HERC Orders Open Access Approval For 100 MW Renewable Supply
POWER & RENEWABLE ENERGY

HERC Orders Open Access Approval For 100 MW Renewable Supply

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements.

The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges.

Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases.

HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements. The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges. Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases. HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD, NaBFID Partner to Fund Rural Infrastructure

The National Bank for Agriculture and Rural Development (NABARD) and the National Bank for Financing Infrastructure and Development (NaBFID) have signed a Memorandum of Understanding (MoU) to collaborate on financing infrastructure projects with significant rural impact.The partnership combines NABARD’s expertise in rural and agricultural infrastructure with NaBFID’s specialised infrastructure financing capabilities. It will focus on joint financing, knowledge sharing and developing financing solutions to improve access to long-term, competitively priced capital for rural infrastructure an..

Next Story
Infrastructure Energy

Advait Energy Wins Rs 1.34 Billion MPPTCL Order

Advait Energy Transitions (AETL) has secured a Rs 1.34 billion turnkey contract from Madhya Pradesh Power Transmission Co. Ltd. (MPPTCL) for the design, manufacturing and supply of Emergency Restoration Systems (ERS) for 400kV, 220kV and 132kV EHV transmission lines.The order, received against Tender No. TR-23/2025 on August 25, 2026, will be executed over 18 months. The contract value, inclusive of taxes, covers the complete ERS along with the required accessories.Emergency Restoration Systems are used to restore transmission infrastructure following disruptions, helping maintain continuity a..

Next Story
Real Estate

Gradiant expands Coimbatore engineering centre

Gradiant has expanded its Global Engineering Center (GEC) in Coimbatore, more than doubling its engineering workforce from approximately 100 to over 200 professionals as it strengthens its global project execution capabilities.The expanded centre will bring together multidisciplinary expertise across process engineering, detailed design and project engineering, enabling the India team to take on greater responsibility for the engineering and design of Gradiant’s international projects.According to Govind Alagappan, COO, Gradiant, Coimbatore’s engineering talent and industrial heritage make..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement