GMLR Phase 1 Flyover To Open By 2026, Says BMC
ROADS & HIGHWAYS

GMLR Phase 1 Flyover To Open By 2026, Says BMC

The first phase of the Goregaon–Mulund Link Road (GMLR), an ambitious project being executed by the Brihanmumbai Municipal Corporation (BMC), is expected to become operational by 2026. The 12.2-kilometre high-speed corridor will include underground tunnels, bridges and traffic interchanges, ultimately connecting Goregaon in the western suburbs with Mulund in the eastern suburbs. The overall project has been divided into four phases.

In the first phase, a 1.2-kilometre flyover will begin near the Dindoshi court and descend at Sanjay Gandhi National Park (SGNP), from where motorists will be able to enter the twin tunnels directly once they are completed. The flyover will feature six vehicular lanes and an elevated rotary, or circular intersection, constructed on a raised platform. Walkways will also be added on both sides along with deck slabs.

The bridge will give motorists direct access between Dindoshi and SGNP, and once the two underground tunnels are ready, vehicles will be able to move straight from the flyover into the tunnel system. Tunnel boring is scheduled to begin in 2026, with civil works expected to take around one year.

The flyover will rest on 31 pillars, of which 27 have already been erected. Work on the remaining four pillars is under way. The west-bound arm is slated for completion by January 2026, while the east-bound arm is targeted for completion by April 2026. Ancillary works will follow, with the BMC aiming to open the flyover by May 2026.

“This flyover will mark the end of the first stage of the project. In the long run, we aim to connect the GMLR with the Versova–Bhayander Coastal Road. By 2028, commuting across the suburban belt will become significantly easier, as these two projects will be absolute gamechangers,” said Abhijit Bangar, Additional Municipal Commissioner (Projects).

The total cost of the GMLR project is Rs 140 billion, and the BMC has set a deadline of 2028 for full completion.

The first phase of the Goregaon–Mulund Link Road (GMLR), an ambitious project being executed by the Brihanmumbai Municipal Corporation (BMC), is expected to become operational by 2026. The 12.2-kilometre high-speed corridor will include underground tunnels, bridges and traffic interchanges, ultimately connecting Goregaon in the western suburbs with Mulund in the eastern suburbs. The overall project has been divided into four phases. In the first phase, a 1.2-kilometre flyover will begin near the Dindoshi court and descend at Sanjay Gandhi National Park (SGNP), from where motorists will be able to enter the twin tunnels directly once they are completed. The flyover will feature six vehicular lanes and an elevated rotary, or circular intersection, constructed on a raised platform. Walkways will also be added on both sides along with deck slabs. The bridge will give motorists direct access between Dindoshi and SGNP, and once the two underground tunnels are ready, vehicles will be able to move straight from the flyover into the tunnel system. Tunnel boring is scheduled to begin in 2026, with civil works expected to take around one year. The flyover will rest on 31 pillars, of which 27 have already been erected. Work on the remaining four pillars is under way. The west-bound arm is slated for completion by January 2026, while the east-bound arm is targeted for completion by April 2026. Ancillary works will follow, with the BMC aiming to open the flyover by May 2026. “This flyover will mark the end of the first stage of the project. In the long run, we aim to connect the GMLR with the Versova–Bhayander Coastal Road. By 2028, commuting across the suburban belt will become significantly easier, as these two projects will be absolute gamechangers,” said Abhijit Bangar, Additional Municipal Commissioner (Projects). The total cost of the GMLR project is Rs 140 billion, and the BMC has set a deadline of 2028 for full completion.

Next Story
Real Estate

Modon, Related, Panepinto form JV for Harborside 4 in Jersey City

Abu Dhabi-based Modon Holding PSC has formed a joint venture with US real estate major Related Companies and Jersey City-based Panepinto Properties to develop Harborside 4, a 54-storey luxury residential tower on a prime waterfront site in downtown Jersey City, New Jersey.Under the partnership, Modon will hold a majority equity stake alongside Related and Panepinto, marking another step in the group’s strategy to scale and diversify its global real estate portfolio. The project will be developed on one of the last remaining premium waterfront parcels in the city.Designed by Handel Architects..

Next Story
Infrastructure Urban

P+Ex and Post-Tensioning Institute partner to drive sustainability

P+Ex, the Center of Excellence for Concrete Preservation and Service Life Extension, has announced a strategic partnership with the Post-Tensioning Institute (PTI) aimed at advancing sustainability, durability, and resilience in the built environment.The collaboration brings together P+Ex’s expertise in concrete preservation, repair, and service life extension with PTI’s global leadership in post-tensioning technology. Through this alliance, the two organisations will work to advance best practices in durability-focused design for new structures, while also promoting effective repair, reha..

Next Story
Infrastructure Energy

India’s Largest 2,000 MW Subansiri Hydro Project Turns Operational

India’s largest hydropower project, the 2,000 MW Subansiri Lower Hydroelectric Project, has finally become operational with the commissioning of its first unit, marking a major milestone after nearly 20 years of development marked by delays, protests and cost escalation.The 250 MW Unit-2 of the project, located on the Subansiri River at Gerukamukh on the Assam–Arunachal Pradesh border, was virtually inaugurated from New Delhi by Union Minister of Power Manohar Lal Khattar. The event was attended by Pankaj Agarwal, Secretary (Power), and Bhupender Gupta, Chairman and Managing Director, Nati..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App