Railway rejects bids for station redevelopment work
RAILWAYS & METRO RAIL

Railway rejects bids for station redevelopment work

The railways has cancelled tenders for the redevelopment of the New Delhi and Ahmedabad train stations because the bids received were "excessively" high in comparison to the cost projected by the national transporter.

Because the lowest bidders quoted rates far in excess of the estimated costs, the railway was left with no choice but to discharge the tenders and review them.

The Union Cabinet approved Rs 100 billion in September 2022 for the rebuilding of three major railway stations: New Delhi, Ahmedabad, and Mumbai's Chhatrapati Shivaji Maharaj Terminus (CSMT).

See also:
Railway project to rejuvenate Gwalior station on lines of airport
Restoration of Nandi Halt station started by South Western Railway


Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

The railways has cancelled tenders for the redevelopment of the New Delhi and Ahmedabad train stations because the bids received were excessively high in comparison to the cost projected by the national transporter. Because the lowest bidders quoted rates far in excess of the estimated costs, the railway was left with no choice but to discharge the tenders and review them. The Union Cabinet approved Rs 100 billion in September 2022 for the rebuilding of three major railway stations: New Delhi, Ahmedabad, and Mumbai's Chhatrapati Shivaji Maharaj Terminus (CSMT). See also: Railway project to rejuvenate Gwalior station on lines of airport Restoration of Nandi Halt station started by South Western Railway

Next Story
Infrastructure Transport

Indian Railways Marks New Milestone with 4.5 km Long ‘Rudrastra’ Trial

Indian Railways has successfully conducted the trial run of Asia’s longest freight train, named ‘Rudrastra’, achieving a new milestone in cargo transportation, as per news reports. The 4.5 km-long train began its trial from Ganjkhwaja railway station in Chandauli, Uttar Pradesh, and travelled to Garhwa in Jharkhand. Covering a distance of 209 km in 5 hours and 10 minutes, it maintained an average speed of 40.5 km per hour. The train was formed by combining three long-haul racks, with ..

Next Story
Infrastructure Energy

UltraTech Launches India’s First On-Site Hybrid RTC Renewable Energy Project

UltraTech Cement has operationalised a 7.5 MW round-the-clock (RTC) hybrid renewable energy project at its Sewagram Cement Works in Gujarat. The first-of-its-kind solution combines bifacial solar modules with trackers, wind energy and battery storage, co-located on-site, to ensure uninterrupted power for cement manufacturing without grid reliance. The project was executed in collaboration with clean energy solutions provider Gentari. Installed as a behind-the-meter system, it is the country..

Next Story
Infrastructure Transport

Patna Metro Trials Successful, Red Line Priority Corridor to Launch This Month

Patna is set to roll out its first metro rail service later this month, with successful trial runs conducted on the Red Line priority corridor, the Patna Metro Rail Corporation announced.On 7 September, a metro train completed a test run between the Patna depot and Bhootnath station. Officials said the trials involved rigorous checks of rolling stock fitness, overhead electrification (OHE), and track alignment and stability to ensure operational safety and performance.The corridor from the New Pataliputra Bus Terminal to Bhoothnath has been designated as the priority stretch and will be the fi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?