DJB Says Forest Curbs Delay Sangam Vihar Sewer Work
WATER & WASTE

DJB Says Forest Curbs Delay Sangam Vihar Sewer Work

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions.

The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks.

The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work.

Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions. The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks. The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work. Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

Related Stories

Gold Stories

Next Story
Real Estate

Mumbai Central Emerges as a New Luxury Residential Corridor

Mumbai Central is emerging as a growing premium residential micro-market in South Mumbai, supported by improved connectivity, new redevelopment projects and proximity to major business districts.Residential capital values in the area are currently estimated at around ₹50,000-₹85,000 per sq ft, compared with ₹85,000 to more than ₹1.5 lakh per sq ft in parts of Worli, according to market estimates cited by industry players. The area has also recorded annual appreciation of around 14-18 per cent, although transaction activity and pricing vary across projects and locations.The area's chang..

Next Story
Technology

Bridgestone India Opens New Select Store in Pune

Bridgestone India has opened a new Bridgestone Select Store at Hinjewadi Phata in Pune, strengthening its retail presence in the city and Maharashtra.The new outlet, Deepraj Tyres, is located at Hinjewadi Phata/Wakad Bridge. Designed as a one-stop destination for passenger vehicle owners, the store offers tyres, expert guidance and wheel care services supported by modern equipment.“Pune is an important market for Bridgestone. The opening of this Select Store in the city reflects our commitment to offering customers easy access to premium products and trusted services. Our focus is on buildin..

Next Story
Infrastructure Transport

VECV, Rosmerta Partner for Authorised Vehicle Scrapping in NCR

VE Commercial Vehicles (VECV) and Rosmerta Auto Recycling Pvt Ltd (RARPL) have entered into a strategic partnership to facilitate the authorised scrapping and recycling of end-of-life (ELV) commercial vehicles across the National Capital Region (NCR).The collaboration will provide Eicher Trucks and Buses dealers and customers with access to a structured, transparent and compliant vehicle scrapping process. It aims to help commercial vehicle owners retire ageing trucks and buses through authorised channels while supporting fleet renewal and responsible resource recovery.The partnership comes as..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code