October sees Rs 4.31 trillion overruns in 411 infra projects
ECONOMY & POLICY

October sees Rs 4.31 trillion overruns in 411 infra projects

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays.

The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion.

Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays. The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion. Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

BMW Ventures Secures Rs 249.83 Million (mn) Steel Orders

BMW Ventures Limited said it has secured two purchase orders totalling Rs 249.83 million (mn) from Lata Projects Limited for the supply of TMT steel FE-550D grade for three units of 800 megawatt (MW) capacity at the USCTPP Adani project. The orders were disclosed to the stock exchanges under Regulation 30 of the SEBI Listing Regulations and carry a contract value inclusive of all taxes.\n\nThe company stated that the orders will be executed within eight weeks from the date of the purchase orders and that the contract provides for 100 per cent advance payment with specified guarantees. The supp..

Next Story
Real Estate

Housing Sales Dip in Top Eight Cities in Q2, Pune and Bengaluru Hit Hard

Housing sales across the top eight cities fell six point one per cent year-on-year to 91,729 units in the April-June quarter from 97,674 a year earlier, PropTiger’s Real Insight Residential report showed. The moderation reflected seasonal pre-monsoon effects and heightened buyer caution amid the US-Iran conflict. New launches rose six per cent to 89,161 units. The impact was concentrated in technology-driven markets, with Pune and Bengaluru among the hardest hit. Pune recorded the steepest annual decline at 20.8 per cent, with sales falling to 12,642 units, while Ahmedabad declined 20.2 per ..

Next Story
Infrastructure Urban

India And ADB Sign US$230 Million Loan To Modernise Chennai Water

The Government of India and the Asian Development Bank (ADB) signed a US$230 million loan to modernise and expand water supply and sanitation infrastructure in Chennai. Saurabh Singh, Deputy Secretary, Department of Economic Affairs (DEA), signed on behalf of the Government of India and Mio Oka, Country Director of ADB’s India Resident Mission, signed for the lender. The engagement was guided by Baldeo Purushartha, Joint Secretary (ADB and Japan), DEA. The Chennai Climate-Resilient Water Security and Sewerage Project aims to improve access to safe and reliable water and sanitation citywide w..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code