GERC Defers Rs2.34 per kWh Tariff For 1,250 MW Solar Procurement
POWER & RENEWABLE ENERGY

GERC Defers Rs2.34 per kWh Tariff For 1,250 MW Solar Procurement

The Gujarat Electricity Regulatory Commission (GERC) has deferred approval of a tariff of Rs2.34 per kWh for 1,250 MW of solar capacity procured by Gujarat Urja Vikas Nigam Limited (GUVNL). The commission cited concerns about renewable energy curtailment, grid stability and the cost implications of integrating additional solar without adequate storage. The order was issued on five September 2026 after a hearing on two September 2026 before a bench comprising the chairman and members.

The procurement covered 625 MW of base capacity and 625 MW under a greenshoe option following a Phase XXVIII competitive bidding process. The tender attracted 24 bids totalling 4,176.7 MW and an e-reverse auction in March 2026 produced the discovered tariff for three successful developers. NLC India Renewables Limited was allocated 900 MW (300 MW base and 600 MW under the greenshoe) with a capacity utilisation factor of 26 per cent; Welspun Renewable Energy Private Limited was allocated 300 MW with a capacity utilisation factor of 28.9 per cent and declined the greenshoe; Meghmani Renew Energy Private Limited was allotted 50 MW with a capacity utilisation factor of 24.5 per cent.

GUVNL argued the discovered tariff is lower than rates found in earlier procurement rounds and said the procurement would help Gujarat meet renewable purchase obligations through FY 2029–30 while contributing to India’s goal of 50 per cent non-fossil installed capacity by 2030. The utility asked the commission to weigh the longer term benefits of lower tariffs for consumers and the role of the procurement in state planning.

GERC issued a 13-point query seeking detailed information on curtailment, grid management, energy storage requirements, resource adequacy and the actual cost of solar after accounting for storage, balancing and backing down. The commission requested daily renewable curtailment data from one September 2025 to 31 August 2026 and asked for a time bound plan to address curtailment and measures to ensure grid stability. It also directed GUVNL to demonstrate consistency with updated resource adequacy plans and to quantify overall integration costs.

GUVNL sought three weeks to submit technical studies, curtailment data and supporting documents and the commission allowed the extension, setting a deadline of 23 September 2026 for additional filings. The matter will return to a subsequent hearing after the submission for the commission to decide whether to adopt the tariff and any conditions required to safeguard grid operations.

The Gujarat Electricity Regulatory Commission (GERC) has deferred approval of a tariff of Rs2.34 per kWh for 1,250 MW of solar capacity procured by Gujarat Urja Vikas Nigam Limited (GUVNL). The commission cited concerns about renewable energy curtailment, grid stability and the cost implications of integrating additional solar without adequate storage. The order was issued on five September 2026 after a hearing on two September 2026 before a bench comprising the chairman and members. The procurement covered 625 MW of base capacity and 625 MW under a greenshoe option following a Phase XXVIII competitive bidding process. The tender attracted 24 bids totalling 4,176.7 MW and an e-reverse auction in March 2026 produced the discovered tariff for three successful developers. NLC India Renewables Limited was allocated 900 MW (300 MW base and 600 MW under the greenshoe) with a capacity utilisation factor of 26 per cent; Welspun Renewable Energy Private Limited was allocated 300 MW with a capacity utilisation factor of 28.9 per cent and declined the greenshoe; Meghmani Renew Energy Private Limited was allotted 50 MW with a capacity utilisation factor of 24.5 per cent. GUVNL argued the discovered tariff is lower than rates found in earlier procurement rounds and said the procurement would help Gujarat meet renewable purchase obligations through FY 2029–30 while contributing to India’s goal of 50 per cent non-fossil installed capacity by 2030. The utility asked the commission to weigh the longer term benefits of lower tariffs for consumers and the role of the procurement in state planning. GERC issued a 13-point query seeking detailed information on curtailment, grid management, energy storage requirements, resource adequacy and the actual cost of solar after accounting for storage, balancing and backing down. The commission requested daily renewable curtailment data from one September 2025 to 31 August 2026 and asked for a time bound plan to address curtailment and measures to ensure grid stability. It also directed GUVNL to demonstrate consistency with updated resource adequacy plans and to quantify overall integration costs. GUVNL sought three weeks to submit technical studies, curtailment data and supporting documents and the commission allowed the extension, setting a deadline of 23 September 2026 for additional filings. The matter will return to a subsequent hearing after the submission for the commission to decide whether to adopt the tariff and any conditions required to safeguard grid operations.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Welspun One unveils Diwali campaign for World Trade Center Thane

Welspun One has unveiled A Dream Diwali, a festive brand film promoting World Trade Center Thane, its proposed mixed-use development in the Mumbai Metropolitan Region (MMR). The campaign uses individual interpretations of an ideal Diwali to introduce the experiences and offerings planned at the development.The film follows different characters as they share their festive wishes and go about activities such as shopping, meeting friends, playing games and spending time with family. Through these everyday moments, the campaign presents the idea that celebrations are personal and that different ge..

Next Story
Equipment

BorgWarner secures three turbocharger contracts with global powertrain leader

BorgWarner has secured three new turbocharger contracts with a global powertrain technology company. The wins comprise one contract for its variable turbine geometry (VTG) turbocharger and two for its wastegate turbocharger. The technologies will be deployed in the customer's light-vehicle gasoline platforms in South America and Europe, with production scheduled to begin in 2027.The VTG turbochargers are designed for gasoline engines operating under demanding conditions and high-boost pressure requirements. They are engineered to support Miller-cycle engines and withstand exhaust temperatures ..

Next Story
Infrastructure Transport

International Digi Yatra Trials Begin at Seven Airports

India has begun trials of Digi Yatra for international passengers at seven airports, allowing eligible Indian passport holders to use facial recognition at selected airport checkpoints. The facility is currently limited to Indian nationals with e-passports travelling on selected international flights operated by Air India and IndiGo. The Civil Aviation Ministry announced the trials on 1 November, with testing scheduled through December 2026. A wider rollout is expected in 2027 after the ministry assesses passenger feedback gathered during the trial period, according to PTI. The system is inten..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code