DJB Says Forest Curbs Delay Sangam Vihar Sewer Work
WATER & WASTE

DJB Says Forest Curbs Delay Sangam Vihar Sewer Work

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions.

The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks.

The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work.

Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions. The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks. The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work. Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Emiza Expands Bhiwandi Fulfilment Capacity by 2.32 Lakh Sq Ft

Emiza, a leading third-party logistics (3PL) provider, has expanded its Mumbai operations with the launch of two new fulfilment facilities in Bhiwandi, adding a combined capacity of 2.32 lakh sq ft to its network.The new facilities, spread across 75,000 sq ft and 1,57,000 sq ft, mark Emiza’s fifth and sixth warehouses in the Mumbai region. The expansion strengthens the company’s fulfilment infrastructure in Western India amid the rapid growth of India’s digital commerce ecosystem.With increasing online consumption, wider product categories and rising customer expectations for faster deli..

Next Story
Infrastructure Urban

Ingersoll Rand Showcases Air Solutions for Semiconductor Sector

Ingersoll Rand will showcase its advanced compressed air solutions for India’s growing semiconductor ecosystem at SEMICON India 2026, scheduled from September 17–19 at Yashobhoomi, New Delhi.The company will display its portfolio of oil-free compressors, centrifugal compression technologies and advanced air treatment systems at Stall No. 1156, Hall No. 1. The solutions are designed to address the stringent air quality, reliability and efficiency requirements of semiconductor manufacturing applications.With India accelerating investments across semiconductor manufacturing, packaging, equipm..

Next Story
Infrastructure Energy

RECPDCL Transfers Musalgaon Transmission SPV to MSETCL

REC Power Development and Consultancy Limited (RECPDCL), a wholly owned subsidiary of REC Limited, has handed over Musalgaon Power Transmission Limited, a project-specific Special Purpose Vehicle (SPV), to Maharashtra State Electricity Transmission Company Limited (MSETCL).MSETCL emerged as the successful bidder through the Tariff-Based Competitive Bidding (TBCB) process conducted by RECPDCL, the Bid Process Coordinator, for developing Maharashtra’s intra-state transmission project on a Build, Own, Operate and Transfer (BOOT) basis.The SPV was handed over by Shri Ratnesh Kumar, General Manag..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code