SCR Has 1,481 km Of Rail Projects Worth Rs 242.102 bn Under Way
ECONOMY & POLICY

SCR Has 1,481 km Of Rail Projects Worth Rs 242.102 bn Under Way

South Central Railway has set in motion 1,481 km of new-line, doubling and tripling projects at a cost of Rs 24,210.179 crore, equivalent to Rs 242.102 billion (bn), the zone's general manager Sanjay Kumar Srivastava told a meeting with Members of Parliament. The projects are under way across the zone and span constituencies in Telangana, Andhra Pradesh and Karnataka. The meeting at Rail Nilayam was attended by Union Minister of Coal and Mines G Kishan Reddy and 15 MPs.

Srivastava outlined the zone's performance in passenger services, freight loading, passenger amenities, station cleanliness and other initiatives, and said the SCR now comprises three divisions — Secunderabad, Hyderabad and Nanded — following a reorganisation in June. He said the restructuring had not affected progress and that the zone had achieved its targets and surpassed last year's performance. The official provided details of ongoing works and timelines.

40 railway stations in Telangana are being redeveloped at a cost of more than Rs 2,000 crore, or about Rs 20 bn, and four stations — Hi-Tech City, Begumpet, Karimnagar and Warangal — have already been commissioned under the Amrit Bharat Station Scheme while work progresses at the remainder. Since April the zone has introduced four pairs of new trains and five pairs of Amrit Bharat trains; 14 trains have been extended to different terminals, 56 trains have been given additional stoppages and 30 pairs have been regularised. The release said these measures are intended to enhance connectivity and passenger convenience.

MPs welcomed the initiatives and raised issues relating to construction of road underbridges and road overbridges, proposals for new railway lines, requests for additional stoppages and extensions of services, and calls for improved passenger amenities. They urged the SCR to expedite project execution to ensure completion within the targeted timelines. Srivastava said the zone would give due consideration to the suggestions while formulating proposals for new works and services.

South Central Railway has set in motion 1,481 km of new-line, doubling and tripling projects at a cost of Rs 24,210.179 crore, equivalent to Rs 242.102 billion (bn), the zone's general manager Sanjay Kumar Srivastava told a meeting with Members of Parliament. The projects are under way across the zone and span constituencies in Telangana, Andhra Pradesh and Karnataka. The meeting at Rail Nilayam was attended by Union Minister of Coal and Mines G Kishan Reddy and 15 MPs. Srivastava outlined the zone's performance in passenger services, freight loading, passenger amenities, station cleanliness and other initiatives, and said the SCR now comprises three divisions — Secunderabad, Hyderabad and Nanded — following a reorganisation in June. He said the restructuring had not affected progress and that the zone had achieved its targets and surpassed last year's performance. The official provided details of ongoing works and timelines. 40 railway stations in Telangana are being redeveloped at a cost of more than Rs 2,000 crore, or about Rs 20 bn, and four stations — Hi-Tech City, Begumpet, Karimnagar and Warangal — have already been commissioned under the Amrit Bharat Station Scheme while work progresses at the remainder. Since April the zone has introduced four pairs of new trains and five pairs of Amrit Bharat trains; 14 trains have been extended to different terminals, 56 trains have been given additional stoppages and 30 pairs have been regularised. The release said these measures are intended to enhance connectivity and passenger convenience. MPs welcomed the initiatives and raised issues relating to construction of road underbridges and road overbridges, proposals for new railway lines, requests for additional stoppages and extensions of services, and calls for improved passenger amenities. They urged the SCR to expedite project execution to ensure completion within the targeted timelines. Srivastava said the zone would give due consideration to the suggestions while formulating proposals for new works and services.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Modi Urges End-to-End Reforms for Infrastructure Projects

Prime Minister Narendra Modi on Tuesday called for continuous reforms across all stages of infrastructure project execution during the 53rd PRAGATI meeting. He asked ministries and state governments to adopt an end-to-end approach and a proactive work culture to ensure timely delivery. The meeting reviewed six key infrastructure projects in the railway, road and power sectors across nine states with a cumulative investment of Rs 300 billion (Rs 300 bn). Officials assessed projects on timelines, inter-agency coordination and resolution of pending issues. He said infrastructure projects should b..

Next Story
Infrastructure Transport

GMR Airports Plans US$2 bn Expansion In Delhi And Hyderabad

GMR Airports plans a US$2 billion (bn) expansion of facilities at New Delhi and Hyderabad as part of a major modernisation drive. Hyderabad’s upgraded airport will be able to accommodate about 80 million (mn) passengers a year, more than double its current annual volume of 34 mn fliers. The company is India’s largest airport operator by number of fliers annually, while rival Adani Airport Holdings Ltd is the biggest by number of airports and is reported to be looking to invest US$15 bn to boost passenger capacity over the next five years. Executives indicated the build-outs in New Delhi an..

Next Story
Infrastructure Transport

Mumbai Airport to Demolish Part of Terminal One From 15 January

Adani Group-operated Mumbai International Airport (MIAL) will begin partial demolition of the north section of Terminal one-B at Chatrapati Shivaji Maharaj International Airport from 15 January 2027, according to a letter to the civil aviation ministry. The operator has begun redistributing air traffic to Terminal two and to Navi Mumbai International Airport to facilitate the work. The airport, managed by Mumbai International Airport, currently has a capacity of over 50 million (mn) passengers and handles over 950 flight movements daily. Terminal one is nearly 80 years old and parts of it have..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement