Top NFR Official Reviews Jiribam-Imphal Railway Progress
ROADS & HIGHWAYS

Top NFR Official Reviews Jiribam-Imphal Railway Progress

A senior official of Northeast Frontier Railway reviewed progress in the under-construction sections of the 110.625 km Jiribam?Imphal railway line to ensure timely completion of the strategic link that will provide direct rail connectivity to Manipur's capital Imphal. The project is described as one of the most challenging railway infrastructure endeavours in the Northeast, traversing difficult hilly terrain and requiring extensive tunnelling and bridge construction. The review follows ongoing phased execution across multiple sections of the alignment.

General Manager (Construction) Ashish Bansal conducted an inspection of the Jiribam?Khongsang, Khongsang?Awangkhul and Awangkhul?Imphal sections and reviewed the status of key construction activities along the alignment. The inspection included assessment of critical infrastructure works and logistical preparedness ahead of a Commission of Railway Safety inspection scheduled for October. The review sought to identify bottlenecks and prioritise remedial actions to maintain momentum on works.

He inspected tunnel numbers 28 and 12 and reviewed tunnelling progress across the project, with particular attention to geological challenges and the use of advanced construction techniques. The General Manager emphasised maintaining the highest standards of safety, construction quality and timely execution while directing teams to monitor works closely and resolve issues promptly. Officials were instructed to coordinate closely with contractors and suppliers to ensure material and manpower readiness for upcoming schedules.

The alignment features 54 tunnels with a cumulative length of approximately 66.47 km and includes 15 major bridges and 116 minor bridges, among them bridge number 164 at Noney with a pier height of 141 metres that will be the tallest structure on the route. The tunnelling works across complex geological formations are being completed with stringent safety and quality measures. There are 11 railway stations planned along the line and phased commissioning has seen the Jiribam?Vangaichungpao section opened in February 2017 and the Vangaichungpao?Khongsang section opened in September 2022. Work on remaining sections continues in a phased manner towards final completion.

A senior official of Northeast Frontier Railway reviewed progress in the under-construction sections of the 110.625 km Jiribam?Imphal railway line to ensure timely completion of the strategic link that will provide direct rail connectivity to Manipur's capital Imphal. The project is described as one of the most challenging railway infrastructure endeavours in the Northeast, traversing difficult hilly terrain and requiring extensive tunnelling and bridge construction. The review follows ongoing phased execution across multiple sections of the alignment. General Manager (Construction) Ashish Bansal conducted an inspection of the Jiribam?Khongsang, Khongsang?Awangkhul and Awangkhul?Imphal sections and reviewed the status of key construction activities along the alignment. The inspection included assessment of critical infrastructure works and logistical preparedness ahead of a Commission of Railway Safety inspection scheduled for October. The review sought to identify bottlenecks and prioritise remedial actions to maintain momentum on works. He inspected tunnel numbers 28 and 12 and reviewed tunnelling progress across the project, with particular attention to geological challenges and the use of advanced construction techniques. The General Manager emphasised maintaining the highest standards of safety, construction quality and timely execution while directing teams to monitor works closely and resolve issues promptly. Officials were instructed to coordinate closely with contractors and suppliers to ensure material and manpower readiness for upcoming schedules. The alignment features 54 tunnels with a cumulative length of approximately 66.47 km and includes 15 major bridges and 116 minor bridges, among them bridge number 164 at Noney with a pier height of 141 metres that will be the tallest structure on the route. The tunnelling works across complex geological formations are being completed with stringent safety and quality measures. There are 11 railway stations planned along the line and phased commissioning has seen the Jiribam?Vangaichungpao section opened in February 2017 and the Vangaichungpao?Khongsang section opened in September 2022. Work on remaining sections continues in a phased manner towards final completion.

Related Stories

Gold Stories

Next Story
Equipment

Enerpac launches battery and diesel-powered split-flow pumps

Enerpac has introduced two split-flow pump series for multi-point lifting and skidding applications, particularly at remote industrial sites and locations with limited access to conventional power sources.The new SFP-B Series is battery-powered, while the SFP-D Series runs on diesel. Both operate at pressures of up to 700 bar and are designed to simplify equipment setup and provide greater control during lifting operations.The SFP-B Series offers up to 75 minutes of runtime at full capacity and has four outlets for multi-point lifting. Its 150-litre oil reservoir supports demanding application..

Next Story
Infrastructure Urban

Electromech Infraprojects Files DRHP for Rs 3.26 Billion IPO

Electromech Infraprojects has filed its Draft Red Herring Prospectus (DRHP) with the Securities and Exchange Board of India (SEBI) for a proposed initial public offering (IPO). The offering comprises a fresh issue of equity shares aggregating up to Rs 3.26 billion and an offer for sale of up to 1.89 million equity shares by existing shareholders. The shares have a face value of Rs 5 each.The Mumbai-based company provides mechanical, electrical and plumbing (MEP) solutions for data centres, Global Capability Centres (GCCs), and commercial and industrial projects. Its services cover technical de..

Next Story
Real Estate

Dubai South Home Sales Rise 27% Above 2025 Total: Anarock

Dubai South recorded 12,428 residential property transactions between January and August 2026, surpassing the 9,788 transactions registered during the whole of 2025 by 27 per cent, according to Anarock Research's Dubai South Residential Micro-Market Report. Residential sales value reached AED 15.9 billion during the eight-month period, representing 81 per cent of the AED 19.6 billion recorded in 2025.The report highlights significant growth in Dubai South's residential market, with annual sales value increasing from AED 720 million in 2020 to AED 19.6 billion in 2025. Transaction volumes also ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code