October sees Rs 4.31 trillion overruns in 411 infra projects
ECONOMY & POLICY

October sees Rs 4.31 trillion overruns in 411 infra projects

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays.

The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion.

Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays. The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion. Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

Next Story
Infrastructure Urban

Welspun Enterprises Wins 910 MLD Panjrapur WTP Contract

Welspun Enterprises (WEL), the infrastructure and energy arm of Welspun World, has secured a major contract from the Brihanmumbai Municipal Corporation (BMC) to design, build and operate a 910 million litres per day (MLD) Water Treatment Plant (WTP) at Panjrapur, Maharashtra.Valued at approximately Rs 31.45 billion, the project encompasses end-to-end civil, mechanical, electrical and instrumentation works, including the construction of a treated water sump and pumping station. Of the total value, nearly Rs 11.56 billion is allocated to Operations & Maintenance (O&M), with an additional..

Next Story
Infrastructure Energy

Mitsubishi Power Wins Boiler Upgrade Contract for O Mon 1 Plant

Mitsubishi Power, a power solutions brand of Mitsubishi Heavy Industries, (MHI), has been awarded a contract to support the oil-to-natural-gas fuel conversion at the O Mon 1 Thermal Power Plant in Can Tho, southern Vietnam. As the OEM of the plant’s existing boiler, Mitsubishi Power will supply key equipment—including new gas burners—and implement a selective catalytic reduction (SCR) system to reduce NOx emissions and help the plant meet stricter environmental standards.The O Mon 1 facility includes two 330 MW units that commenced operations in 2009 and 2015, with all major equipment or..

Next Story
Equipment

Liebherr’s 10,000th XPower Wheel Loader Joins BERGER’s Fleet

BERGER Rohstoffe GmbH has welcomed the 10,000th Liebherr XPower wheel loader to its operations at the Schlag granite quarry in Passau. The milestone machine, officially handed over at Liebherr’s Bischofshofen plant in May 2025, underscores the long-standing partnership between BERGER, Liebherr, and the Beutlhauser Group. Equipped with Liebherr’s signature power-split travel drive, the new L 580 XPower is already delivering strong results under demanding quarry conditions.At the Schlag quarry, BERGER Rohstoffe processes approximately 200,000 tonnes of Bayerwald granite annually into high-qu..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement