Railways Targets Kavach Rollout On Key Routes In 2026
RAILWAYS & METRO RAIL

Railways Targets Kavach Rollout On Key Routes In 2026

After missing its December 2025 deadline, Indian Railways is now aiming to operationalise the indigenous automatic train protection system, Kavach, on the Delhi–Mumbai and Delhi–Howrah routes sometime in 2026, officials said, citing steady progress and an aggressive execution strategy.

Kavach is a technology-intensive safety system designed to assist loco pilots in maintaining prescribed speed limits by automatically applying brakes if the driver fails to respond. Officials said around 25 per cent of the work on these high-density routes has already been commissioned and is ready for use, while major components for the remaining 75 per cent have been installed. Efforts are now focused on integrating and operationalising the system end to end.

The Ministry of Railways had earlier said on August 7, 2024, that Kavach installation on these routes would be completed by March 2025. This deadline was later extended to December 2025, as outlined in the budget document titled ‘Railways Estimates for Revised Estimates 2024–25 and Budget Estimates 2025–26’ released on February 1, 2025.

Providing an update in the Lok Sabha on December 17, Railway Minister Ashwini Vaishnaw said Kavach Version 4.0 has been successfully commissioned on 738 route km following extensive trials. This includes the Palwal–Mathura–Nagda section, covering 633 route km on the Delhi–Mumbai corridor, and the Howrah–Bardhaman section, spanning 105 route km on the Delhi–Howrah route.

The Minister added that optical fibre cable has been laid along 7,129 km, supported by the installation of 800 telecom towers. Other critical components have also progressed, with Station Kavach installed at 860 stations, track-side equipment deployed across 5,672 route km, and Loco Kavach fitted on 4,154 locomotives.

Once fully operational, Kavach is expected to significantly enhance safety on some of India’s busiest rail corridors by reducing the risk of human error and improving overall train control.

After missing its December 2025 deadline, Indian Railways is now aiming to operationalise the indigenous automatic train protection system, Kavach, on the Delhi–Mumbai and Delhi–Howrah routes sometime in 2026, officials said, citing steady progress and an aggressive execution strategy. Kavach is a technology-intensive safety system designed to assist loco pilots in maintaining prescribed speed limits by automatically applying brakes if the driver fails to respond. Officials said around 25 per cent of the work on these high-density routes has already been commissioned and is ready for use, while major components for the remaining 75 per cent have been installed. Efforts are now focused on integrating and operationalising the system end to end. The Ministry of Railways had earlier said on August 7, 2024, that Kavach installation on these routes would be completed by March 2025. This deadline was later extended to December 2025, as outlined in the budget document titled ‘Railways Estimates for Revised Estimates 2024–25 and Budget Estimates 2025–26’ released on February 1, 2025. Providing an update in the Lok Sabha on December 17, Railway Minister Ashwini Vaishnaw said Kavach Version 4.0 has been successfully commissioned on 738 route km following extensive trials. This includes the Palwal–Mathura–Nagda section, covering 633 route km on the Delhi–Mumbai corridor, and the Howrah–Bardhaman section, spanning 105 route km on the Delhi–Howrah route. The Minister added that optical fibre cable has been laid along 7,129 km, supported by the installation of 800 telecom towers. Other critical components have also progressed, with Station Kavach installed at 860 stations, track-side equipment deployed across 5,672 route km, and Loco Kavach fitted on 4,154 locomotives. Once fully operational, Kavach is expected to significantly enhance safety on some of India’s busiest rail corridors by reducing the risk of human error and improving overall train control.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement