October sees Rs 4.31 trillion overruns in 411 infra projects
ECONOMY & POLICY

October sees Rs 4.31 trillion overruns in 411 infra projects

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays.

The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion.

Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays. The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion. Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

Next Story
Building Material

UltraTech’s Limestone Mine Gets India’s First-Ever 7-Star Rating

UltraTech Cement, India’s largest producer of cement and Ready-Mix Concrete (RMC), has received top honours for sustainable mining practices. Thirteen of the company’s limestone mines were awarded star ratings by the Indian Bureau of Mines (IBM), Ministry of Mines, for FY 2023–24 during a ceremony held in Jaipur, Rajasthan. Among these, the Naokari Limestone Mine—part of UltraTech’s Awarpur Cement Works in Chandrapur, Maharashtra—was awarded India’s first-ever 7-star rating for a limestone mine, in recognition of exceptional performance in ‘Green Mining’. The remain..

Next Story
Infrastructure Urban

Sieger Parking Enters Mumbai Market, Expands West India Presence

Sieger Parking, a Coimbatore-headquartered specialist in automated and multi-level car parking systems, has announced its entry into Western India with the launch of a regional office in Mumbai. This move marks a key milestone in the company’s pan-India growth strategy and its commitment to delivering technology-driven, space-efficient parking solutions across urban India. The Mumbai office will serve as the regional headquarters for Maharashtra and neighbouring states, supporting end-to-end operations with on-ground sales, project management, and service teams. The aim is to fast-track..

Next Story
Resources

IGBC Green Kochi Conclave 2025 Champions Culture and Climate Action

The Indian Green Building Council (IGBC), part of CII, hosted the Green Kochi Conclave 2025 on 4 July at Hotel Holiday Inn, Kochi, under the theme “Tharavadu to Tomorrow: Weaving Kerala’s Heritage into a Sustainable Built Environment.” The event brought together policymakers, architects, developers, and thought leaders to discuss Kerala’s progress in blending cultural heritage with sustainable design.  Kerala is emerging as a frontrunner in climate-resilient development, thanks to passive design strategies, rainwater harvesting, cool roof initiatives, and the widespread adopt..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?