+
CERC Approves Tariff For Power Grid Rajasthan Solar Evacuation Asset
POWER & RENEWABLE ENERGY

CERC Approves Tariff For Power Grid Rajasthan Solar Evacuation Asset

The Central Electricity Regulatory Commission issued an order determining annual fixed charges for Power Grid Corporation of India Limited for a transmission asset to evacuate renewable power from Solar Energy Zones in Rajasthan. The order covers Phase?II Part?A1, intended to support the evacuation of eight point one GW of solar generation. The principal work was augmentation of the Fatehgarh?II Pooling Station with a 1,500 MVA, 765/400 kV transformer and associated bays; the asset achieved commercial operation on first August 2024 and the tariff has been fixed for the 2024–29 period.

Commission records show commissioning was delayed by 790 days beyond the revised scheduled commercial operation date of third June 2022. Power Grid attributed the delay mainly to the second wave of the COVID?19 pandemic with labour shortages, demobilisation, supply chain disruptions and lockdown restrictions, and the Central Transmission Utility of India Limited (CTUIL) had sought deferral over environmental and operational concerns including the habitat of the Great Indian Bustard. After review CERC condoned 758 days, disallowed 32 days and ordered pro?rata reductions in interest during construction and incidental expenditure during construction for the disallowed period.

The project was initially estimated to cost Rs 688.8 million (mn) and the revised completion cost rose to Rs 1.0644 billion (bn), but CERC found the final expenditure remained within the approved revised cost estimate with no unapproved overrun. The increase was attributed mainly to higher market prices for substation equipment, elevated interest costs from the extended construction period and additional incidental expenses. For tariff purposes the Commission approved a capital cost of Rs 885.7 million (mn) on the commercial operation date after deductions for disallowed interest, undischarged liabilities and unapproved incidental expenditure.

CERC also approved additional capital expenditure of Rs 174.2 million (mn) during 2024–29 for balance and retention payments and deferred works within the original project scope. The tariff was computed on a prescribed 70:30 debt?to?equity ratio and the Commission reviewed working capital and initial spares in accordance with regulatory limits. Power Grid is permitted to recover the approved annual fixed charges from concerned regional distribution licensees and other beneficiaries using the transmission system to facilitate evacuation of the linked renewable projects.

The Central Electricity Regulatory Commission issued an order determining annual fixed charges for Power Grid Corporation of India Limited for a transmission asset to evacuate renewable power from Solar Energy Zones in Rajasthan. The order covers Phase?II Part?A1, intended to support the evacuation of eight point one GW of solar generation. The principal work was augmentation of the Fatehgarh?II Pooling Station with a 1,500 MVA, 765/400 kV transformer and associated bays; the asset achieved commercial operation on first August 2024 and the tariff has been fixed for the 2024–29 period. Commission records show commissioning was delayed by 790 days beyond the revised scheduled commercial operation date of third June 2022. Power Grid attributed the delay mainly to the second wave of the COVID?19 pandemic with labour shortages, demobilisation, supply chain disruptions and lockdown restrictions, and the Central Transmission Utility of India Limited (CTUIL) had sought deferral over environmental and operational concerns including the habitat of the Great Indian Bustard. After review CERC condoned 758 days, disallowed 32 days and ordered pro?rata reductions in interest during construction and incidental expenditure during construction for the disallowed period. The project was initially estimated to cost Rs 688.8 million (mn) and the revised completion cost rose to Rs 1.0644 billion (bn), but CERC found the final expenditure remained within the approved revised cost estimate with no unapproved overrun. The increase was attributed mainly to higher market prices for substation equipment, elevated interest costs from the extended construction period and additional incidental expenses. For tariff purposes the Commission approved a capital cost of Rs 885.7 million (mn) on the commercial operation date after deductions for disallowed interest, undischarged liabilities and unapproved incidental expenditure. CERC also approved additional capital expenditure of Rs 174.2 million (mn) during 2024–29 for balance and retention payments and deferred works within the original project scope. The tariff was computed on a prescribed 70:30 debt?to?equity ratio and the Commission reviewed working capital and initial spares in accordance with regulatory limits. Power Grid is permitted to recover the approved annual fixed charges from concerned regional distribution licensees and other beneficiaries using the transmission system to facilitate evacuation of the linked renewable projects.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Suzuki Targets 4 mn Units in India by FY30, Builds Global Hub

Suzuki Motor Corporation plans to raise annual production capacity in India to approximately 4 mn units from fiscal 2030, strengthening the country’s role as a manufacturing and export hub for its global operations. The Japanese car maker announced the target as part of its Technology Strategy 2026, which outlines its development and manufacturing priorities for the coming decade. The company also aims to improve development efficiency by 30 per cent from the FY20 level and manufacturing efficiency by 50 per cent by FY30. It plans to halve the lead time required to develop new vehicles by im..

Next Story
Infrastructure Transport

Ayodhya Airport to Add Flights to Delhi, Bengaluru and Mumbai

Ayodhya airport will get additional direct air services to Delhi and Bengaluru from October 1, followed by a daily non-stop connection to Mumbai from October 30. The existing IndiGo service to Hyderabad is also being prepared for conversion into a daily operation, widening travel options from the temple city. Passengers travelling to Delhi will have two direct options at different times of day from October 1. Akasa Air flight QP 1608 will depart Ayodhya at 12:50 pm and arrive in Delhi at 2:20 pm, while Air India Express flight IX 1274 will leave at 2:10 pm and reach the capital at 3:45 pm. Ind..

Next Story
Infrastructure Urban

Cement Prices Rise Again in Himachal Pradesh

Cement prices in Himachal Pradesh have increased for the second time this month, raising construction expenses for households, contractors and other consumers. Cement companies raised rates by Rs. 5 per bag on Friday, 10 days after a similar increase was implemented on September 15. The two revisions have lifted prices by a total of Rs. 10 per bag within 10 days. Dealers Pawan, Rohit, Manoj and Rakesh said the latest rates were being applied across the market, adding to the financial pressure on people building or renovating homes. ACC Suraksha cement is now priced at Rs. 425 per bag, compared..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code