Power Supply Begins on 50-km Bullet Train Stretch
POWER & RENEWABLE ENERGY

Power Supply Begins on 50-km Bullet Train Stretch

The overhead equipment system for power supply on the Surat-Bilimora section of the 508-km-long Mumbai-Ahmedabad Bullet Train corridor has been successfully energised, the Ministry of Railways said on Saturday. The milestone covers approximately 50 km of elevated alignment between Surat and Bilimora stations.

Energisation will be carried out progressively in smaller sections under the supervision of technical teams, with safety procedures and compliance requirements being monitored. The ministry issued a public safety advisory urging residents, commuters, construction workers and other people near the alignment not to approach or touch overhead electrical installations or conduct unauthorised work in the area.

Officials clarified that the start of energisation does not mean the section is ready for train operations. However, they described it as a significant step towards testing and eventual operation of the high-speed rail corridor. The section includes both Up and Down lines on the elevated alignment.

The ministry recently extended the deadline for beginning Bullet Train operations on the 100-km Surat-Vapi section from August 2027 to the last quarter of 2027. The Surat-Bilimora stretch is expected to support further testing activities as construction and systems work progress along the corridor.

The corridor uses a 2 x 25 kV overhead traction system, an electrification technology used in high-speed rail networks. Its electrical network will be supplied through 14 traction substations connected to the national grid and monitored by a centralised control centre.

The Surat-Bilimora alignment includes bridges over four rivers and a steel bridge over National Highway 53. The viaduct is also fitted with approximately 94,000 noise barriers intended to reduce the impact of train operations on surrounding areas. The Mumbai-Ahmedabad corridor is being developed across a total length of 508 km.

The overhead equipment system for power supply on the Surat-Bilimora section of the 508-km-long Mumbai-Ahmedabad Bullet Train corridor has been successfully energised, the Ministry of Railways said on Saturday. The milestone covers approximately 50 km of elevated alignment between Surat and Bilimora stations. Energisation will be carried out progressively in smaller sections under the supervision of technical teams, with safety procedures and compliance requirements being monitored. The ministry issued a public safety advisory urging residents, commuters, construction workers and other people near the alignment not to approach or touch overhead electrical installations or conduct unauthorised work in the area. Officials clarified that the start of energisation does not mean the section is ready for train operations. However, they described it as a significant step towards testing and eventual operation of the high-speed rail corridor. The section includes both Up and Down lines on the elevated alignment. The ministry recently extended the deadline for beginning Bullet Train operations on the 100-km Surat-Vapi section from August 2027 to the last quarter of 2027. The Surat-Bilimora stretch is expected to support further testing activities as construction and systems work progress along the corridor. The corridor uses a 2 x 25 kV overhead traction system, an electrification technology used in high-speed rail networks. Its electrical network will be supplied through 14 traction substations connected to the national grid and monitored by a centralised control centre. The Surat-Bilimora alignment includes bridges over four rivers and a steel bridge over National Highway 53. The viaduct is also fitted with approximately 94,000 noise barriers intended to reduce the impact of train operations on surrounding areas. The Mumbai-Ahmedabad corridor is being developed across a total length of 508 km.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

DMRC Invites Bids for Solar-Linked BESS Power Procurement

Delhi Metro Rail Corporation (DMRC) has invited bids for renewable energy from an Inter-State Transmission System (ISTS)-connected generating plant combining a solar photovoltaic (PV) system with a co-located Battery Energy Storage System (BESS). The procurement will be conducted through competitive bidding followed by an e-reverse auction. The last date for submitting online bids is December 10, 2026, at 3 PM. DMRC will open the technical bids on December 11, 2026, at 3 PM. The opening of financial bids and the e-reverse auction will be scheduled after completion of the technical evaluation. ..

Next Story
Infrastructure Energy

Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30. Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of s..

Next Story
Infrastructure Transport

India’s First High-Speed Rail Service to Begin in 2027

India’s first high-speed rail service will commence in 2027, with the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail corridor scheduled to open first, Railway Minister Ashwini Vaishnaw said. The remaining sections to Mumbai will be opened in phases. Vaishnaw said 456 km of pier work and 371 km of viaduct construction had been completed by September. About 600,000 noise barriers had been installed along a 299 km stretch, while 9,300 overhead equipment masts had been erected across a 206 km viaduct. Four mountain tunnels have been excavated, and 5 km of the 21 km Maharashtra tunnel..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code