October sees Rs 4.31 trillion overruns in 411 infra projects
ECONOMY & POLICY

October sees Rs 4.31 trillion overruns in 411 infra projects

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays.

The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion.

Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays. The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion. Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

Next Story
Infrastructure Transport

Uttar Pradesh unveils infrastructure-led growth roadmap at RAHSTA

Mumbai, 9 July 2026: Uttar Pradesh’s ambitious infrastructure-led growth strategy took centre stage on Day 2 of the 16th RAHSTA Expo, where senior government officials outlined how expressways, industrial corridors and technology-driven governance are transforming the state into one of India's most attractive investment destinations.Delivering the keynote address, Srihari Pratap Shahi, IAS, Additional Chief Executive Officer, Uttar Pradesh Expressways Industrial Development Authority (UPEIDA), highlighted the state's long-term vision of integrating world-class expressways with industrial dev..

Next Story
Real Estate

NCW closes PRIME Offices Fund at Rs 40 billion

Nuvama and Cushman & Wakefield Management (NCW) has announced the final close of its flagship PRIME Offices Fund at approximately Rs 40 billion, exceeding its original target of Rs 30 billion following strong investor demand.The fund was launched to provide Indian investors with access to institutional-grade commercial office assets across key office markets in the country. According to NCW, the increase in the fund size was supported by strong investor participation and the availability of investment opportunities in India's office sector.The fund has already committed around 45 per cent ..

Next Story
Real Estate

Mayfair Housing adopts Autodesk Forma for digital project planning

Mayfair Housing has entered into a three-year strategic partnership with Autodesk to deploy Autodesk Forma, an AI-enabled cloud platform, as part of its digital transformation programme aimed at improving project planning and execution across its development and redevelopment portfolio.The platform will be integrated into the company's Building Information Modelling (BIM) workflow to support architects, planners and project teams during the early stages of design and development. Autodesk Forma combines real-world data, environmental simulations and collaborative workflows to facilitate data-d..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement