+
When the Clause Bars Damages
ECONOMY & POLICY

When the Clause Bars Damages

In large-scale infrastructure and construction projects, delays are often an inevitable reality. To shield themselves from financial liabilities arising out of project prolongations, employers – particularly government entities and public-sector undertakings (PSUs) – frequently incorporate st...

In large-scale infrastructure and construction projects, delays are often an inevitable reality. To shield themselves from financial liabilities arising out of project prolongations, employers – particularly government entities and public-sector undertakings (PSUs) – frequently incorporate standard ‘No Damage for Delay’ or ‘No Liability’ clauses. These clauses aim to restrict the contractor's remedy solely to an extension of time (EOT), barring any monetary claims for extra overheads, idling costs or lost profits.Origin and relevanceUnderstanding the nature, enforceability and judicial treatment of these clauses under Indian contract and arbitration law is vital for both project owners and contractors. As observed by the Supreme Court of India in Northern Railway v. Sarvesh Chopra (citing Hudson’s Building and Engineering Contracts), the ‘no damage for delay’ clause originated in American jurisprudence, where the owner grants an extension of time for completion across various defined delays, including breaches of contract for which the owner would prima facie be liable, while specifying that an EOT is the contractor’s sole remedy. The Court held that ‘no damage’ clauses protect the owner from the late start or coordination claims due to other contractor delays that would otherwise arise.In standard-form government and institutional contracts, these provisions are typically drafted with categorical phrasing: “No claim in respect of compensation or otherwise...shall be admitted”; “No claim whatsoever will be entertained by the Railways on account of any delay or holdup...”; “...such failure or delay shall in no way affect or vitiate the contract... or entitle the Contractor to damages or compensation therefor”. Primarily designed to protect owners from coordination bottlenecks, delayed handovers and third-party interface issues, these clauses shift the entire financial risk of project prolongation onto the executing contractor.The Indian Contract ActThe fundamental challenge to ‘no damage’ clauses stems from whether parties can contract out of statutory damages. Their validity is tested against several mandatory provisions of the Indian Contract Act 1872, such as Section 23, according to which agreements are void if their object defeats the provisions of any law or is opposed to public policy. Indian courts have held that while individuals may waive rights enacted solely for private benefit, rights tied to public policy and statutory remedy schemes cannot be contracted away. In relevance, Section 28 of the Act says that agreements that absolutely restrict a party from enforcing their rights or extinguishing liabilities upon expiry of a specified period are void to that extent. Sections 55 and 73 provide the statutory framework governing the consequences of delay and breach of contract. While parties may, subject to applicable law, agree to allocate contractual risks and restrict particular remedies, a clause that seeks to completely exclude liability for the consequences of a party’s own breach may raise questions concerning its validity, scope and enforceability under the Indian Contract Act 1872. The effect of such an exclusion must, therefore, be determined having regard to the language of the clause, the nature of the breach, the parties’ contractual allocation of risk and the applicable statutory and judicial principles.Judicial interpretationsThe judicial interpretation surrounding ‘no damage for delay’ clauses has evolved through conflicting lines of precedent. Ramnath International Construction (P) Ltd v. Union of India and ONGC v. Wig Bros. Builders deal with scenarios when the contractor voluntarily agreed to an extension of time as the exclusive remedy. An arbitrator awarding damages contrary to the explicit contractual bar exceeds their jurisdiction.  A contrasting line of authority has focused on the distinction between a clause that restricts a departmental authority from entertaining a claim and a clause that extinguishes the substantive legal right of a contractor to seek damages before an independent adjudicatory forum. In Port of Calcutta v. Engineers-De-Space-Age and Asian Techs Ltd v. Union of India, the Supreme Court examined that the prohibitory clause binds only the departmental authorities from entertaining claims internally, but does not prohibit an independent arbitral tribunal from awarding damages for breach of contract.Another line of judicial reasoning examined whether a contractual provision that excludes compensation for employer-caused delay can operate consistently with the statutory framework of the Contract Act. Decisions, including Simplex Concrete Piles (India) Ltd v. Union of India and Delhi Jal Board v. V.K. Dewan, opined that contractual provisions that disentitle a contractor from claiming damages under Sections 55 and 73 defeat statutory intent and are void under Section 23 of the Contract Act for violating public policy.The issue is further complicated by the principle of prevention. Where the employer itself commits acts or omissions that prevent the contractor from performing within the stipulated period, the employer may not, in every circumstance, be permitted to rely mechanically upon the original completion date or contractual consequences arising from delay. The precise effect of the prevention principle, however, depends upon the contractual terms and the factual circumstances of the case. The presence of an EOT mechanism, waiver, undertaking, correspondence between the parties, acceptance of extensions or conduct indicating acquiescence may materially affect the contractor’s entitlement.In India, there is a trend towards construction contracts providing for alternate dispute resolution mechanisms, specifically arbitration. The issue that then arises is whether the arbitrator is bound by a clause that prohibits the parties for claiming damages in case of delay. It is established that the arbitral tribunal is a creature of the contract and is bound to decide disputes in accordance with substantive Indian law as per Section 28 of the Arbitration and Conciliation Act 1996. In MBL Infrastructures Ltd v. DMRC & Ircon International Ltd v. GPT-Rahee JV, the Delhi High Court held if a contractual term is found to violate statutory provisions, it is void ab initio, allowing tribunals to award damages for employer-attributable breaches despite the presence of exclusionary clauses. However, the recent decision in C&C Constructions Ltd v. Ircon International Ltd serves as an essential caution. In that case, the Supreme Court upheld an exclusion clause primarily because the contractor had signed undertakings waiving delay damages and had failed to challenge the validity of the clause under Sections 23 and 28 of the Contract Act during the initial proceedings before the High Court.In conclusionThe central question is not simply whether a ‘no damages for delay’ clause exists but rather what the clause legally excludes, whose delay caused the prolongation, whether the employer’s conduct amounts to a breach or prevention, whether the contractor has waived or otherwise relinquished its rights, and whether the exclusion is enforceable under the Indian Contract Act 1872 and the Arbitration & Conciliation Act 1996.About the author:Ronak Desai is a construction lawyer and heads International Construction Law Offices, Mumbai (ICLO). Email: rd@constructionlawoffices.com

Related Stories

Gold Stories

Next Story
Products

Colour, Wood-Finish Profiles Gain Ground in Home Design

Colour and wood-finish profiles are gaining traction in residential fenestration as homeowners increasingly seek doors and windows that complement interior and exterior design, according to Durakraft Extrusions.The company said traditional white profiles are increasingly being complemented by a wider range of colours, textures and finishes as homeowners and designers place greater emphasis on personalised interiors.Wood finishes are being used to introduce a natural and warm appearance, while shades such as anthracite grey, black, walnut, mahogany and Golden Oak offer options to coordinate fen..

Next Story
Building Material

Hard Worker Wins Three Honours at Kyoorius Design Awards

The Ramco Cements Limited’s construction chemicals brand, Hard Worker, has won three honours at the Kyoorius Design Awards 2026, including the Grand Prix – Grey Elephant in the Design in Action category.The brand also secured two Blue Elephant honours, one for Design in Action and another for Packaging, recognising the design approach behind its brand identity and packaging.Launched in 2025, Hard Worker entered the construction chemicals segment with the brand promise, “Hard-working products for hardworking people.” Its visual identity uses animals and birds to represent product benefi..

Next Story
Infrastructure Transport

Kopri-Patni Creek Bridge to Improve Thane-Navi Mumbai Connectivity

Road connectivity between Thane and Navi Mumbai is set to receive a boost with the proposed six-lane Kopri-Patni Creek Bridge, which will provide a new route across Thane Creek. The project is intended to create a direct link between the two urban centres and add capacity to the region’s road network. The bridge will connect Kopri in Thane East with Patni in Navi Mumbai. It will begin at Mith Bandar Road in Kopri, about 750 metres from Thane railway station, cross Thane Creek and land near Airoli Knowledge City Road in Navi Mumbai. The project has advanced with Akshya Infra Projects emerging..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code