CERC Approves Tariff For Power Grid Rajasthan Solar Evacuation Asset
POWER & RENEWABLE ENERGY

CERC Approves Tariff For Power Grid Rajasthan Solar Evacuation Asset

The Central Electricity Regulatory Commission issued an order determining annual fixed charges for Power Grid Corporation of India Limited for a transmission asset to evacuate renewable power from Solar Energy Zones in Rajasthan. The order covers Phase?II Part?A1, intended to support the evacuation of eight point one GW of solar generation. The principal work was augmentation of the Fatehgarh?II Pooling Station with a 1,500 MVA, 765/400 kV transformer and associated bays; the asset achieved commercial operation on first August 2024 and the tariff has been fixed for the 2024–29 period.

Commission records show commissioning was delayed by 790 days beyond the revised scheduled commercial operation date of third June 2022. Power Grid attributed the delay mainly to the second wave of the COVID?19 pandemic with labour shortages, demobilisation, supply chain disruptions and lockdown restrictions, and the Central Transmission Utility of India Limited (CTUIL) had sought deferral over environmental and operational concerns including the habitat of the Great Indian Bustard. After review CERC condoned 758 days, disallowed 32 days and ordered pro?rata reductions in interest during construction and incidental expenditure during construction for the disallowed period.

The project was initially estimated to cost Rs 688.8 million (mn) and the revised completion cost rose to Rs 1.0644 billion (bn), but CERC found the final expenditure remained within the approved revised cost estimate with no unapproved overrun. The increase was attributed mainly to higher market prices for substation equipment, elevated interest costs from the extended construction period and additional incidental expenses. For tariff purposes the Commission approved a capital cost of Rs 885.7 million (mn) on the commercial operation date after deductions for disallowed interest, undischarged liabilities and unapproved incidental expenditure.

CERC also approved additional capital expenditure of Rs 174.2 million (mn) during 2024–29 for balance and retention payments and deferred works within the original project scope. The tariff was computed on a prescribed 70:30 debt?to?equity ratio and the Commission reviewed working capital and initial spares in accordance with regulatory limits. Power Grid is permitted to recover the approved annual fixed charges from concerned regional distribution licensees and other beneficiaries using the transmission system to facilitate evacuation of the linked renewable projects.

The Central Electricity Regulatory Commission issued an order determining annual fixed charges for Power Grid Corporation of India Limited for a transmission asset to evacuate renewable power from Solar Energy Zones in Rajasthan. The order covers Phase?II Part?A1, intended to support the evacuation of eight point one GW of solar generation. The principal work was augmentation of the Fatehgarh?II Pooling Station with a 1,500 MVA, 765/400 kV transformer and associated bays; the asset achieved commercial operation on first August 2024 and the tariff has been fixed for the 2024–29 period. Commission records show commissioning was delayed by 790 days beyond the revised scheduled commercial operation date of third June 2022. Power Grid attributed the delay mainly to the second wave of the COVID?19 pandemic with labour shortages, demobilisation, supply chain disruptions and lockdown restrictions, and the Central Transmission Utility of India Limited (CTUIL) had sought deferral over environmental and operational concerns including the habitat of the Great Indian Bustard. After review CERC condoned 758 days, disallowed 32 days and ordered pro?rata reductions in interest during construction and incidental expenditure during construction for the disallowed period. The project was initially estimated to cost Rs 688.8 million (mn) and the revised completion cost rose to Rs 1.0644 billion (bn), but CERC found the final expenditure remained within the approved revised cost estimate with no unapproved overrun. The increase was attributed mainly to higher market prices for substation equipment, elevated interest costs from the extended construction period and additional incidental expenses. For tariff purposes the Commission approved a capital cost of Rs 885.7 million (mn) on the commercial operation date after deductions for disallowed interest, undischarged liabilities and unapproved incidental expenditure. CERC also approved additional capital expenditure of Rs 174.2 million (mn) during 2024–29 for balance and retention payments and deferred works within the original project scope. The tariff was computed on a prescribed 70:30 debt?to?equity ratio and the Commission reviewed working capital and initial spares in accordance with regulatory limits. Power Grid is permitted to recover the approved annual fixed charges from concerned regional distribution licensees and other beneficiaries using the transmission system to facilitate evacuation of the linked renewable projects.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

GEON Commissions 10 MW/20 MWh BESS in Jaisalmer

GEON, the future technologies division of Kabra Extrusiontechnik, has commissioned a 10 MW/20 MWh battery energy storage system (BESS) in Jaisalmer, Rajasthan, on an engineering, procurement and construction (EPC) basis.Executed in accordance with the Rajasthan Integrated Clean Energy Policy, 2024, the project covered detailed engineering and design, equipment procurement and supply, installation, testing and commissioning.The system has a power capacity of 10 MW and an energy storage capacity of 20 MWh. It is designed to improve energy management, support grid stability and facilitate the int..

Next Story
Infrastructure Urban

Tembo Lists on BSE, Expands Defence Manufacturing Plans

Tembo Global Industries has listed its equity shares on the Main Board of BSE while expanding its focus on defence manufacturing and unmanned aerial vehicle (UAV) technologies alongside its existing engineering and industrial businesses.Through its subsidiary, Tembo Classic Engineering, the company is developing manufacturing capabilities in small arms and ammunition. Its defence facility in Amravati, Maharashtra, is under development, with commercial production targeted for Q1 FY2028. The subsidiary has obtained government licences for ammunition and small-arms manufacturing.The company is co..

Next Story
Infrastructure Urban

Bondada Gets NSE In-Principle Nod for Main Board Migration

Bondada Engineering has received in-principle approval from the National Stock Exchange of India (NSE) to migrate its equity shares from the BSE SME Platform to NSE’s Capital Market Segment, or Main Board.The approval, conveyed through a letter dated 14 October 2026, follows BSE’s in-principle approval on 9 September 2026 for migration to its Main Board. The company now holds preliminary approvals to establish a presence on the Main Boards of both exchanges.Bondada Engineering will complete the subsequent formalities required under applicable regulatory and stock exchange requirements. The..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code