DJB Says Forest Curbs Delay Sangam Vihar Sewer Work
WATER & WASTE

DJB Says Forest Curbs Delay Sangam Vihar Sewer Work

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions.

The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks.

The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work.

Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions. The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks. The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work. Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

KONE Opens India's First Digital Experience Centre in Pune

KONE, a global elevator and escalator manufacturer, has inaugurated its first Digital Experience Centre (DEC) in India, located in Pune. The facility aims to showcase how artificial intelligence (AI), connectivity and data-driven technologies can enhance customer experiences and improve building operations.The centre was inaugurated by Jussi Herlin, Executive Vice Chair, KONE Corporation; Philippe Delorme, President and CEO, KONE; and Nandan Nilekani, Co-founder and Chairman of the Board, Infosys.Designed as an interactive customer environment, the facility demonstrates digital solutions cover..

Next Story
Infrastructure Urban

CII GreenCo Launches Circularity Guidelines for Indian Industry

The Confederation of Indian Industry (CII) GreenCo Council has launched the CII GreenCo Circularity Guidelines – Pilot Version at the 17th CII GreenCo Waste & Resource Management Summit 2026 in Chennai. The initiative aims to strengthen resource efficiency, waste reduction and circular economy practices across Indian manufacturing and process industries.The guidelines introduce a structured framework with circularity indices covering raw materials, consumables, packaging and other resource inputs. These indicators will help industries assess existing practices, identify opportunities to ..

Next Story
Infrastructure Energy

Global Electronics Association Launches IPC-1783-CO2E Standard

The Global Electronics Association has introduced IPC-1783-CO2E, a new international standard aimed at improving consistency, transparency and comparability in product carbon footprint reporting across the electronics manufacturing industry.The standard, titled International Standard for Data Collection and Reporting of CO2 Equivalent (CO2e) Emissions for the Electronics Manufacturing Supply Chain, provides industry-specific guidance for collecting, estimating and reporting carbon emissions data.With increasing regulatory requirements and customer expectations, electronics manufacturers face c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code