Around 423 infra projects hit cost overruns of Rs 4.95 lakh cr
ECONOMY & POLICY

Around 423 infra projects hit cost overruns of Rs 4.95 lakh cr

As per a report, around 423 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of over Rs 4.95 lakh crore.

As per the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,568 projects, 423 registered cost overruns, and around 721 projects were delayed.

The ministry's latest report for May 2022 said the total original cost of execution of the 1,568 projects was Rs 21,59,802.67 crore and their expected completion cost is Rs 26,54,818.05 crore, which shows overall cost overruns of Rs 4,95,015.38 crore.

As per the report, the expense incurred on these projects till May 2022 is Rs 13,42,535.22 crore, which is 50.57% of the expected cost of the projects.

However, the number of delayed projects drops to 563 if the delay is calculated based on the latest plan of completion.

Further, it revealed that for 569 projects, neither the year of commissioning nor the tentative gestation time has been registered.

Out of the 721 delayed projects, 113 projects have overall delays in the 1-12 months range, 121 projects have been delayed for 13-24 months, 350 projects for 25-60 months, and 137 projects have been delayed for 61 months and more.

In these 721 delayed projects, the average time overrun is 43.34 months.

Causes for time overruns as reported by various project executing agencies include delay in obtaining forest and environment clearances, land acquisition, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in tendering, change in scope, delay in finalisation of detailed engineering, ordering and equipment supply, and law and order issues are among the other reasons.

The report also noted state-wise lockdowns due to Covid-19 as a reason for the delay in these projects' implementation.

Image Source

Also read: As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

As per a report, around 423 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of over Rs 4.95 lakh crore. As per the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,568 projects, 423 registered cost overruns, and around 721 projects were delayed. The ministry's latest report for May 2022 said the total original cost of execution of the 1,568 projects was Rs 21,59,802.67 crore and their expected completion cost is Rs 26,54,818.05 crore, which shows overall cost overruns of Rs 4,95,015.38 crore. As per the report, the expense incurred on these projects till May 2022 is Rs 13,42,535.22 crore, which is 50.57% of the expected cost of the projects. However, the number of delayed projects drops to 563 if the delay is calculated based on the latest plan of completion. Further, it revealed that for 569 projects, neither the year of commissioning nor the tentative gestation time has been registered. Out of the 721 delayed projects, 113 projects have overall delays in the 1-12 months range, 121 projects have been delayed for 13-24 months, 350 projects for 25-60 months, and 137 projects have been delayed for 61 months and more. In these 721 delayed projects, the average time overrun is 43.34 months. Causes for time overruns as reported by various project executing agencies include delay in obtaining forest and environment clearances, land acquisition, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in tendering, change in scope, delay in finalisation of detailed engineering, ordering and equipment supply, and law and order issues are among the other reasons. The report also noted state-wise lockdowns due to Covid-19 as a reason for the delay in these projects' implementation. Image Source Also read: As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

Next Story
Infrastructure Urban

Implementation Status of Jal Jeevan Mission

Since August 2019 the Government has implemented Jal Jeevan Mission to provide assured potable water through household tap connections in rural India. At the start of the mission only 32.3 million (mn) rural households, representing 16.7 per cent, were reported to have tap water connections. States and union territories have reported that 125.8 mn additional rural households have since been provided with tap connections. As a result, of about 193.6 mn rural households roughly 158.2 mn, or 81.71 per cent, are reported to have tap water supply at home.\n\nThe State, district and village level st..

Next Story
Infrastructure Urban

Jal Jeevan Mission Reaches Eighty One Per Cent Rural Coverage

The Government reported substantial progress under the Jal Jeevan Mission, launched in August 2019 to provide tap water to every rural household. At launch only 32.3 million (mn) rural households had tap connections and states and Union territories reported provision of 125.8 mn additional households by March 2026. Consequently, out of about 193.6 mn rural households around 158.2 mn, or 81.71 per cent, are reported to have tap water at home. The Finance Minister announced extension of the mission until 2028 in the 2025-26 budget speech. The Swachh Bharat Mission Grameen, launched in October 20..

Next Story
Infrastructure Urban

Empowering Local Governance for Sustainable Rural Water Supply

The Ministry of Jal Shakti has aligned the Jal Jeevan Mission (JJM) with the 73rd Amendment to strengthen village level planning and community ownership of water supply. Gram Panchayats, village water and sanitation committees and Pani Samitis are to plan, implement, manage and maintain piped water systems, with gram sabha processes formalising handover and oversight. Implementation support agencies including non government organisations, community based organisations and self help groups have been empanelled to train local committees and promote women participation. Under JJM, the department ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement