DJB Says Forest Curbs Delay Sangam Vihar Sewer Work
WATER & WASTE

DJB Says Forest Curbs Delay Sangam Vihar Sewer Work

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions.

The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks.

The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work.

Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

The Delhi Jal Board (DJB) told the National Green Tribunal (NGT) that sewer network work in parts of Sangam Vihar has been delayed by restrictions on construction in forest land and by pending road cutting permissions. The update was filed as a status report in a case on untreated sewage and sets out progress under the Delhi Sewage Master Plan-2031. The utility said phased work reflects complex ground conditions. The affidavit said Phase II covers several colonies and has advanced in a staggered manner because of peculiar site conditions and other impediments. Sewer lines have been completed in eight colonies unaffected by forest encroachments, while work in 14 other colonies has been limited to portions outside forest land; 11 of those sites are partly on forest land. Affected pockets include Sangam Vihar's L, C, D and F-3 blocks. The DJB reported that work in the partly forest sites is about 25 per cent complete and has been slowed by delays in statutory permissions, with projected completion by March 2027. Of the remaining three Phase II colonies, sewer laying has been finished in one, while work in two colonies in Durga Vihar, Deoli Extension, remains stalled because of public hindrance and local resistance. The utility said the executing agency could not complete the balance work. Peripheral trunk sewer lines have been completed along major roads leading out of Sangam Vihar to intercept domestic sewage in storm water drains and convey it to the sewer network along Mehrauli-Badarpur Road and eventually to the 170 million (mn) gallons per day Okhla sewage treatment plant. For Phase I, sewer lines have already been laid in several unauthorised colonies including Shiv Park, Jawahar Park and Krishna Park Extension. The affidavit noted delays in a separate balance work package after the original contract awarded in May 2018 was terminated in September 2022. A fresh work order worth Rs 313.1 mn was issued in November 2025 to complete the balance package.

Next Story
Infrastructure Transport

Fadnavis Urges Completion Of Metro Projects Within Three Years

Maharashtra Chief Minister Devendra Fadnavis has directed officials to ensure that all metro rail projects in the state are completed within three years from the start of construction as the government accelerates expansion of its urban rapid transit network. Chairing the state cabinet’s Infrastructure Committee, he said the expansion in Mumbai, Pune, Nagpur and the Mumbai Metropolitan Region will strengthen safe, fast and environment-friendly public transport and support future urban growth. An official statement said the state currently has 174 km of operational metro corridors, while 291 ..

Next Story
Infrastructure Urban

Vedanta Aluminium Raises Rs 135 bn Loan After Demerger

Vedanta Aluminium Metal Ltd has raised Rs 135 bn from a syndicate of banks, marking the first significant local currency loan for the business since the Vedanta Group split into separately listed firms. The financing was arranged with Axis Bank Ltd, HDFC Bank Ltd and ICICI Bank Ltd involved, and reflects efforts to establish independently financed entities following a court-approved demerger. Axis Bank signed a loan agreement supplying Rs 55 bn, while HDFC Bank and ICICI Bank will together provide about Rs 80 bn. Lenders are expected to syndicate portions of the facility with Axis Bank launchi..

Next Story
Infrastructure Transport

Airbus Selects Aerolloy To Supply Titanium Castings

Airbus has selected Aerolloy Technologies, a wholly owned subsidiary of PTC Industries (PTC), to develop, qualify and supply titanium castings for the A320neo, A330neo and A350 aircraft programmes. The agreement establishes the development, qualification and industrialisation pathway for Aerolloy to progress into production supply, subject to the successful completion of Airbus qualification and programme requirements. The selection marks a significant milestone for the Indian manufacturer in the global commercial aerospace supply chain and follows Airbus's evaluation process. Under the agreem..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement