HERC Orders Open Access Approval For 100 MW Renewable Supply
POWER & RENEWABLE ENERGY

HERC Orders Open Access Approval For 100 MW Renewable Supply

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements.

The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges.

Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases.

HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements. The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges. Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases. HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

Related Stories

Gold Stories

Next Story
Products

Interio by Godrej launches modular workplace solutions

Interio by Godrej has launched Workscapes, a modular workplace solutions category designed to help organisations configure and adapt workspaces to changing requirements. The portfolio combines mobile and compatible furniture and support elements that can be rearranged across different work modes without changes to fixed layouts.Workscapes includes Collaboration Tables, Privacy Solutions, Mobile Markerboards and Space Dividers, Power Solutions, Storage and Support Elements, Meeting and Presentation Tools, and Seating Elements. The range is designed for focused work, collaboration, informal disc..

Next Story
Infrastructure Urban

CAFE-III Gives Auto Industry Investment Clarity

The government’s new Corporate Average Fuel Economy (CAFE-III) norms have provided the automobile industry with a clearer framework for technology investments, according to industry representatives. The framework seeks to balance environmental objectives with flexibility for manufacturers while encouraging the adoption of flex-fuel vehicles and biofuels. Society of Indian Automobile Manufacturers (SIAM) President Shenu Agarwal said the five-year framework would give automakers greater predictability to plan investments and accelerate innovation. He said the regulation established annual targ..

Next Story
Infrastructure Energy

Mines Ministry to Auction Two Offshore Mineral Blocks in Andaman Sea

The Ministry of Mines will launch an auction of two offshore mineral blocks in the Andaman Sea on Thursday, seeking to unlock India’s offshore mineral potential and strengthen long-term mineral resource security. The blocks will be offered under a composite licence, which permits exploration and development activities in accordance with the applicable regulatory framework. The ministry said the auction was intended to encourage systematic exploration, attract investment and promote the use of advanced technologies for offshore mineral exploration and development. The initiative is also aimed..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code