GMLR Phase 1 Flyover To Open By 2026, Says BMC
ROADS & HIGHWAYS

GMLR Phase 1 Flyover To Open By 2026, Says BMC

The first phase of the Goregaon–Mulund Link Road (GMLR), an ambitious project being executed by the Brihanmumbai Municipal Corporation (BMC), is expected to become operational by 2026. The 12.2-kilometre high-speed corridor will include underground tunnels, bridges and traffic interchanges, ultimately connecting Goregaon in the western suburbs with Mulund in the eastern suburbs. The overall project has been divided into four phases.

In the first phase, a 1.2-kilometre flyover will begin near the Dindoshi court and descend at Sanjay Gandhi National Park (SGNP), from where motorists will be able to enter the twin tunnels directly once they are completed. The flyover will feature six vehicular lanes and an elevated rotary, or circular intersection, constructed on a raised platform. Walkways will also be added on both sides along with deck slabs.

The bridge will give motorists direct access between Dindoshi and SGNP, and once the two underground tunnels are ready, vehicles will be able to move straight from the flyover into the tunnel system. Tunnel boring is scheduled to begin in 2026, with civil works expected to take around one year.

The flyover will rest on 31 pillars, of which 27 have already been erected. Work on the remaining four pillars is under way. The west-bound arm is slated for completion by January 2026, while the east-bound arm is targeted for completion by April 2026. Ancillary works will follow, with the BMC aiming to open the flyover by May 2026.

“This flyover will mark the end of the first stage of the project. In the long run, we aim to connect the GMLR with the Versova–Bhayander Coastal Road. By 2028, commuting across the suburban belt will become significantly easier, as these two projects will be absolute gamechangers,” said Abhijit Bangar, Additional Municipal Commissioner (Projects).

The total cost of the GMLR project is Rs 140 billion, and the BMC has set a deadline of 2028 for full completion.

The first phase of the Goregaon–Mulund Link Road (GMLR), an ambitious project being executed by the Brihanmumbai Municipal Corporation (BMC), is expected to become operational by 2026. The 12.2-kilometre high-speed corridor will include underground tunnels, bridges and traffic interchanges, ultimately connecting Goregaon in the western suburbs with Mulund in the eastern suburbs. The overall project has been divided into four phases. In the first phase, a 1.2-kilometre flyover will begin near the Dindoshi court and descend at Sanjay Gandhi National Park (SGNP), from where motorists will be able to enter the twin tunnels directly once they are completed. The flyover will feature six vehicular lanes and an elevated rotary, or circular intersection, constructed on a raised platform. Walkways will also be added on both sides along with deck slabs. The bridge will give motorists direct access between Dindoshi and SGNP, and once the two underground tunnels are ready, vehicles will be able to move straight from the flyover into the tunnel system. Tunnel boring is scheduled to begin in 2026, with civil works expected to take around one year. The flyover will rest on 31 pillars, of which 27 have already been erected. Work on the remaining four pillars is under way. The west-bound arm is slated for completion by January 2026, while the east-bound arm is targeted for completion by April 2026. Ancillary works will follow, with the BMC aiming to open the flyover by May 2026. “This flyover will mark the end of the first stage of the project. In the long run, we aim to connect the GMLR with the Versova–Bhayander Coastal Road. By 2028, commuting across the suburban belt will become significantly easier, as these two projects will be absolute gamechangers,” said Abhijit Bangar, Additional Municipal Commissioner (Projects). The total cost of the GMLR project is Rs 140 billion, and the BMC has set a deadline of 2028 for full completion.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App