BESS Helps Singareni Save Rs Two Point Six mn With Surplus Solar
POWER & RENEWABLE ENERGY

BESS Helps Singareni Save Rs Two Point Six mn With Surplus Solar

Singareni Collieries Company Limited has begun harnessing surplus solar generation by deploying a battery energy storage system (BESS) to capture daytime output at the Mandamarri solar complex. The Singareni battery unit is the first and largest BESS project in Telangana and was commissioned under state government directions. The system stores excess solar energy in batteries for later use rather than allowing it to be supplied free to the grid.

In its first four months of operation the BESS stored 335,485 units of electricity and generated financial savings of Rs two point five seven million (mn) for Singareni, according to company officials. The facility captures surplus daytime output that would otherwise be exported without compensation and allows that energy to be used when demand rises or during lower production periods. Company representatives described the installation as an experimental measure to improve utilisation of captive solar assets.

The experimental BESS was installed in January with an investment of Rs 25 mn and serves as an auxiliary facility to the 28 megawatt (MW) Mandamarri solar plant. The project was developed following instructions from the chief minister and the energy minister as part of efforts to strengthen the operational efficiency of state energy assets. Officials indicated that the initiative aims to reduce losses and secure more predictable energy availability for Singareni operations.

The results in the early months are being monitored to assess scalability and cost benefits for similar plants across the state. If sustained, the savings and improved load management could inform wider deployment of storage solutions within the public sector. Singareni will continue to record performance data while the state evaluates the potential for further investment in storage technology.

Singareni Collieries Company Limited has begun harnessing surplus solar generation by deploying a battery energy storage system (BESS) to capture daytime output at the Mandamarri solar complex. The Singareni battery unit is the first and largest BESS project in Telangana and was commissioned under state government directions. The system stores excess solar energy in batteries for later use rather than allowing it to be supplied free to the grid. In its first four months of operation the BESS stored 335,485 units of electricity and generated financial savings of Rs two point five seven million (mn) for Singareni, according to company officials. The facility captures surplus daytime output that would otherwise be exported without compensation and allows that energy to be used when demand rises or during lower production periods. Company representatives described the installation as an experimental measure to improve utilisation of captive solar assets. The experimental BESS was installed in January with an investment of Rs 25 mn and serves as an auxiliary facility to the 28 megawatt (MW) Mandamarri solar plant. The project was developed following instructions from the chief minister and the energy minister as part of efforts to strengthen the operational efficiency of state energy assets. Officials indicated that the initiative aims to reduce losses and secure more predictable energy availability for Singareni operations. The results in the early months are being monitored to assess scalability and cost benefits for similar plants across the state. If sustained, the savings and improved load management could inform wider deployment of storage solutions within the public sector. Singareni will continue to record performance data while the state evaluates the potential for further investment in storage technology.

Next Story
Real Estate

CREDAI-MCHI to Host 10th Design & Construction Conference

CREDAI-MCHI will host the 10th anniversary edition of its Design & Construction Conference on August 19, 2026, at the Jio World Convention Centre in Mumbai.The event is expected to bring together more than 500 procurement leaders, construction heads, architects, consultants and senior real estate decision-makers, alongside over 50 construction and ancillary brands.The conference will feature product launches, technology showcases, knowledge sessions, strategic business-to-business networking and recognition of procurement professionals contributing to the transformation of the construction..

Next Story
Infrastructure Energy

BorgWarner Wins Extension for High-Voltage Inverter Programmes

BorgWarner has secured a major extension of several high-volume high-voltage inverter programmes from a leading European automotive manufacturer.The contracts cover updated inverter designs for plug-in hybrid and 800V battery-electric vehicle applications. Production is scheduled to begin in 2029.Isabelle McKenzie, President and General Manager, BorgWarner PowerDrive Systems, said the programme extensions demonstrate the company’s position in power electronics and reflect the strength of its technology, in-house expertise and customer relationships.For plug-in hybrid vehicles, BorgWarner wil..

Next Story
Infrastructure Urban

Castrol India Q2 Profit Rises 43% to Rs 3.48 bn

Castrol India reported a 43 per cent year-on-year increase in profit after tax to Rs 3.48 billion for the quarter ended June 30, 2026, supported by growth across its consumer, industrial and institutional businesses.Revenue from operations increased 25 per cent to Rs 18.71 billion during the second quarter of 2026, compared with Rs 14.97 billion in the corresponding period of 2025. EBITDA rose 41 per cent to Rs 4.94 billion from Rs 3.50 billion.Sequentially, revenue increased from Rs 15.45 billion in the first quarter of 2026, while EBITDA rose from Rs 3.29 billion. Profit after tax increased ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement