Land Acquisition And Forest Clearance Stall NH 169 Widening
ROADS & HIGHWAYS

Land Acquisition And Forest Clearance Stall NH 169 Widening

The widening of a 45 kilometre section of National Highway 169 that links Mangaluru with Solapur has been delayed by land acquisition and forest clearance issues. The Rs 11,370 mn project to upgrade the Bikarnakatte to Sanoor section between Mangaluru and Karkala began more than five years ago and remains incomplete. A feasibility study was initiated in 2014 and the National Highways Authority of India finalised acquisition plans in 2018.

The scheme aims to improve connectivity and ease congestion, with two bypasses at Gurupura and Moodbidri expected to relieve town traffic. The upgrade should also enhance access to educational institutions, tourist sites and pilgrimage centres such as Dharmasthala and Sringeri and support local economic activity.

Compensation disputes have been identified as the main obstacle, with work stalled at Padavu village for two and a half kilometres and an 830-metre stretch at Kanthavara awaiting forest clearance. Representatives of a landowners action committee said the authority owes Rs 2,860 mn in compensation and that arbitration, appeals and court proceedings have delayed payments for about two years. They cited Central Vigilance Commission guidelines that had envisaged payments of Rs 0.35 mn and noted a guideline value at Padavu of about Rs 1.0117 mn in 2020.

Work on other stretches has progressed, with the Vamanjoor to Baiturli section advancing rapidly and retaining structures and realignment works near temples under way to improve safety. Dense Bituminous Macadam has been completed for 32.65 kilometres of the 45 kilometre corridor and the Moodbidri bypass is in progress. A two and a half kilometre section at Paduva was descoped owing to contractor delay, while minor land issues have slowed realignment at Yedapadavu. Project managers are targeting completion of ongoing works by June ahead of the monsoon and locals have urged timely delivery to reduce landslide risk from unscientific hill cutting.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The widening of a 45 kilometre section of National Highway 169 that links Mangaluru with Solapur has been delayed by land acquisition and forest clearance issues. The Rs 11,370 mn project to upgrade the Bikarnakatte to Sanoor section between Mangaluru and Karkala began more than five years ago and remains incomplete. A feasibility study was initiated in 2014 and the National Highways Authority of India finalised acquisition plans in 2018. The scheme aims to improve connectivity and ease congestion, with two bypasses at Gurupura and Moodbidri expected to relieve town traffic. The upgrade should also enhance access to educational institutions, tourist sites and pilgrimage centres such as Dharmasthala and Sringeri and support local economic activity. Compensation disputes have been identified as the main obstacle, with work stalled at Padavu village for two and a half kilometres and an 830-metre stretch at Kanthavara awaiting forest clearance. Representatives of a landowners action committee said the authority owes Rs 2,860 mn in compensation and that arbitration, appeals and court proceedings have delayed payments for about two years. They cited Central Vigilance Commission guidelines that had envisaged payments of Rs 0.35 mn and noted a guideline value at Padavu of about Rs 1.0117 mn in 2020. Work on other stretches has progressed, with the Vamanjoor to Baiturli section advancing rapidly and retaining structures and realignment works near temples under way to improve safety. Dense Bituminous Macadam has been completed for 32.65 kilometres of the 45 kilometre corridor and the Moodbidri bypass is in progress. A two and a half kilometre section at Paduva was descoped owing to contractor delay, while minor land issues have slowed realignment at Yedapadavu. Project managers are targeting completion of ongoing works by June ahead of the monsoon and locals have urged timely delivery to reduce landslide risk from unscientific hill cutting.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement