+
HERC Orders Open Access Approval For 100 MW Renewable Supply
POWER & RENEWABLE ENERGY

HERC Orders Open Access Approval For 100 MW Renewable Supply

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements.

The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges.

Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases.

HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements. The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges. Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases. HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Emiza Expands Bhiwandi Fulfilment Capacity by 2.32 Lakh Sq Ft

Emiza, a leading third-party logistics (3PL) provider, has expanded its Mumbai operations with the launch of two new fulfilment facilities in Bhiwandi, adding a combined capacity of 2.32 lakh sq ft to its network.The new facilities, spread across 75,000 sq ft and 1,57,000 sq ft, mark Emiza’s fifth and sixth warehouses in the Mumbai region. The expansion strengthens the company’s fulfilment infrastructure in Western India amid the rapid growth of India’s digital commerce ecosystem.With increasing online consumption, wider product categories and rising customer expectations for faster deli..

Next Story
Infrastructure Urban

Ingersoll Rand Showcases Air Solutions for Semiconductor Sector

Ingersoll Rand will showcase its advanced compressed air solutions for India’s growing semiconductor ecosystem at SEMICON India 2026, scheduled from September 17–19 at Yashobhoomi, New Delhi.The company will display its portfolio of oil-free compressors, centrifugal compression technologies and advanced air treatment systems at Stall No. 1156, Hall No. 1. The solutions are designed to address the stringent air quality, reliability and efficiency requirements of semiconductor manufacturing applications.With India accelerating investments across semiconductor manufacturing, packaging, equipm..

Next Story
Infrastructure Energy

RECPDCL Transfers Musalgaon Transmission SPV to MSETCL

REC Power Development and Consultancy Limited (RECPDCL), a wholly owned subsidiary of REC Limited, has handed over Musalgaon Power Transmission Limited, a project-specific Special Purpose Vehicle (SPV), to Maharashtra State Electricity Transmission Company Limited (MSETCL).MSETCL emerged as the successful bidder through the Tariff-Based Competitive Bidding (TBCB) process conducted by RECPDCL, the Bid Process Coordinator, for developing Maharashtra’s intra-state transmission project on a Build, Own, Operate and Transfer (BOOT) basis.The SPV was handed over by Shri Ratnesh Kumar, General Manag..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code