Allahabad HC Grants Zero Period Waiver for Sunshine Trade Tower
Real Estate

Allahabad HC Grants Zero Period Waiver for Sunshine Trade Tower

The Allahabad High Court has granted a zero period waiver for the Sunshine Trade Tower project due to delays caused by incomplete road infrastructure. This waiver allows the project developers to extend the deadline without facing penalties, providing crucial relief as they address the ongoing construction issues.

Sunshine Trade Tower, a significant commercial development in Allahabad, faced delays primarily because the associated road infrastructure was not ready as initially promised. The developers had sought this waiver to avoid financial penalties and additional complications arising from the delay.

The court's decision underscores the challenges faced by real estate developers when external factors, such as infrastructure readiness, impact project timelines. By allowing the waiver, the court acknowledged the constraints beyond the developers control and provided a pragmatic solution to avoid unjust financial burdens.

This ruling is expected to influence similar cases where developers encounter unforeseen delays linked to municipal or infrastructural shortcomings. It highlights the need for better coordination between developers and local authorities to ensure that essential infrastructure is completed in tandem with construction projects.

The decision also reflects a growing trend towards judicial leniency in cases where developers face genuine difficulties due to factors outside their immediate control. This approach aims to balance the interests of developers with the need for timely project completion and regulatory compliance.

As the Sunshine Trade Tower project progresses, this waiver could provide the necessary breathing space to address remaining challenges and ensure successful project completion.

The Allahabad High Court has granted a zero period waiver for the Sunshine Trade Tower project due to delays caused by incomplete road infrastructure. This waiver allows the project developers to extend the deadline without facing penalties, providing crucial relief as they address the ongoing construction issues. Sunshine Trade Tower, a significant commercial development in Allahabad, faced delays primarily because the associated road infrastructure was not ready as initially promised. The developers had sought this waiver to avoid financial penalties and additional complications arising from the delay. The court's decision underscores the challenges faced by real estate developers when external factors, such as infrastructure readiness, impact project timelines. By allowing the waiver, the court acknowledged the constraints beyond the developers control and provided a pragmatic solution to avoid unjust financial burdens. This ruling is expected to influence similar cases where developers encounter unforeseen delays linked to municipal or infrastructural shortcomings. It highlights the need for better coordination between developers and local authorities to ensure that essential infrastructure is completed in tandem with construction projects. The decision also reflects a growing trend towards judicial leniency in cases where developers face genuine difficulties due to factors outside their immediate control. This approach aims to balance the interests of developers with the need for timely project completion and regulatory compliance. As the Sunshine Trade Tower project progresses, this waiver could provide the necessary breathing space to address remaining challenges and ensure successful project completion.

Next Story
Real Estate

DLF Returns to Mumbai with Premium Andheri Residential Project

Delhi-NCR based real estate major DLF announced its return to the Mumbai market on 17 July with the launch of its premium residential project, The WestPark, in Andheri. The first phase includes 416 apartments spread across four towers, with two towers launched on the announcement day. The company plans to invest over Rs 8 billion in the project and expects a topline exceeding Rs 20 billion from Phase 1.“We have launched two towers and, given the strong response, plan to unveil the remaining two towers ahead of schedule, within the next few days,” said Aakash Ohri, Joint Managing Director o..

Next Story
Infrastructure Urban

APCRDA Advances Net Zero Goal with IGBC Training for Officials

In a significant stride towards Andhra Pradesh’s Net Zero target by 2040 and the Swarna Andhra 2047 vision, the Andhra Pradesh Capital Region Development Authority (APCRDA), in partnership with the Indian Green Building Council (IGBC), conducted a high-level capacity-building programme for senior officials in Vijayawada on Friday.Held at a city hotel, the session saw the participation of over 50 senior APCRDA officials, including the Engineer-in-Chief, Chief Engineer (H&B), Director (Planning), Director (Environment), and heads of key departments. The training centred on IGBC’s Green B..

Next Story
Infrastructure Energy

Assam Solar Project Halted as Waaree EPC Contract Is Cancelled

Following the Assam government’s withdrawal from its proposed solar project, the Engineering, Procurement, and Construction (EPC) contract awarded to Waaree Renewable has been suspended. Waaree Group’s EPC division informed the stock exchange of this development through a regulatory filing.The Assam solar project was suspended due to funding challenges, which rendered the initiative unviable for the state government. Waaree Renewable Transmission Limited (RTL) explained that the Government of Assam has withdrawn the project’s funding via the Asian Development Bank (ADB) loan. Consequentl..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?