GERC Defers Rs2.34 per kWh Tariff For 1,250 MW Solar Procurement
POWER & RENEWABLE ENERGY

GERC Defers Rs2.34 per kWh Tariff For 1,250 MW Solar Procurement

The Gujarat Electricity Regulatory Commission (GERC) has deferred approval of a tariff of Rs2.34 per kWh for 1,250 MW of solar capacity procured by Gujarat Urja Vikas Nigam Limited (GUVNL). The commission cited concerns about renewable energy curtailment, grid stability and the cost implications of integrating additional solar without adequate storage. The order was issued on five September 2026 after a hearing on two September 2026 before a bench comprising the chairman and members.

The procurement covered 625 MW of base capacity and 625 MW under a greenshoe option following a Phase XXVIII competitive bidding process. The tender attracted 24 bids totalling 4,176.7 MW and an e-reverse auction in March 2026 produced the discovered tariff for three successful developers. NLC India Renewables Limited was allocated 900 MW (300 MW base and 600 MW under the greenshoe) with a capacity utilisation factor of 26 per cent; Welspun Renewable Energy Private Limited was allocated 300 MW with a capacity utilisation factor of 28.9 per cent and declined the greenshoe; Meghmani Renew Energy Private Limited was allotted 50 MW with a capacity utilisation factor of 24.5 per cent.

GUVNL argued the discovered tariff is lower than rates found in earlier procurement rounds and said the procurement would help Gujarat meet renewable purchase obligations through FY 2029–30 while contributing to India’s goal of 50 per cent non-fossil installed capacity by 2030. The utility asked the commission to weigh the longer term benefits of lower tariffs for consumers and the role of the procurement in state planning.

GERC issued a 13-point query seeking detailed information on curtailment, grid management, energy storage requirements, resource adequacy and the actual cost of solar after accounting for storage, balancing and backing down. The commission requested daily renewable curtailment data from one September 2025 to 31 August 2026 and asked for a time bound plan to address curtailment and measures to ensure grid stability. It also directed GUVNL to demonstrate consistency with updated resource adequacy plans and to quantify overall integration costs.

GUVNL sought three weeks to submit technical studies, curtailment data and supporting documents and the commission allowed the extension, setting a deadline of 23 September 2026 for additional filings. The matter will return to a subsequent hearing after the submission for the commission to decide whether to adopt the tariff and any conditions required to safeguard grid operations.

The Gujarat Electricity Regulatory Commission (GERC) has deferred approval of a tariff of Rs2.34 per kWh for 1,250 MW of solar capacity procured by Gujarat Urja Vikas Nigam Limited (GUVNL). The commission cited concerns about renewable energy curtailment, grid stability and the cost implications of integrating additional solar without adequate storage. The order was issued on five September 2026 after a hearing on two September 2026 before a bench comprising the chairman and members. The procurement covered 625 MW of base capacity and 625 MW under a greenshoe option following a Phase XXVIII competitive bidding process. The tender attracted 24 bids totalling 4,176.7 MW and an e-reverse auction in March 2026 produced the discovered tariff for three successful developers. NLC India Renewables Limited was allocated 900 MW (300 MW base and 600 MW under the greenshoe) with a capacity utilisation factor of 26 per cent; Welspun Renewable Energy Private Limited was allocated 300 MW with a capacity utilisation factor of 28.9 per cent and declined the greenshoe; Meghmani Renew Energy Private Limited was allotted 50 MW with a capacity utilisation factor of 24.5 per cent. GUVNL argued the discovered tariff is lower than rates found in earlier procurement rounds and said the procurement would help Gujarat meet renewable purchase obligations through FY 2029–30 while contributing to India’s goal of 50 per cent non-fossil installed capacity by 2030. The utility asked the commission to weigh the longer term benefits of lower tariffs for consumers and the role of the procurement in state planning. GERC issued a 13-point query seeking detailed information on curtailment, grid management, energy storage requirements, resource adequacy and the actual cost of solar after accounting for storage, balancing and backing down. The commission requested daily renewable curtailment data from one September 2025 to 31 August 2026 and asked for a time bound plan to address curtailment and measures to ensure grid stability. It also directed GUVNL to demonstrate consistency with updated resource adequacy plans and to quantify overall integration costs. GUVNL sought three weeks to submit technical studies, curtailment data and supporting documents and the commission allowed the extension, setting a deadline of 23 September 2026 for additional filings. The matter will return to a subsequent hearing after the submission for the commission to decide whether to adopt the tariff and any conditions required to safeguard grid operations.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

GEON Commissions 10 MW/20 MWh BESS in Jaisalmer

GEON, the future technologies division of Kabra Extrusiontechnik, has commissioned a 10 MW/20 MWh battery energy storage system (BESS) in Jaisalmer, Rajasthan, on an engineering, procurement and construction (EPC) basis.Executed in accordance with the Rajasthan Integrated Clean Energy Policy, 2024, the project covered detailed engineering and design, equipment procurement and supply, installation, testing and commissioning.The system has a power capacity of 10 MW and an energy storage capacity of 20 MWh. It is designed to improve energy management, support grid stability and facilitate the int..

Next Story
Infrastructure Urban

Tembo Lists on BSE, Expands Defence Manufacturing Plans

Tembo Global Industries has listed its equity shares on the Main Board of BSE while expanding its focus on defence manufacturing and unmanned aerial vehicle (UAV) technologies alongside its existing engineering and industrial businesses.Through its subsidiary, Tembo Classic Engineering, the company is developing manufacturing capabilities in small arms and ammunition. Its defence facility in Amravati, Maharashtra, is under development, with commercial production targeted for Q1 FY2028. The subsidiary has obtained government licences for ammunition and small-arms manufacturing.The company is co..

Next Story
Infrastructure Urban

Bondada Gets NSE In-Principle Nod for Main Board Migration

Bondada Engineering has received in-principle approval from the National Stock Exchange of India (NSE) to migrate its equity shares from the BSE SME Platform to NSE’s Capital Market Segment, or Main Board.The approval, conveyed through a letter dated 14 October 2026, follows BSE’s in-principle approval on 9 September 2026 for migration to its Main Board. The company now holds preliminary approvals to establish a presence on the Main Boards of both exchanges.Bondada Engineering will complete the subsequent formalities required under applicable regulatory and stock exchange requirements. The..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code