers, and it comes with a financial allocation of Rs 34.45 billion. According to the Central Railway (CR) spokesperson, A total of 2,139 hectares of land is necessary for the Nanded-Wardha rail line, and nearly 1,912 hectares have already been procured. The process to acquire the remaining 227 hectares is currently underway. The completion of this new railway line is expected to significantly enhance rail connectivity between Hingoli and Nanded in Marathwada and Wardha, Yavatmal, and Washim districts in Vidarbha. This development is anticipated to have a positive impact on the socio-economic growth of these regions. The funding for the project is divided, with the Indian Railways covering 60% of the costs and the state government responsible for the remaining 40%. Additionally, the Deoli station, situated 15 kilometers from Wardha, was inaugurated on August 25. CR authorities have reported, The Wardha-Deoli-Bhidi-Kalamb section (38.6 kilometers) of the Wardha-Nanded rail route is nearing completion. So far, 35 major bridges on the route have been successfully constructed, and work on 79 minor bridges and road underbridges has also been completed. Railway activist Gautam Nahata emphasized the urgency of expediting the Wardha-Nanded rail project. He stated, Both the Marathwada and Vidarbha regions in the state are considered underdeveloped, and improved rail connectivity would play a pivotal role in their socio-economic advancement. See also: Nashik-Pune rail project beacons a new corridorMaharashtra govt approves survey for Jalna-Nanded expressway construction

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code