+
Around 423 infra projects hit cost overruns of Rs 4.95 lakh cr
ECONOMY & POLICY

Around 423 infra projects hit cost overruns of Rs 4.95 lakh cr

As per a report, around 423 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of over Rs 4.95 lakh crore.

As per the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,568 projects, 423 registered cost overruns, and around 721 projects were delayed.

The ministry's latest report for May 2022 said the total original cost of execution of the 1,568 projects was Rs 21,59,802.67 crore and their expected completion cost is Rs 26,54,818.05 crore, which shows overall cost overruns of Rs 4,95,015.38 crore.

As per the report, the expense incurred on these projects till May 2022 is Rs 13,42,535.22 crore, which is 50.57% of the expected cost of the projects.

However, the number of delayed projects drops to 563 if the delay is calculated based on the latest plan of completion.

Further, it revealed that for 569 projects, neither the year of commissioning nor the tentative gestation time has been registered.

Out of the 721 delayed projects, 113 projects have overall delays in the 1-12 months range, 121 projects have been delayed for 13-24 months, 350 projects for 25-60 months, and 137 projects have been delayed for 61 months and more.

In these 721 delayed projects, the average time overrun is 43.34 months.

Causes for time overruns as reported by various project executing agencies include delay in obtaining forest and environment clearances, land acquisition, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in tendering, change in scope, delay in finalisation of detailed engineering, ordering and equipment supply, and law and order issues are among the other reasons.

The report also noted state-wise lockdowns due to Covid-19 as a reason for the delay in these projects' implementation.

Image Source

Also read: As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

As per a report, around 423 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of over Rs 4.95 lakh crore. As per the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,568 projects, 423 registered cost overruns, and around 721 projects were delayed. The ministry's latest report for May 2022 said the total original cost of execution of the 1,568 projects was Rs 21,59,802.67 crore and their expected completion cost is Rs 26,54,818.05 crore, which shows overall cost overruns of Rs 4,95,015.38 crore. As per the report, the expense incurred on these projects till May 2022 is Rs 13,42,535.22 crore, which is 50.57% of the expected cost of the projects. However, the number of delayed projects drops to 563 if the delay is calculated based on the latest plan of completion. Further, it revealed that for 569 projects, neither the year of commissioning nor the tentative gestation time has been registered. Out of the 721 delayed projects, 113 projects have overall delays in the 1-12 months range, 121 projects have been delayed for 13-24 months, 350 projects for 25-60 months, and 137 projects have been delayed for 61 months and more. In these 721 delayed projects, the average time overrun is 43.34 months. Causes for time overruns as reported by various project executing agencies include delay in obtaining forest and environment clearances, land acquisition, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in tendering, change in scope, delay in finalisation of detailed engineering, ordering and equipment supply, and law and order issues are among the other reasons. The report also noted state-wise lockdowns due to Covid-19 as a reason for the delay in these projects' implementation. Image Source Also read: As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code