Vizhinjam Port Rail Link Tender to Be Issued Shortly
PORTS & SHIPPING

Vizhinjam Port Rail Link Tender to Be Issued Shortly

A key rail project connecting Vizhinjam port to the national railway grid is nearing approval, with tenders expected to be issued within 10 days. This railway link aims to attract cargo from states such as Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana, turning Vizhinjam into a cargo gateway rather than just a transshipment hub.
Vizhinjam International Seaport Ltd (VISL) has formed a review committee to finalise the draft tender submitted by Konkan Railway Corporation Ltd (KRCL). The tender is likely to be published in August, and contracts are expected to be awarded by November. The 10.7 km-long railway line will include a 9.43 km tunnel—India’s third longest.
The Rs 1,482.92 crore project will be executed under the Engineering, Procurement and Construction (EPC) model. The selected contractor will be responsible for design and delivery. Construction is slated for completion by December 2028.
The rail route will run primarily under the Vizhinjam–Balaramapuram road, with about 2.5–3 km of the tunnel passing below private property at a depth of 30–35 metres. To address concerns of residents, authorities plan to release a video walkthrough illustrating that Indian companies have successfully completed 450 km of underground railway tunnels without harming heritage sites or residential structures.
Roughly 5.526 hectares of land is being acquired across four villages: Balaramapuram, Pallichal, Athiyannoor, and Vizhinjam. While road infrastructure to the port is under development, experts warn that additional upgrades are crucial for the port to function at full capacity.

A key rail project connecting Vizhinjam port to the national railway grid is nearing approval, with tenders expected to be issued within 10 days. This railway link aims to attract cargo from states such as Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana, turning Vizhinjam into a cargo gateway rather than just a transshipment hub.Vizhinjam International Seaport Ltd (VISL) has formed a review committee to finalise the draft tender submitted by Konkan Railway Corporation Ltd (KRCL). The tender is likely to be published in August, and contracts are expected to be awarded by November. The 10.7 km-long railway line will include a 9.43 km tunnel—India’s third longest.The Rs 1,482.92 crore project will be executed under the Engineering, Procurement and Construction (EPC) model. The selected contractor will be responsible for design and delivery. Construction is slated for completion by December 2028.The rail route will run primarily under the Vizhinjam–Balaramapuram road, with about 2.5–3 km of the tunnel passing below private property at a depth of 30–35 metres. To address concerns of residents, authorities plan to release a video walkthrough illustrating that Indian companies have successfully completed 450 km of underground railway tunnels without harming heritage sites or residential structures.Roughly 5.526 hectares of land is being acquired across four villages: Balaramapuram, Pallichal, Athiyannoor, and Vizhinjam. While road infrastructure to the port is under development, experts warn that additional upgrades are crucial for the port to function at full capacity.

Next Story
Infrastructure Urban

U-Sphere Appoints Biju Mahima as CEO to Lead Smart and Sustainable Growth

U-Sphere, a subsidiary of ULCCS, has appointed Biju Mahima as Chief Executive Officer. With over 30 years of experience in construction, infrastructure, and engineering across India and the Middle East, Mahima brings deep expertise in large-scale, high-impact projects. He previously held leadership roles at Jindal Steel & Power and LULU Infra Build, where he led the Rs 15 billion Lulu IT Park in Cochin. His international experience includes stints at Emirates Engineering Services, UAE, and Al Zamil Industries, Saudi Arabia. Mahima is an Indian Engineering Services officer and hol..

Next Story
Resources

Tata Power-DDL Enhances Electrical Safety for Kanwar Yatra 2025

Tata Power Delhi Distribution (Tata Power-DDL), serving around 9 million people in North Delhi, is implementing intensive safety measures along the designated Kanwar Yatra routes within its operational area. As lakhs of devotees undertake this annual pilgrimage, the risk of accidental contact with electrical infrastructure increases—particularly during the monsoon. The discom aims for zero incidents during the 2025 Yatra and has mobilised zonal teams to identify all Kanwar camps and carry out strict safety protocols. These include leakage testing of electric poles, transformers, and sub..

Next Story
Real Estate

Knowledge Center Pilots One-Day Design Lab for Architects

A new model of collaborative design is being tested in Gurgaon as the Knowledge Center (KC) soft-launches its One-Day Design Lab, a physical space designed to streamline architecture workflows. Without the fanfare of a grand launch, the Lab is quietly welcoming select studios, developers, and educators to experience its integrated, frictionless setup—compressing weeks of planning into a single day. The Lab offers five interconnected spaces tailored to different design needs. A hands-on Material Library lets architects and clients physically compare finishes, eliminating screen-based gue..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?