October sees Rs 4.31 trillion overruns in 411 infra projects
ECONOMY & POLICY

October sees Rs 4.31 trillion overruns in 411 infra projects

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays.

The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion.

Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays. The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion. Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

Next Story
Infrastructure Energy

ONGC Caps Mori-5 Well in Five Days After Blowout

Oil and Natural Gas Corporation Limited (ONGC) has successfully established well control at the Mori-5 well, completing the capping operation within a record five days. The achievement underscores ONGC’s strong blowout response capability and operational discipline in managing critical field incidents.The blowout occurred on 5 January 2026 during service operations at the well being carried out by PEC contractor M/s Deep Industries Limited. ONGC immediately activated its in-house Crisis Management framework and mobilised specialised manpower and equipment to ensure rapid, safe and controlled..

Next Story
Infrastructure Urban

NIIT MTS Acquires SweetRush for Up to $26 Million

NIIT Learning Systems Limited, through its NIIT Managed Training Services (NIIT MTS) arm, has recently acquired 100 per cent of US-based SweetRush, Inc for an aggregate consideration of up to USD 26 million. The transaction was completed via NIIT MTS’ wholly owned subsidiary, NIIT (USA), Inc., and includes performance-linked earnouts over the next five years, subject to customary adjustments.Headquartered in San Francisco, SweetRush was founded in 2001 by Arturo Schwartzberg and Andrei Hedstrom. The company employs over 100 professionals, supported by an extended network of learning experts ..

Next Story
Infrastructure Urban

Lemon Tree–Fleur Restructuring to Create Two Focused Platforms

Lemon Tree Hotels Limited and Fleur Hotels Limited have recently announced that their Boards have approved a Composite Scheme of Arrangement to simplify group structure, sharpen strategic focus and unlock long-term shareholder value, subject to regulatory and shareholder approvals.The reorganisation will result in two distinct yet complementary platforms. Lemon Tree Hotels will operate as a pure-play, asset-light hotel management and brand platform, while Fleur Hotels, a subsidiary of Lemon Tree, will emerge as a large-scale hotel ownership and development platform with a strong growth pipelin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App