Vizhinjam Port Rail Link Tender to Be Issued Shortly
PORTS & SHIPPING

Vizhinjam Port Rail Link Tender to Be Issued Shortly

A key rail project connecting Vizhinjam port to the national railway grid is nearing approval, with tenders expected to be issued within 10 days. This railway link aims to attract cargo from states such as Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana, turning Vizhinjam into a cargo gateway rather than just a transshipment hub.
Vizhinjam International Seaport Ltd (VISL) has formed a review committee to finalise the draft tender submitted by Konkan Railway Corporation Ltd (KRCL). The tender is likely to be published in August, and contracts are expected to be awarded by November. The 10.7 km-long railway line will include a 9.43 km tunnel—India’s third longest.
The Rs 1,482.92 crore project will be executed under the Engineering, Procurement and Construction (EPC) model. The selected contractor will be responsible for design and delivery. Construction is slated for completion by December 2028.
The rail route will run primarily under the Vizhinjam–Balaramapuram road, with about 2.5–3 km of the tunnel passing below private property at a depth of 30–35 metres. To address concerns of residents, authorities plan to release a video walkthrough illustrating that Indian companies have successfully completed 450 km of underground railway tunnels without harming heritage sites or residential structures.
Roughly 5.526 hectares of land is being acquired across four villages: Balaramapuram, Pallichal, Athiyannoor, and Vizhinjam. While road infrastructure to the port is under development, experts warn that additional upgrades are crucial for the port to function at full capacity.

A key rail project connecting Vizhinjam port to the national railway grid is nearing approval, with tenders expected to be issued within 10 days. This railway link aims to attract cargo from states such as Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana, turning Vizhinjam into a cargo gateway rather than just a transshipment hub.Vizhinjam International Seaport Ltd (VISL) has formed a review committee to finalise the draft tender submitted by Konkan Railway Corporation Ltd (KRCL). The tender is likely to be published in August, and contracts are expected to be awarded by November. The 10.7 km-long railway line will include a 9.43 km tunnel—India’s third longest.The Rs 1,482.92 crore project will be executed under the Engineering, Procurement and Construction (EPC) model. The selected contractor will be responsible for design and delivery. Construction is slated for completion by December 2028.The rail route will run primarily under the Vizhinjam–Balaramapuram road, with about 2.5–3 km of the tunnel passing below private property at a depth of 30–35 metres. To address concerns of residents, authorities plan to release a video walkthrough illustrating that Indian companies have successfully completed 450 km of underground railway tunnels without harming heritage sites or residential structures.Roughly 5.526 hectares of land is being acquired across four villages: Balaramapuram, Pallichal, Athiyannoor, and Vizhinjam. While road infrastructure to the port is under development, experts warn that additional upgrades are crucial for the port to function at full capacity.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App